研究尼泊尔农村市政当局推动的建筑项目超时的原因和影响

IF 1.5 4区 社会学 Q2 SOCIAL SCIENCES, INTERDISCIPLINARY Evaluation and Program Planning Pub Date : 2024-05-17 DOI:10.1016/j.evalprogplan.2024.102436
Madhav Prasad Koirala , Roshan Samrat Shahi
{"title":"研究尼泊尔农村市政当局推动的建筑项目超时的原因和影响","authors":"Madhav Prasad Koirala ,&nbsp;Roshan Samrat Shahi","doi":"10.1016/j.evalprogplan.2024.102436","DOIUrl":null,"url":null,"abstract":"<div><p>Time overruns are the most common issue in construction projects, which have a significant negative impact on the project and the parties involved. This also applies to National Competitive Bidding (NCB) construction projects in municipalities, jeopardizing project timelines, costs, and quality standards. Poor performance by professionals in rural municipalities has resulted in inadequate infrastructure development in these areas. The goal of this study is to understand the causes and effects of time overruns by employing an exploratory and descriptive research methodology. The data from clients, consultants, and contractors consistently highlights key factors contributing to project delays, including adverse weather conditions, limited involvement from contractor head offices, insufficient consultant experience, inadequate site management, and delays in site mobilization. These delays incur substantial costs related to materials, land acquisition, labor, and market risks. The results included that 52.17% the projects experienced time overruns ranging from 24.4% to 514.71%. Furthermore, 21.73% of projects experienced cost overruns, with the highest at 19.92%. These findings provide critical insights for improving project management and addressing construction time overruns. It recommends conducting national-scale analyses to gain a comprehensive understanding of construction delays and to implement effective mitigation strategies.</p></div>","PeriodicalId":48046,"journal":{"name":"Evaluation and Program Planning","volume":null,"pages":null},"PeriodicalIF":1.5000,"publicationDate":"2024-05-17","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Examining the causes and effects of time overruns in construction projects promoted by rural municipalities in Nepal\",\"authors\":\"Madhav Prasad Koirala ,&nbsp;Roshan Samrat Shahi\",\"doi\":\"10.1016/j.evalprogplan.2024.102436\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"<div><p>Time overruns are the most common issue in construction projects, which have a significant negative impact on the project and the parties involved. This also applies to National Competitive Bidding (NCB) construction projects in municipalities, jeopardizing project timelines, costs, and quality standards. Poor performance by professionals in rural municipalities has resulted in inadequate infrastructure development in these areas. The goal of this study is to understand the causes and effects of time overruns by employing an exploratory and descriptive research methodology. The data from clients, consultants, and contractors consistently highlights key factors contributing to project delays, including adverse weather conditions, limited involvement from contractor head offices, insufficient consultant experience, inadequate site management, and delays in site mobilization. These delays incur substantial costs related to materials, land acquisition, labor, and market risks. The results included that 52.17% the projects experienced time overruns ranging from 24.4% to 514.71%. Furthermore, 21.73% of projects experienced cost overruns, with the highest at 19.92%. These findings provide critical insights for improving project management and addressing construction time overruns. It recommends conducting national-scale analyses to gain a comprehensive understanding of construction delays and to implement effective mitigation strategies.</p></div>\",\"PeriodicalId\":48046,\"journal\":{\"name\":\"Evaluation and Program Planning\",\"volume\":null,\"pages\":null},\"PeriodicalIF\":1.5000,\"publicationDate\":\"2024-05-17\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Evaluation and Program Planning\",\"FirstCategoryId\":\"90\",\"ListUrlMain\":\"https://www.sciencedirect.com/science/article/pii/S0149718924000387\",\"RegionNum\":4,\"RegionCategory\":\"社会学\",\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"Q2\",\"JCRName\":\"SOCIAL SCIENCES, INTERDISCIPLINARY\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Evaluation and Program Planning","FirstCategoryId":"90","ListUrlMain":"https://www.sciencedirect.com/science/article/pii/S0149718924000387","RegionNum":4,"RegionCategory":"社会学","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"Q2","JCRName":"SOCIAL SCIENCES, INTERDISCIPLINARY","Score":null,"Total":0}
引用次数: 0

摘要

超时是建筑项目中最常见的问题,会对项目和相关各方产生重大负面影响。这同样适用于市政当局的国家竞争性招标(NCB)建筑项目,会危及项目的时限、成本和质量标准。农村市政当局专业人员的不佳表现导致这些地区的基础设施发展不足。本研究的目标是采用探索性和描述性研究方法,了解超时的原因和影响。来自客户、顾问和承包商的数据一致强调了造成项目延误的关键因素,包括恶劣的天气条件、承包商总部的参与有限、顾问经验不足、现场管理不足以及现场动员延误。这些延误造成了与材料、土地征用、劳动力和市场风险相关的大量成本。调查结果显示,52.17%的项目超时 24.4%至 514.71%不等。此外,21.73%的项目出现成本超支,最高的为 19.92%。这些发现为改进项目管理和解决施工超时问题提供了重要启示。报告建议开展全国范围的分析,以全面了解施工延误情况,并实施有效的缓解策略。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
查看原文
分享 分享
微信好友 朋友圈 QQ好友 复制链接
本刊更多论文
Examining the causes and effects of time overruns in construction projects promoted by rural municipalities in Nepal

Time overruns are the most common issue in construction projects, which have a significant negative impact on the project and the parties involved. This also applies to National Competitive Bidding (NCB) construction projects in municipalities, jeopardizing project timelines, costs, and quality standards. Poor performance by professionals in rural municipalities has resulted in inadequate infrastructure development in these areas. The goal of this study is to understand the causes and effects of time overruns by employing an exploratory and descriptive research methodology. The data from clients, consultants, and contractors consistently highlights key factors contributing to project delays, including adverse weather conditions, limited involvement from contractor head offices, insufficient consultant experience, inadequate site management, and delays in site mobilization. These delays incur substantial costs related to materials, land acquisition, labor, and market risks. The results included that 52.17% the projects experienced time overruns ranging from 24.4% to 514.71%. Furthermore, 21.73% of projects experienced cost overruns, with the highest at 19.92%. These findings provide critical insights for improving project management and addressing construction time overruns. It recommends conducting national-scale analyses to gain a comprehensive understanding of construction delays and to implement effective mitigation strategies.

求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
Evaluation and Program Planning
Evaluation and Program Planning SOCIAL SCIENCES, INTERDISCIPLINARY-
CiteScore
3.10
自引率
6.20%
发文量
112
期刊介绍: Evaluation and Program Planning is based on the principle that the techniques and methods of evaluation and planning transcend the boundaries of specific fields and that relevant contributions to these areas come from people representing many different positions, intellectual traditions, and interests. In order to further the development of evaluation and planning, we publish articles from the private and public sectors in a wide range of areas: organizational development and behavior, training, planning, human resource development, health and mental, social services, mental retardation, corrections, substance abuse, and education.
期刊最新文献
Anticipatory evaluation. How to incorporate an anticipatory technique into a theory-driven evaluation process. Results of application in a case study. What evaluation criteria are used in policy evaluation research: A cross-field literature review A program evaluation of the new choices workforce development program: An appreciative inquiry approach The Problems (and possible solutions) of assessing risk, race and recidivism in long operating drug treatment courts A theoretical framework to companies value creation through a systematic review of intangibles’ management
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
现在去查看 取消
×
提示
确定
0
微信
客服QQ
Book学术公众号 扫码关注我们
反馈
×
意见反馈
请填写您的意见或建议
请填写您的手机或邮箱
已复制链接
已复制链接
快去分享给好友吧!
我知道了
×
扫码分享
扫码分享
Book学术官方微信
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术
文献互助 智能选刊 最新文献 互助须知 联系我们:info@booksci.cn
Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。
Copyright © 2023 Book学术 All rights reserved.
ghs 京公网安备 11010802042870号 京ICP备2023020795号-1