减轻阿尔及利亚社交活动延误主要原因的措施

IF 0.6 Q4 ENGINEERING, CIVIL Civil and Environmental Engineering Reports Pub Date : 2023-09-08 DOI:10.59440/ceer/172022
Zemra Rachid
{"title":"减轻阿尔及利亚社交活动延误主要原因的措施","authors":"Zemra Rachid","doi":"10.59440/ceer/172022","DOIUrl":null,"url":null,"abstract":"Social housing in Algeria is carried out with state budget funds in order to eliminate social inequalities and guarantee a decent life to the citizen. However, delays have been observed in the realization. This study aims to examine the main causes and develop guidelines to effectively mitigate delays. Through an in-depth analysis of the literature and formal interviews on the topic of potential risks with construction experts, a list of 67 delay factors was identified. Data was collected through an online questionnaire via Google Forms and semi-structured interviews of a sample professionals established in Algeria. A total of 59 valid responses were analyzed and classified by SPSS software. The results indicate that the 5 most critical causes are: \"Delay in payment\", \"Slow change orders in extra works\", \"Ineffective planning and scheduling\", \"Slow change orders in extra quantities\", and \"Difficulties in financing the project by contractor\". Though, the correct implementation of the measures suggested by this study allows government authorities and professionals to deal with the 10 most critical causes that have favored the occurrence of delays in order to successfully implement similar construction projects.","PeriodicalId":54121,"journal":{"name":"Civil and Environmental Engineering Reports","volume":"24 1","pages":"0"},"PeriodicalIF":0.6000,"publicationDate":"2023-09-08","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Measures To Mitigate The Main Causes Of Social Hoising Delays In Algeria\",\"authors\":\"Zemra Rachid\",\"doi\":\"10.59440/ceer/172022\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"Social housing in Algeria is carried out with state budget funds in order to eliminate social inequalities and guarantee a decent life to the citizen. However, delays have been observed in the realization. This study aims to examine the main causes and develop guidelines to effectively mitigate delays. Through an in-depth analysis of the literature and formal interviews on the topic of potential risks with construction experts, a list of 67 delay factors was identified. Data was collected through an online questionnaire via Google Forms and semi-structured interviews of a sample professionals established in Algeria. A total of 59 valid responses were analyzed and classified by SPSS software. The results indicate that the 5 most critical causes are: \\\"Delay in payment\\\", \\\"Slow change orders in extra works\\\", \\\"Ineffective planning and scheduling\\\", \\\"Slow change orders in extra quantities\\\", and \\\"Difficulties in financing the project by contractor\\\". Though, the correct implementation of the measures suggested by this study allows government authorities and professionals to deal with the 10 most critical causes that have favored the occurrence of delays in order to successfully implement similar construction projects.\",\"PeriodicalId\":54121,\"journal\":{\"name\":\"Civil and Environmental Engineering Reports\",\"volume\":\"24 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.6000,\"publicationDate\":\"2023-09-08\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Civil and Environmental Engineering Reports\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.59440/ceer/172022\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"Q4\",\"JCRName\":\"ENGINEERING, CIVIL\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Civil and Environmental Engineering Reports","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.59440/ceer/172022","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"Q4","JCRName":"ENGINEERING, CIVIL","Score":null,"Total":0}
引用次数: 0

摘要

阿尔及利亚的社会住房是由国家预算资金提供的,目的是消除社会不平等,保证公民过上体面的生活。然而,在实现过程中观察到延迟。本研究旨在检查主要原因,并制定有效减轻延误的指导方针。通过对文献的深入分析和对建筑专家潜在风险主题的正式访谈,我们确定了67个延迟因素。数据是通过谷歌表格的在线问卷和对在阿尔及利亚建立的样本专业人员的半结构化访谈收集的。采用SPSS软件对59份有效问卷进行分析和分类。研究结果表明,最关键的5个原因分别是:“付款延迟”、“额外工程变更订单慢”、“计划和调度无效”、“额外数量变更订单慢”和“承包商融资困难”。尽管如此,正确实施本研究建议的措施可以让政府当局和专业人士处理10个最关键的原因,这些原因有利于延迟的发生,以便成功实施类似的建设项目。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
查看原文
分享 分享
微信好友 朋友圈 QQ好友 复制链接
本刊更多论文
Measures To Mitigate The Main Causes Of Social Hoising Delays In Algeria
Social housing in Algeria is carried out with state budget funds in order to eliminate social inequalities and guarantee a decent life to the citizen. However, delays have been observed in the realization. This study aims to examine the main causes and develop guidelines to effectively mitigate delays. Through an in-depth analysis of the literature and formal interviews on the topic of potential risks with construction experts, a list of 67 delay factors was identified. Data was collected through an online questionnaire via Google Forms and semi-structured interviews of a sample professionals established in Algeria. A total of 59 valid responses were analyzed and classified by SPSS software. The results indicate that the 5 most critical causes are: "Delay in payment", "Slow change orders in extra works", "Ineffective planning and scheduling", "Slow change orders in extra quantities", and "Difficulties in financing the project by contractor". Though, the correct implementation of the measures suggested by this study allows government authorities and professionals to deal with the 10 most critical causes that have favored the occurrence of delays in order to successfully implement similar construction projects.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
14.30%
发文量
40
审稿时长
52 weeks
期刊最新文献
Comparison of the Use of Renewable Energy Sources (Res) by Poland and Latvia in the Perspective of the Environmental Objectives Set by the European Union Interlevel Connections as a Way to Increase the Ventilation Efficiency of a Mine Ventilation Network - a Case Study Flexural Buckling Resistance of Stiffeners Reinforcing Wall of a Steel Silo Short- term Influence of Glyphosate on Microorganisms in Backyard Compost Ozonation in Wastewater Disinfection
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
现在去查看 取消
×
提示
确定
0
微信
客服QQ
Book学术公众号 扫码关注我们
反馈
×
意见反馈
请填写您的意见或建议
请填写您的手机或邮箱
已复制链接
已复制链接
快去分享给好友吧!
我知道了
×
扫码分享
扫码分享
Book学术官方微信
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术
文献互助 智能选刊 最新文献 互助须知 联系我们:info@booksci.cn
Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。
Copyright © 2023 Book学术 All rights reserved.
ghs 京公网安备 11010802042870号 京ICP备2023020795号-1