用帕累托图方法对渠首工程和西贝朗主干渠改造工程进行项目进度分析 范围灌溉现代化项目(RIMP) Jatitujuh 区 Majalengka 县

A. Hidayat, Lia Laila Nurjamilah, Erni Sari Lombun Taruan
{"title":"用帕累托图方法对渠首工程和西贝朗主干渠改造工程进行项目进度分析 范围灌溉现代化项目(RIMP) Jatitujuh 区 Majalengka 县","authors":"A. Hidayat, Lia Laila Nurjamilah, Erni Sari Lombun Taruan","doi":"10.31949/stima.v7i0.884","DOIUrl":null,"url":null,"abstract":"Project scheduling has an important role in ensuring smooth project implementation and achieving the desired project objectives. In this context, the project scheduling analysis of the Rentang Headworks and Cipelang Main Canal Upgrading Works Rentang Irrigation Modernization Project (RIMP) in Jatitujuh District, Majalengka Regency is important to ensure the efficiency and effectiveness of project implementation. The Pareto diagram method is used in this analysis to identify and address key issues that may arise during project implementation. This research aims to improve the scheduling of the RIMP project by using the Pareto diagram method to increase the efficiency of time, cost, and resources. The results of the analysis show that the critical factors affecting the scheduling of the RIMP project are delays in material procurement, lack of coordination between related parties, and changes in demand from stakeholders. In the Pareto diagram, these problems are placed on the Y-axis and ranked in order of importance. After identifying the main problems, specific improvement measures were proposed to address each problem. Measures such as improving material procurement, enhancing coordination between relevant parties, and devising a more structured change request mechanism can help reduce delays and improve project scheduling efficiency. Using the Pareto diagram method, this RIMP project scheduling analysis provides a clear view of the key issues affecting project execution. The results of this analysis can be used by the project team to make better decisions in project planning and execution, with the hope of improving the efficiency and success of the project.","PeriodicalId":161203,"journal":{"name":"SEMINAR TEKNOLOGI MAJALENGKA (STIMA)","volume":"78 3 1","pages":""},"PeriodicalIF":0.0000,"publicationDate":"2023-11-07","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Analisa Penjadwalan Proyek Rentang Headworks And Cipelang Main Canal Upgrading Works Rentang Irrigation Modernization Project (RIMP) Dengan Metode Diagram Pareto Kecamatan Jatitujuh Kabupaten Majalengka\",\"authors\":\"A. Hidayat, Lia Laila Nurjamilah, Erni Sari Lombun Taruan\",\"doi\":\"10.31949/stima.v7i0.884\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"Project scheduling has an important role in ensuring smooth project implementation and achieving the desired project objectives. In this context, the project scheduling analysis of the Rentang Headworks and Cipelang Main Canal Upgrading Works Rentang Irrigation Modernization Project (RIMP) in Jatitujuh District, Majalengka Regency is important to ensure the efficiency and effectiveness of project implementation. The Pareto diagram method is used in this analysis to identify and address key issues that may arise during project implementation. This research aims to improve the scheduling of the RIMP project by using the Pareto diagram method to increase the efficiency of time, cost, and resources. The results of the analysis show that the critical factors affecting the scheduling of the RIMP project are delays in material procurement, lack of coordination between related parties, and changes in demand from stakeholders. In the Pareto diagram, these problems are placed on the Y-axis and ranked in order of importance. After identifying the main problems, specific improvement measures were proposed to address each problem. Measures such as improving material procurement, enhancing coordination between relevant parties, and devising a more structured change request mechanism can help reduce delays and improve project scheduling efficiency. Using the Pareto diagram method, this RIMP project scheduling analysis provides a clear view of the key issues affecting project execution. The results of this analysis can be used by the project team to make better decisions in project planning and execution, with the hope of improving the efficiency and success of the project.\",\"PeriodicalId\":161203,\"journal\":{\"name\":\"SEMINAR TEKNOLOGI MAJALENGKA (STIMA)\",\"volume\":\"78 3 1\",\"pages\":\"\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2023-11-07\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"SEMINAR TEKNOLOGI MAJALENGKA (STIMA)\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.31949/stima.v7i0.884\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"SEMINAR TEKNOLOGI MAJALENGKA (STIMA)","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.31949/stima.v7i0.884","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

摘要

项目进度安排在确保项目顺利实施和实现预期项目目标方面发挥着重要作用。在这种情况下,对 Majalengka 县 Jatitujuh 区 Rentang Headworks 和 Cipelang Main Canal 升级工程 Rentang 灌溉现代化项目(RIMP)进行项目进度分析,对于确保项目实施的效率和效果非常重要。本分析采用了帕累托图法,以确定并解决项目实施过程中可能出现的关键问题。本研究旨在利用帕累托图法改进 RIMP 项目的时间安排,以提高时间、成本和资源的效率。分析结果表明,影响 RIMP 项目进度安排的关键因素是材料采购延迟、相关方之间缺乏协调以及利益相关方需求的变化。在帕累托图表中,这些问题被放在 Y 轴上,并按重要性排序。在确定主要问题后,针对每个问题提出了具体的改进措施。改进材料采购、加强相关各方之间的协调、设计更有条理的变更申请机制等措施有助于减少延误,提高项目进度安排效率。通过使用帕累托图法,本 RIMP 项目进度分析可清晰地了解影响项目执行的关键问题。项目团队可利用分析结果,在项目规划和执行过程中做出更好的决策,从而提高项目的效率和成功率。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
查看原文
分享 分享
微信好友 朋友圈 QQ好友 复制链接
本刊更多论文
Analisa Penjadwalan Proyek Rentang Headworks And Cipelang Main Canal Upgrading Works Rentang Irrigation Modernization Project (RIMP) Dengan Metode Diagram Pareto Kecamatan Jatitujuh Kabupaten Majalengka
Project scheduling has an important role in ensuring smooth project implementation and achieving the desired project objectives. In this context, the project scheduling analysis of the Rentang Headworks and Cipelang Main Canal Upgrading Works Rentang Irrigation Modernization Project (RIMP) in Jatitujuh District, Majalengka Regency is important to ensure the efficiency and effectiveness of project implementation. The Pareto diagram method is used in this analysis to identify and address key issues that may arise during project implementation. This research aims to improve the scheduling of the RIMP project by using the Pareto diagram method to increase the efficiency of time, cost, and resources. The results of the analysis show that the critical factors affecting the scheduling of the RIMP project are delays in material procurement, lack of coordination between related parties, and changes in demand from stakeholders. In the Pareto diagram, these problems are placed on the Y-axis and ranked in order of importance. After identifying the main problems, specific improvement measures were proposed to address each problem. Measures such as improving material procurement, enhancing coordination between relevant parties, and devising a more structured change request mechanism can help reduce delays and improve project scheduling efficiency. Using the Pareto diagram method, this RIMP project scheduling analysis provides a clear view of the key issues affecting project execution. The results of this analysis can be used by the project team to make better decisions in project planning and execution, with the hope of improving the efficiency and success of the project.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
期刊最新文献
PEMBUATAN PART RING RAINFORCEMENT MENGGUNAKAN MESIN PRESS STAMPING CHIN FONG 110 SISTEM INFORMASI PENGOLAHAN DATA ABSENSI PEGAWAI KANTOR BALAI KB KECAMATAN PANYINGKIRAN BERBASIS WEB DAN ANDROID Penentuan Waktu Baku dengan Metode Stopwacth Time Study Studi Kasus Depot Air Syam STUDI KELAYAKAN SIFAT – SIFAT AGREGAT UNTUK CAMPURAN BETON TERHADAP NILAI KUAT TEKAN BETON DI PROYEK REKONSTRUKSI ATAU PENINGKATAN KAPASITAS STRUKTUR JALAN KADUT – SP. GUNUNGLARANG TONGGOH KEC. BANTARUJEG KAB. MAJALENGKA Metode Pelaksanaan Pekerjaan Dinding Penahan Tanah (Retaining Wall) Pada Proyek Preservasi Jalan Cirebon - Palimanan - Sumedang (Studi Kasus : Longsoran Km.68+500 Kabupaten Sumedang)
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
现在去查看 取消
×
提示
确定
0
微信
客服QQ
Book学术公众号 扫码关注我们
反馈
×
意见反馈
请填写您的意见或建议
请填写您的手机或邮箱
已复制链接
已复制链接
快去分享给好友吧!
我知道了
×
扫码分享
扫码分享
Book学术官方微信
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术
文献互助 智能选刊 最新文献 互助须知 联系我们:info@booksci.cn
Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。
Copyright © 2023 Book学术 All rights reserved.
ghs 京公网安备 11010802042870号 京ICP备2023020795号-1