{"title":"具有中断的重复建设项目中的资源平衡:一种综合方法","authors":"Guyu Dai, Mingjuan Liao, Renqian Zhang","doi":"10.3846/jcem.2023.17568","DOIUrl":null,"url":null,"abstract":"Despite the significance of resource levelling, project managers lack various ways to smooth resource usage fluctuation of a repetitive construction project besides changing resource usage. Tolerating interruptions is an effective way to provide flexibility for a schedule but is ignored when solving resource levelling problems. Therefore, this paper investigates the impacts of interruptions on resource usage fluctuation and develops an integrated approach that simultaneously integrates two scheduling adjusting processes: changing resource usage and tolerating interruptions. In this paper, two interruption conditions are proposed to identify which activities are suitable to be interrupted for smoothing resource usage fluctuation. The traditional resource levelling model is modified to a new scheduling model by incorporating interruptions. A two-stage GA-based scheduling algorithm is developed by integrating changing resource usage and tolerating interruptions. A commonly used pipeline project is adopted to illustrate the steps of the proposed approach and demonstrate its effectiveness and superiority through comparison with previous studies. A large-scale project further verifies the usability of the proposed approach. The results confirmed the feasibility to smooth resource usage fluctuation by interruptions, and the integrated approach can achieve a more competitive resource levelling result.","PeriodicalId":15524,"journal":{"name":"Journal of Civil Engineering and Management","volume":" ","pages":""},"PeriodicalIF":4.3000,"publicationDate":"2023-01-23","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"2","resultStr":"{\"title\":\"RESOURCE LEVELLING IN REPETITIVE CONSTRUCTION PROJECTS WITH INTERRUPTIONS: AN INTEGRATED APPROACH\",\"authors\":\"Guyu Dai, Mingjuan Liao, Renqian Zhang\",\"doi\":\"10.3846/jcem.2023.17568\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"Despite the significance of resource levelling, project managers lack various ways to smooth resource usage fluctuation of a repetitive construction project besides changing resource usage. Tolerating interruptions is an effective way to provide flexibility for a schedule but is ignored when solving resource levelling problems. Therefore, this paper investigates the impacts of interruptions on resource usage fluctuation and develops an integrated approach that simultaneously integrates two scheduling adjusting processes: changing resource usage and tolerating interruptions. In this paper, two interruption conditions are proposed to identify which activities are suitable to be interrupted for smoothing resource usage fluctuation. The traditional resource levelling model is modified to a new scheduling model by incorporating interruptions. A two-stage GA-based scheduling algorithm is developed by integrating changing resource usage and tolerating interruptions. A commonly used pipeline project is adopted to illustrate the steps of the proposed approach and demonstrate its effectiveness and superiority through comparison with previous studies. A large-scale project further verifies the usability of the proposed approach. The results confirmed the feasibility to smooth resource usage fluctuation by interruptions, and the integrated approach can achieve a more competitive resource levelling result.\",\"PeriodicalId\":15524,\"journal\":{\"name\":\"Journal of Civil Engineering and Management\",\"volume\":\" \",\"pages\":\"\"},\"PeriodicalIF\":4.3000,\"publicationDate\":\"2023-01-23\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"2\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Journal of Civil Engineering and Management\",\"FirstCategoryId\":\"5\",\"ListUrlMain\":\"https://doi.org/10.3846/jcem.2023.17568\",\"RegionNum\":3,\"RegionCategory\":\"工程技术\",\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"Q1\",\"JCRName\":\"ENGINEERING, CIVIL\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Journal of Civil Engineering and Management","FirstCategoryId":"5","ListUrlMain":"https://doi.org/10.3846/jcem.2023.17568","RegionNum":3,"RegionCategory":"工程技术","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"Q1","JCRName":"ENGINEERING, CIVIL","Score":null,"Total":0}
RESOURCE LEVELLING IN REPETITIVE CONSTRUCTION PROJECTS WITH INTERRUPTIONS: AN INTEGRATED APPROACH
Despite the significance of resource levelling, project managers lack various ways to smooth resource usage fluctuation of a repetitive construction project besides changing resource usage. Tolerating interruptions is an effective way to provide flexibility for a schedule but is ignored when solving resource levelling problems. Therefore, this paper investigates the impacts of interruptions on resource usage fluctuation and develops an integrated approach that simultaneously integrates two scheduling adjusting processes: changing resource usage and tolerating interruptions. In this paper, two interruption conditions are proposed to identify which activities are suitable to be interrupted for smoothing resource usage fluctuation. The traditional resource levelling model is modified to a new scheduling model by incorporating interruptions. A two-stage GA-based scheduling algorithm is developed by integrating changing resource usage and tolerating interruptions. A commonly used pipeline project is adopted to illustrate the steps of the proposed approach and demonstrate its effectiveness and superiority through comparison with previous studies. A large-scale project further verifies the usability of the proposed approach. The results confirmed the feasibility to smooth resource usage fluctuation by interruptions, and the integrated approach can achieve a more competitive resource levelling result.
期刊介绍:
The Journal of Civil Engineering and Management is a peer-reviewed journal that provides an international forum for the dissemination of the latest original research, achievements and developments. We publish for researchers, designers, users and manufacturers in the different fields of civil engineering and management.
The journal publishes original articles that present new information and reviews. Our objective is to provide essential information and new ideas to help improve civil engineering competency, efficiency and productivity in world markets.
The Journal of Civil Engineering and Management publishes articles in the following fields:
building materials and structures,
structural mechanics and physics,
geotechnical engineering,
road and bridge engineering,
urban engineering and economy,
constructions technology, economy and management,
information technologies in construction,
fire protection, thermoinsulation and renovation of buildings,
labour safety in construction.