印度尼西亚亚齐Krueng Baro河Keumala堰沉降盆地评价

A. Azmeri, Henny Herawati, Nur Aisya Amalia, F. Z. Jemi
{"title":"印度尼西亚亚齐Krueng Baro河Keumala堰沉降盆地评价","authors":"A. Azmeri, Henny Herawati, Nur Aisya Amalia, F. Z. Jemi","doi":"10.13170/aijst.8.2.13327","DOIUrl":null,"url":null,"abstract":"Krueng Baro Irrigation network is a strategic technical irrigation area in Pidie, Aceh, Indonesia. The primary water source is the Krueng Baro River flow using the infrastructure of Keumala Weir in which sedimentation is currently a significant problem in its operations. To prevent the sediment from entering the irrigation channel is to settle it in the settling basin. However, the primary irrigation channel with the stone masonry walls kept experiencing high sedimentation. Therefore, this study aimed to evaluate the performance of the Keumala Weir settling basin including its capacity and efficiency. This study used a survey method for data collection and an evaluation method following the current guidelines for data analysis. The sediment sampling was conducted in the settling basin and the primary channel. The flushing was currently carried out for seven days. However, the settling basin capacity of 2,436.75 m3 did not meet the flushing requirements. Thus, the flushing should be performed daily for a volume of 1,859.43 m3 to fulfill the condition, so that the capacity of the settling basin was controlled. The efficiency of sediment settling was 75%, and the effect of water turbulence was in a safe condition, that the sediment settled in a settling basin would not be eroded when it is empty or full. For the flushing efficiency, the shear stress was 15,538 N/m2 that can rinse less than 16 mm particles. Based on this evaluation, it can be concluded that the sediments in the primary channel were from the settling basin. It is suggested to limit the speed in the regulating building to approximately 1.5 m/s to reduce the sediments entering the primary channel. It also requires accuracy in the operation of the primary channel intake.","PeriodicalId":7128,"journal":{"name":"Aceh International Journal of Science and Technology","volume":"1 1","pages":""},"PeriodicalIF":0.0000,"publicationDate":"2019-08-31","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"1","resultStr":"{\"title\":\"Evaluation of the Settling Basin of Keumala Weir, Krueng Baro River, Aceh, Indonesia\",\"authors\":\"A. Azmeri, Henny Herawati, Nur Aisya Amalia, F. Z. Jemi\",\"doi\":\"10.13170/aijst.8.2.13327\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"Krueng Baro Irrigation network is a strategic technical irrigation area in Pidie, Aceh, Indonesia. The primary water source is the Krueng Baro River flow using the infrastructure of Keumala Weir in which sedimentation is currently a significant problem in its operations. To prevent the sediment from entering the irrigation channel is to settle it in the settling basin. However, the primary irrigation channel with the stone masonry walls kept experiencing high sedimentation. Therefore, this study aimed to evaluate the performance of the Keumala Weir settling basin including its capacity and efficiency. This study used a survey method for data collection and an evaluation method following the current guidelines for data analysis. The sediment sampling was conducted in the settling basin and the primary channel. The flushing was currently carried out for seven days. However, the settling basin capacity of 2,436.75 m3 did not meet the flushing requirements. Thus, the flushing should be performed daily for a volume of 1,859.43 m3 to fulfill the condition, so that the capacity of the settling basin was controlled. The efficiency of sediment settling was 75%, and the effect of water turbulence was in a safe condition, that the sediment settled in a settling basin would not be eroded when it is empty or full. For the flushing efficiency, the shear stress was 15,538 N/m2 that can rinse less than 16 mm particles. Based on this evaluation, it can be concluded that the sediments in the primary channel were from the settling basin. It is suggested to limit the speed in the regulating building to approximately 1.5 m/s to reduce the sediments entering the primary channel. It also requires accuracy in the operation of the primary channel intake.\",\"PeriodicalId\":7128,\"journal\":{\"name\":\"Aceh International Journal of Science and Technology\",\"volume\":\"1 1\",\"pages\":\"\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2019-08-31\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"1\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Aceh International Journal of Science and Technology\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.13170/aijst.8.2.13327\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Aceh International Journal of Science and Technology","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.13170/aijst.8.2.13327","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 1

摘要

Krueng Baro灌溉网是印度尼西亚亚齐省Pidie的一个战略技术灌区。主要水源是利用Keumala Weir基础设施的Krueng Baro河流量,其中沉积目前是其运营中的一个重大问题。防止泥沙进入灌溉渠的方法是将泥沙沉降到沉降池中。然而,石质砌筑墙的一次灌渠一直处于高淤积状态。因此,本研究旨在对库玛拉堰沉降盆地的承载力和效率进行评价。本研究采用调查法进行数据收集,采用评估法进行数据分析。泥沙取样分别在沉降盆地和主要河道进行。冲洗目前进行了7天。但沉淀池容量为2436.75 m3,不能满足冲洗要求。因此,每天应冲洗1,859.43 m3,以满足条件,从而控制沉降池的容量。泥沙沉降效率为75%,水流紊流作用处于安全条件下,沉降池在空或满的情况下沉淀的泥沙不会被侵蚀。对于冲洗效率,剪切应力为15,538 N/m2,可冲洗小于16 mm的颗粒。据此判断,主河道的沉积物主要来自沉降盆地。建议将调节楼的速度控制在1.5 m/s左右,以减少进入主通道的沉积物。它还要求主通道进气操作的准确性。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
查看原文
分享 分享
微信好友 朋友圈 QQ好友 复制链接
本刊更多论文
Evaluation of the Settling Basin of Keumala Weir, Krueng Baro River, Aceh, Indonesia
Krueng Baro Irrigation network is a strategic technical irrigation area in Pidie, Aceh, Indonesia. The primary water source is the Krueng Baro River flow using the infrastructure of Keumala Weir in which sedimentation is currently a significant problem in its operations. To prevent the sediment from entering the irrigation channel is to settle it in the settling basin. However, the primary irrigation channel with the stone masonry walls kept experiencing high sedimentation. Therefore, this study aimed to evaluate the performance of the Keumala Weir settling basin including its capacity and efficiency. This study used a survey method for data collection and an evaluation method following the current guidelines for data analysis. The sediment sampling was conducted in the settling basin and the primary channel. The flushing was currently carried out for seven days. However, the settling basin capacity of 2,436.75 m3 did not meet the flushing requirements. Thus, the flushing should be performed daily for a volume of 1,859.43 m3 to fulfill the condition, so that the capacity of the settling basin was controlled. The efficiency of sediment settling was 75%, and the effect of water turbulence was in a safe condition, that the sediment settled in a settling basin would not be eroded when it is empty or full. For the flushing efficiency, the shear stress was 15,538 N/m2 that can rinse less than 16 mm particles. Based on this evaluation, it can be concluded that the sediments in the primary channel were from the settling basin. It is suggested to limit the speed in the regulating building to approximately 1.5 m/s to reduce the sediments entering the primary channel. It also requires accuracy in the operation of the primary channel intake.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
19
审稿时长
8 weeks
期刊最新文献
Structural Health Monitoring by Identification Dynamic Properties and Load Rating Factor at Multi-span Prestressed Concrete Girder Bridge Isotherm and Kinetic Adsorption of Cadmium (Cd) onto Biosorbent Made from Kepok Banana Peel (Musa Acuminata balbisian): the Effect of Activator Type and Biosorbent Dosage Life Cycle Cost Analysis and Payback Period of 12-kW Wind Turbine for a Remote Telecommunications Base Station Simulation of Multi Reservoir Operation Rules with Interconnected Tunnel and Water Transfer Simple Technology of Material Physics of Groundwater Conservation in Dealing with Climate Change in Disaster Areas of North Sumatra
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
现在去查看 取消
×
提示
确定
0
微信
客服QQ
Book学术公众号 扫码关注我们
反馈
×
意见反馈
请填写您的意见或建议
请填写您的手机或邮箱
已复制链接
已复制链接
快去分享给好友吧!
我知道了
×
扫码分享
扫码分享
Book学术官方微信
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术
文献互助 智能选刊 最新文献 互助须知 联系我们:info@booksci.cn
Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。
Copyright © 2023 Book学术 All rights reserved.
ghs 京公网安备 11010802042870号 京ICP备2023020795号-1