{"title":"大型项目用人单位非商业资源调度优化模型","authors":"Hui Feng, Jingchun Feng, Yanyan Yang","doi":"10.1080/10429247.2020.1861855","DOIUrl":null,"url":null,"abstract":"Abstract Non-commercial resources provided by employers (NCRPE) are the imperative factors affecting the progress of engineering projects. However, the NCRPE with limited supply ability is rarely considered in the schedule optimization models in previous studies. The NCRPE schedule requirement may exceed its limitation, resulting in failing to optimize the schedule. Therefore, a new schedule optimization model is built from the perspective of NCRPE. First, the features of NCRPE and corresponding optimization theory are analyzed. Then, two optimization models are proposed in multi-contract environment before and during the construction of a project, aiming to minimize the unbalance coefficient, variance of NCRPE, and the requirement strength of NCRPE, respectively. Finally, a case study about the South-North Water Transfer Project Program X is conducted. The results show that the proposed model could effectively solve the NCRPE schedule optimization problem. A reasonable and practical program planning and adjustment within different stakeholders can be obtained. The NCRPE schedule optimization can minimize the peak demand amount of the program resources and achieve a relatively balanced total resource demand before the program implementation. Besides, it ensures that the original production system capacity can satisfy the actual demand in the program implementation. The research results can provide a basis for the bidding of each contracted project in the program and the resources optimization of each contracted project in the program implementation process.","PeriodicalId":54353,"journal":{"name":"Engineering Management Journal","volume":"34 1","pages":"217 - 229"},"PeriodicalIF":1.9000,"publicationDate":"2021-01-27","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"https://sci-hub-pdf.com/10.1080/10429247.2020.1861855","citationCount":"0","resultStr":"{\"title\":\"Optimization Model of Schedule-Non-Commercial Resources Provided by Employers of Large Project Programs\",\"authors\":\"Hui Feng, Jingchun Feng, Yanyan Yang\",\"doi\":\"10.1080/10429247.2020.1861855\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"Abstract Non-commercial resources provided by employers (NCRPE) are the imperative factors affecting the progress of engineering projects. However, the NCRPE with limited supply ability is rarely considered in the schedule optimization models in previous studies. The NCRPE schedule requirement may exceed its limitation, resulting in failing to optimize the schedule. Therefore, a new schedule optimization model is built from the perspective of NCRPE. First, the features of NCRPE and corresponding optimization theory are analyzed. Then, two optimization models are proposed in multi-contract environment before and during the construction of a project, aiming to minimize the unbalance coefficient, variance of NCRPE, and the requirement strength of NCRPE, respectively. Finally, a case study about the South-North Water Transfer Project Program X is conducted. The results show that the proposed model could effectively solve the NCRPE schedule optimization problem. A reasonable and practical program planning and adjustment within different stakeholders can be obtained. The NCRPE schedule optimization can minimize the peak demand amount of the program resources and achieve a relatively balanced total resource demand before the program implementation. Besides, it ensures that the original production system capacity can satisfy the actual demand in the program implementation. The research results can provide a basis for the bidding of each contracted project in the program and the resources optimization of each contracted project in the program implementation process.\",\"PeriodicalId\":54353,\"journal\":{\"name\":\"Engineering Management Journal\",\"volume\":\"34 1\",\"pages\":\"217 - 229\"},\"PeriodicalIF\":1.9000,\"publicationDate\":\"2021-01-27\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"https://sci-hub-pdf.com/10.1080/10429247.2020.1861855\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Engineering Management Journal\",\"FirstCategoryId\":\"91\",\"ListUrlMain\":\"https://doi.org/10.1080/10429247.2020.1861855\",\"RegionNum\":4,\"RegionCategory\":\"管理学\",\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"Q3\",\"JCRName\":\"ENGINEERING, INDUSTRIAL\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Engineering Management Journal","FirstCategoryId":"91","ListUrlMain":"https://doi.org/10.1080/10429247.2020.1861855","RegionNum":4,"RegionCategory":"管理学","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"Q3","JCRName":"ENGINEERING, INDUSTRIAL","Score":null,"Total":0}
Optimization Model of Schedule-Non-Commercial Resources Provided by Employers of Large Project Programs
Abstract Non-commercial resources provided by employers (NCRPE) are the imperative factors affecting the progress of engineering projects. However, the NCRPE with limited supply ability is rarely considered in the schedule optimization models in previous studies. The NCRPE schedule requirement may exceed its limitation, resulting in failing to optimize the schedule. Therefore, a new schedule optimization model is built from the perspective of NCRPE. First, the features of NCRPE and corresponding optimization theory are analyzed. Then, two optimization models are proposed in multi-contract environment before and during the construction of a project, aiming to minimize the unbalance coefficient, variance of NCRPE, and the requirement strength of NCRPE, respectively. Finally, a case study about the South-North Water Transfer Project Program X is conducted. The results show that the proposed model could effectively solve the NCRPE schedule optimization problem. A reasonable and practical program planning and adjustment within different stakeholders can be obtained. The NCRPE schedule optimization can minimize the peak demand amount of the program resources and achieve a relatively balanced total resource demand before the program implementation. Besides, it ensures that the original production system capacity can satisfy the actual demand in the program implementation. The research results can provide a basis for the bidding of each contracted project in the program and the resources optimization of each contracted project in the program implementation process.
期刊介绍:
EMJ is designed to provide practical, pertinent knowledge on the management of technology, technical professionals, and technical organizations. EMJ strives to provide value to the practice of engineering management and engineering managers. EMJ is an archival journal that facilitates both practitioners and university faculty in publishing useful articles. The primary focus is on articles that improve the practice of engineering management. To support the practice of engineering management, EMJ publishes papers within key engineering management content areas. EMJ Editors will continue to refine these areas to ensure they are aligned with the challenges faced by technical organizations and technical managers.