{"title":"利用关键路径法(CPM)优化德克拉纳斯达和加里曼丹巴拉特博物馆围栏修复大楼和大厅项目的进度安排","authors":"Layla Mutiara Halim, Lusiana Lusiana, Safarudin M Nuh","doi":"10.26418/jts.v24i2.75578","DOIUrl":null,"url":null,"abstract":"This study investigates the optimization of project scheduling using the Critical Path Method (CPM) in construction projects. Focusing on the Building Rehabilitation Project, Dekranasda Hall, and Kalimantan Barat Museum Fence, the research aims to reduce project duration without altering costs. CPM is employed to map out activities in a network, identifying the critical path to enhance time management. The initial project duration was 249 days. By breaking down work items and increasing the number of workers in critical activities, the duration was reduced to 125 days. Optimization involved dividing tasks into manageable segments and determining the appropriate workforce through trial and error. The study demonstrates that effective project scheduling and resource allocation can significantly reduce completion time, highlighting CPM's value in project management for achieving efficiency and meeting deadlines. The findings emphasize the importance of detailed planning, dependency logic, and continuous monitoring to optimize construction project timelines.","PeriodicalId":52838,"journal":{"name":"Jurnal Teknik Sipil","volume":null,"pages":null},"PeriodicalIF":0.0000,"publicationDate":"2024-06-05","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"OPTIMIZATION SCHEDULING PROJECT REHABILITATION BUILDING AND HALL DEKRANASDA AND KALIMANTAN BARAT MUSEUM FENCE USING CRITICAL PATH METHOD (CPM)\",\"authors\":\"Layla Mutiara Halim, Lusiana Lusiana, Safarudin M Nuh\",\"doi\":\"10.26418/jts.v24i2.75578\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"This study investigates the optimization of project scheduling using the Critical Path Method (CPM) in construction projects. Focusing on the Building Rehabilitation Project, Dekranasda Hall, and Kalimantan Barat Museum Fence, the research aims to reduce project duration without altering costs. CPM is employed to map out activities in a network, identifying the critical path to enhance time management. The initial project duration was 249 days. By breaking down work items and increasing the number of workers in critical activities, the duration was reduced to 125 days. Optimization involved dividing tasks into manageable segments and determining the appropriate workforce through trial and error. The study demonstrates that effective project scheduling and resource allocation can significantly reduce completion time, highlighting CPM's value in project management for achieving efficiency and meeting deadlines. The findings emphasize the importance of detailed planning, dependency logic, and continuous monitoring to optimize construction project timelines.\",\"PeriodicalId\":52838,\"journal\":{\"name\":\"Jurnal Teknik Sipil\",\"volume\":null,\"pages\":null},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2024-06-05\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Jurnal Teknik Sipil\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.26418/jts.v24i2.75578\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Jurnal Teknik Sipil","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.26418/jts.v24i2.75578","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0
摘要
本研究探讨了在建筑项目中使用关键路径法(CPM)优化项目进度的问题。该研究以建筑修复项目、Dekranasda Hall 和加里曼丹巴拉特博物馆围栏为重点,旨在缩短项目工期而不改变成本。CPM 被用来绘制网络中的活动图,确定关键路径以加强时间管理。最初的项目工期为 249 天。通过分解工作项目和增加关键活动中的工人数量,工期缩短至 125 天。优化工作包括将任务划分为可管理的部分,并通过反复试验确定适当的劳动力。这项研究表明,有效的项目进度安排和资源分配可以大大缩短完工时间,突出了 CPM 在项目管理中提高效率和遵守期限的价值。研究结果强调了详细规划、依赖逻辑和持续监控对优化施工项目时间的重要性。
OPTIMIZATION SCHEDULING PROJECT REHABILITATION BUILDING AND HALL DEKRANASDA AND KALIMANTAN BARAT MUSEUM FENCE USING CRITICAL PATH METHOD (CPM)
This study investigates the optimization of project scheduling using the Critical Path Method (CPM) in construction projects. Focusing on the Building Rehabilitation Project, Dekranasda Hall, and Kalimantan Barat Museum Fence, the research aims to reduce project duration without altering costs. CPM is employed to map out activities in a network, identifying the critical path to enhance time management. The initial project duration was 249 days. By breaking down work items and increasing the number of workers in critical activities, the duration was reduced to 125 days. Optimization involved dividing tasks into manageable segments and determining the appropriate workforce through trial and error. The study demonstrates that effective project scheduling and resource allocation can significantly reduce completion time, highlighting CPM's value in project management for achieving efficiency and meeting deadlines. The findings emphasize the importance of detailed planning, dependency logic, and continuous monitoring to optimize construction project timelines.