具有中断的重复建设项目中的资源平衡:一种综合方法

IF 4.3 3区 工程技术 Q1 ENGINEERING, CIVIL Journal of Civil Engineering and Management Pub Date : 2023-01-23 DOI:10.3846/jcem.2023.17568
Guyu Dai, Mingjuan Liao, Renqian Zhang
{"title":"具有中断的重复建设项目中的资源平衡:一种综合方法","authors":"Guyu Dai, Mingjuan Liao, Renqian Zhang","doi":"10.3846/jcem.2023.17568","DOIUrl":null,"url":null,"abstract":"Despite the significance of resource levelling, project managers lack various ways to smooth resource usage fluctuation of a repetitive construction project besides changing resource usage. Tolerating interruptions is an effective way to provide flexibility for a schedule but is ignored when solving resource levelling problems. Therefore, this paper investigates the impacts of interruptions on resource usage fluctuation and develops an integrated approach that simultaneously integrates two scheduling adjusting processes: changing resource usage and tolerating interruptions. In this paper, two interruption conditions are proposed to identify which activities are suitable to be interrupted for smoothing resource usage fluctuation. The traditional resource levelling model is modified to a new scheduling model by incorporating interruptions. A two-stage GA-based scheduling algorithm is developed by integrating changing resource usage and tolerating interruptions. A commonly used pipeline project is adopted to illustrate the steps of the proposed approach and demonstrate its effectiveness and superiority through comparison with previous studies. A large-scale project further verifies the usability of the proposed approach. The results confirmed the feasibility to smooth resource usage fluctuation by interruptions, and the integrated approach can achieve a more competitive resource levelling result.","PeriodicalId":15524,"journal":{"name":"Journal of Civil Engineering and Management","volume":" ","pages":""},"PeriodicalIF":4.3000,"publicationDate":"2023-01-23","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"2","resultStr":"{\"title\":\"RESOURCE LEVELLING IN REPETITIVE CONSTRUCTION PROJECTS WITH INTERRUPTIONS: AN INTEGRATED APPROACH\",\"authors\":\"Guyu Dai, Mingjuan Liao, Renqian Zhang\",\"doi\":\"10.3846/jcem.2023.17568\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"Despite the significance of resource levelling, project managers lack various ways to smooth resource usage fluctuation of a repetitive construction project besides changing resource usage. Tolerating interruptions is an effective way to provide flexibility for a schedule but is ignored when solving resource levelling problems. Therefore, this paper investigates the impacts of interruptions on resource usage fluctuation and develops an integrated approach that simultaneously integrates two scheduling adjusting processes: changing resource usage and tolerating interruptions. In this paper, two interruption conditions are proposed to identify which activities are suitable to be interrupted for smoothing resource usage fluctuation. The traditional resource levelling model is modified to a new scheduling model by incorporating interruptions. A two-stage GA-based scheduling algorithm is developed by integrating changing resource usage and tolerating interruptions. A commonly used pipeline project is adopted to illustrate the steps of the proposed approach and demonstrate its effectiveness and superiority through comparison with previous studies. A large-scale project further verifies the usability of the proposed approach. The results confirmed the feasibility to smooth resource usage fluctuation by interruptions, and the integrated approach can achieve a more competitive resource levelling result.\",\"PeriodicalId\":15524,\"journal\":{\"name\":\"Journal of Civil Engineering and Management\",\"volume\":\" \",\"pages\":\"\"},\"PeriodicalIF\":4.3000,\"publicationDate\":\"2023-01-23\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"2\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Journal of Civil Engineering and Management\",\"FirstCategoryId\":\"5\",\"ListUrlMain\":\"https://doi.org/10.3846/jcem.2023.17568\",\"RegionNum\":3,\"RegionCategory\":\"工程技术\",\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"Q1\",\"JCRName\":\"ENGINEERING, CIVIL\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Journal of Civil Engineering and Management","FirstCategoryId":"5","ListUrlMain":"https://doi.org/10.3846/jcem.2023.17568","RegionNum":3,"RegionCategory":"工程技术","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"Q1","JCRName":"ENGINEERING, CIVIL","Score":null,"Total":0}
引用次数: 2

摘要

尽管资源平衡具有重要意义,但项目经理除了改变资源使用情况外,缺乏各种途径来平滑重复建设项目的资源使用波动。容忍中断是为时间表提供灵活性的有效方法,但在解决资源均衡问题时却被忽略了。因此,本文研究了中断对资源使用波动的影响,并提出了一种整合资源使用变化和容忍中断两个调度调整过程的方法。本文提出了两种中断条件,以确定哪些活动适合中断以平滑资源使用波动。通过引入中断,将传统的资源均衡模型改进为新的调度模型。结合资源使用变化和容忍中断,提出了一种基于遗传算法的两阶段调度算法。以一个常用的管道工程为例,说明了该方法的步骤,并通过与已有研究的比较,证明了该方法的有效性和优越性。一个大型项目进一步验证了所提出方法的可用性。结果表明,该方法可以有效地缓解因中断而引起的资源利用波动,并能获得更具竞争力的资源均衡效果。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
查看原文
分享 分享
微信好友 朋友圈 QQ好友 复制链接
本刊更多论文
RESOURCE LEVELLING IN REPETITIVE CONSTRUCTION PROJECTS WITH INTERRUPTIONS: AN INTEGRATED APPROACH
Despite the significance of resource levelling, project managers lack various ways to smooth resource usage fluctuation of a repetitive construction project besides changing resource usage. Tolerating interruptions is an effective way to provide flexibility for a schedule but is ignored when solving resource levelling problems. Therefore, this paper investigates the impacts of interruptions on resource usage fluctuation and develops an integrated approach that simultaneously integrates two scheduling adjusting processes: changing resource usage and tolerating interruptions. In this paper, two interruption conditions are proposed to identify which activities are suitable to be interrupted for smoothing resource usage fluctuation. The traditional resource levelling model is modified to a new scheduling model by incorporating interruptions. A two-stage GA-based scheduling algorithm is developed by integrating changing resource usage and tolerating interruptions. A commonly used pipeline project is adopted to illustrate the steps of the proposed approach and demonstrate its effectiveness and superiority through comparison with previous studies. A large-scale project further verifies the usability of the proposed approach. The results confirmed the feasibility to smooth resource usage fluctuation by interruptions, and the integrated approach can achieve a more competitive resource levelling result.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
CiteScore
6.70
自引率
4.70%
发文量
0
审稿时长
1.7 months
期刊介绍: The Journal of Civil Engineering and Management is a peer-reviewed journal that provides an international forum for the dissemination of the latest original research, achievements and developments. We publish for researchers, designers, users and manufacturers in the different fields of civil engineering and management. The journal publishes original articles that present new information and reviews. Our objective is to provide essential information and new ideas to help improve civil engineering competency, efficiency and productivity in world markets. The Journal of Civil Engineering and Management publishes articles in the following fields: building materials and structures, structural mechanics and physics, geotechnical engineering, road and bridge engineering, urban engineering and economy, constructions technology, economy and management, information technologies in construction, fire protection, thermoinsulation and renovation of buildings, labour safety in construction.
期刊最新文献
INTEGRATING ENHANCED OPTIMIZATION WITH FINITE ELEMENT ANALYSIS FOR DESIGNING STEEL STRUCTURE WEIGHT UNDER MULTIPLE CONSTRAINTS RANDOM FIELD-BASED TUNNELING INFORMATION MODELING FRAMEWORK FOR PROBABILISTIC SAFETY ASSESSMENT OF SHIELD TUNNELS SHM-BASED PRACTICAL SAFETY EVALUATION AND VIBRATION CONTROL MODEL FOR STEEL PIPES STUDY OF THE INFLUENCE OF METRO LOADS ON THE DESTRUCTION OF NEARBY BUILDINGS AND CONSTRUCTION STRUCTURES USING BIM TECHNOLOGIES PERFORMANCE EVALUATION OF PALM OIL CLINKER AS CEMENT AND SAND REPLACEMENT MATERIALS IN FOAMED CONCRETE
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
现在去查看 取消
×
提示
确定
0
微信
客服QQ
Book学术公众号 扫码关注我们
反馈
×
意见反馈
请填写您的意见或建议
请填写您的手机或邮箱
已复制链接
已复制链接
快去分享给好友吧!
我知道了
×
扫码分享
扫码分享
Book学术官方微信
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术
文献互助 智能选刊 最新文献 互助须知 联系我们:info@booksci.cn
Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。
Copyright © 2023 Book学术 All rights reserved.
ghs 京公网安备 11010802042870号 京ICP备2023020795号-1