自动选择性能最佳的控制点方法,用于有资源限制的项目控制

IF 6 2区 管理学 Q1 OPERATIONS RESEARCH & MANAGEMENT SCIENCE European Journal of Operational Research Pub Date : 2024-11-04 DOI:10.1016/j.ejor.2024.10.025
Jie Song, Jinbo Song, Mario Vanhoucke
{"title":"自动选择性能最佳的控制点方法,用于有资源限制的项目控制","authors":"Jie Song, Jinbo Song, Mario Vanhoucke","doi":"10.1016/j.ejor.2024.10.025","DOIUrl":null,"url":null,"abstract":"During project execution, the actual project progress shows deviations from the baseline schedule due to uncertainty. To complete the project timely, project monitoring is performed at discrete control points to identify project opportunities/problems and take possible corrective actions. These control points affect the quality of project monitoring and corrective actions, but little guidance is available on identifying situations where the control points pay off the most in terms of project duration.","PeriodicalId":55161,"journal":{"name":"European Journal of Operational Research","volume":"143 1","pages":""},"PeriodicalIF":6.0000,"publicationDate":"2024-11-04","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Automatic selection of the best performing control point approach for project control with resource constraints\",\"authors\":\"Jie Song, Jinbo Song, Mario Vanhoucke\",\"doi\":\"10.1016/j.ejor.2024.10.025\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"During project execution, the actual project progress shows deviations from the baseline schedule due to uncertainty. To complete the project timely, project monitoring is performed at discrete control points to identify project opportunities/problems and take possible corrective actions. These control points affect the quality of project monitoring and corrective actions, but little guidance is available on identifying situations where the control points pay off the most in terms of project duration.\",\"PeriodicalId\":55161,\"journal\":{\"name\":\"European Journal of Operational Research\",\"volume\":\"143 1\",\"pages\":\"\"},\"PeriodicalIF\":6.0000,\"publicationDate\":\"2024-11-04\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"European Journal of Operational Research\",\"FirstCategoryId\":\"91\",\"ListUrlMain\":\"https://doi.org/10.1016/j.ejor.2024.10.025\",\"RegionNum\":2,\"RegionCategory\":\"管理学\",\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"Q1\",\"JCRName\":\"OPERATIONS RESEARCH & MANAGEMENT SCIENCE\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"European Journal of Operational Research","FirstCategoryId":"91","ListUrlMain":"https://doi.org/10.1016/j.ejor.2024.10.025","RegionNum":2,"RegionCategory":"管理学","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"Q1","JCRName":"OPERATIONS RESEARCH & MANAGEMENT SCIENCE","Score":null,"Total":0}
引用次数: 0

摘要

在项目执行过程中,由于不确定性,实际项目进度与基准进度会出现偏差。为了按时完成项目,需要在不连续的控制点进行项目监控,以发现项目机会/问题,并采取可能的纠正措施。这些控制点会影响项目监控和纠正措施的质量,但对于如何确定在哪些情况下控制点对项目持续时间的影响最大,却几乎没有任何指导。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
查看原文
分享 分享
微信好友 朋友圈 QQ好友 复制链接
本刊更多论文
Automatic selection of the best performing control point approach for project control with resource constraints
During project execution, the actual project progress shows deviations from the baseline schedule due to uncertainty. To complete the project timely, project monitoring is performed at discrete control points to identify project opportunities/problems and take possible corrective actions. These control points affect the quality of project monitoring and corrective actions, but little guidance is available on identifying situations where the control points pay off the most in terms of project duration.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
European Journal of Operational Research
European Journal of Operational Research 管理科学-运筹学与管理科学
CiteScore
11.90
自引率
9.40%
发文量
786
审稿时长
8.2 months
期刊介绍: The European Journal of Operational Research (EJOR) publishes high quality, original papers that contribute to the methodology of operational research (OR) and to the practice of decision making.
期刊最新文献
Editorial Board Bi-objective ranking and selection using stochastic kriging Single-machine preemptive scheduling with assignable due dates or assignable weights to minimize total weighted late work Measuring carbon emission performance in China's energy market: Evidence from improved non-radial directional distance function data envelopment analysis A general valuation framework for rough stochastic local volatility models and applications
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
现在去查看 取消
×
提示
确定
0
微信
客服QQ
Book学术公众号 扫码关注我们
反馈
×
意见反馈
请填写您的意见或建议
请填写您的手机或邮箱
已复制链接
已复制链接
快去分享给好友吧!
我知道了
×
扫码分享
扫码分享
Book学术官方微信
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术
文献互助 智能选刊 最新文献 互助须知 联系我们:info@booksci.cn
Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。
Copyright © 2023 Book学术 All rights reserved.
ghs 京公网安备 11010802042870号 京ICP备2023020795号-1