{"title":"科学和政策的滞后导致自然资本的损失:以怀霍拉湖/埃尔斯米尔湖为例","authors":"Bryan Robert Jenkins","doi":"10.1080/13241583.2022.2133665","DOIUrl":null,"url":null,"abstract":"ABSTRACT The paper analyses sources of delay in developing environmental interventions to address overallocation of groundwater and water quality degradation for Te Waihora/Lake Ellesmere, a coastal lake in the Canterbury Region of New Zealand. The analysis highlighted the length of time required to collect the science to understand an issue and to formulate and implement policy responses. It also identified delays due to scientific uncertainty, scientific controversies, disregarding science, decision processes, and the response time of the natural system. The absence of clear policy approaches and environmental outcomes in order to implement environmental legislation was a significant source of delay. Delays in implementing environmental interventions led to loss of natural capital with groundwater overallocation reducing flows in groundwater-fed streams and freshwater inflows to the lake, and land use intensification degrading groundwater, groundwater-fed streams, and lake water quality. The extent of development beyond sustainable limits during these delays may have permanently compromised the ability to implement comprehensive environmental interventions.","PeriodicalId":51870,"journal":{"name":"Australasian Journal of Water Resources","volume":"27 1","pages":"117 - 131"},"PeriodicalIF":2.4000,"publicationDate":"2022-11-08","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Science and policy delay leading to loss of natural capital: case study of Te Waihora/Lake Ellesmere\",\"authors\":\"Bryan Robert Jenkins\",\"doi\":\"10.1080/13241583.2022.2133665\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"ABSTRACT The paper analyses sources of delay in developing environmental interventions to address overallocation of groundwater and water quality degradation for Te Waihora/Lake Ellesmere, a coastal lake in the Canterbury Region of New Zealand. The analysis highlighted the length of time required to collect the science to understand an issue and to formulate and implement policy responses. It also identified delays due to scientific uncertainty, scientific controversies, disregarding science, decision processes, and the response time of the natural system. The absence of clear policy approaches and environmental outcomes in order to implement environmental legislation was a significant source of delay. Delays in implementing environmental interventions led to loss of natural capital with groundwater overallocation reducing flows in groundwater-fed streams and freshwater inflows to the lake, and land use intensification degrading groundwater, groundwater-fed streams, and lake water quality. The extent of development beyond sustainable limits during these delays may have permanently compromised the ability to implement comprehensive environmental interventions.\",\"PeriodicalId\":51870,\"journal\":{\"name\":\"Australasian Journal of Water Resources\",\"volume\":\"27 1\",\"pages\":\"117 - 131\"},\"PeriodicalIF\":2.4000,\"publicationDate\":\"2022-11-08\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Australasian Journal of Water Resources\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.1080/13241583.2022.2133665\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"Q2\",\"JCRName\":\"WATER RESOURCES\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Australasian Journal of Water Resources","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1080/13241583.2022.2133665","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"Q2","JCRName":"WATER RESOURCES","Score":null,"Total":0}
Science and policy delay leading to loss of natural capital: case study of Te Waihora/Lake Ellesmere
ABSTRACT The paper analyses sources of delay in developing environmental interventions to address overallocation of groundwater and water quality degradation for Te Waihora/Lake Ellesmere, a coastal lake in the Canterbury Region of New Zealand. The analysis highlighted the length of time required to collect the science to understand an issue and to formulate and implement policy responses. It also identified delays due to scientific uncertainty, scientific controversies, disregarding science, decision processes, and the response time of the natural system. The absence of clear policy approaches and environmental outcomes in order to implement environmental legislation was a significant source of delay. Delays in implementing environmental interventions led to loss of natural capital with groundwater overallocation reducing flows in groundwater-fed streams and freshwater inflows to the lake, and land use intensification degrading groundwater, groundwater-fed streams, and lake water quality. The extent of development beyond sustainable limits during these delays may have permanently compromised the ability to implement comprehensive environmental interventions.
期刊介绍:
The Australasian Journal of Water Resources ( AJWR) is a multi-disciplinary regional journal dedicated to scholarship, professional practice and discussion on water resources planning, management and policy. Its primary geographic focus is on Australia, New Zealand and the Pacific Islands. Papers from outside this region will also be welcomed if they contribute to an understanding of water resources issues in the region. Such contributions could be due to innovations applicable to the Australasian water community, or where clear linkages between studies in other parts of the world are linked to important issues or water planning, management, development and policy challenges in Australasia. These could include papers on global issues where Australasian impacts are clearly identified.