F. Queiroz, Fernando B. C de Araujo, Mylene Marques Fernandes, Juliana Casaccia Vaz
{"title":"天秤座的FPSO -概念设计挑战","authors":"F. Queiroz, Fernando B. C de Araujo, Mylene Marques Fernandes, Juliana Casaccia Vaz","doi":"10.4043/29536-MS","DOIUrl":null,"url":null,"abstract":"\n This paper presents the strategy behind the conceptual design for Libra FPSOs and the technologies being studied to be applied in the future. Considering new reservoir conditions when compared to other Pre-Salt areas in Brazil, such as high GOR, high CO2 content and high productivity wells, surface facilities team have faced new challenges to define the optimum process plant configuration. Concerns related to topside weight and footprint had to be addressed since the early project phase to make sure that the FPSO would be able to operate safely with high production efficiency in a very restricted area.\n Right after Libra block contract signature, Libra Project Team elaborated the documentation to lease the first FPSO (EWT FPSO Pioneiro de Libra) and started conceptual studies for the design of the FPSOs that will develop the production of the field.\n Besides the economic benefits related to the increase of the oil capacity, the conceptual studies at an early stage of the field development provided the project team more confidence regarding lead time and technical aspects of the FPSO. It is expected that new technologies development will add more value to the projects in the near future.","PeriodicalId":11149,"journal":{"name":"Day 1 Mon, May 06, 2019","volume":null,"pages":null},"PeriodicalIF":0.0000,"publicationDate":"2019-04-26","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"1","resultStr":"{\"title\":\"Libra's FPSO - Conceptual Design Challenges\",\"authors\":\"F. Queiroz, Fernando B. C de Araujo, Mylene Marques Fernandes, Juliana Casaccia Vaz\",\"doi\":\"10.4043/29536-MS\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"\\n This paper presents the strategy behind the conceptual design for Libra FPSOs and the technologies being studied to be applied in the future. Considering new reservoir conditions when compared to other Pre-Salt areas in Brazil, such as high GOR, high CO2 content and high productivity wells, surface facilities team have faced new challenges to define the optimum process plant configuration. Concerns related to topside weight and footprint had to be addressed since the early project phase to make sure that the FPSO would be able to operate safely with high production efficiency in a very restricted area.\\n Right after Libra block contract signature, Libra Project Team elaborated the documentation to lease the first FPSO (EWT FPSO Pioneiro de Libra) and started conceptual studies for the design of the FPSOs that will develop the production of the field.\\n Besides the economic benefits related to the increase of the oil capacity, the conceptual studies at an early stage of the field development provided the project team more confidence regarding lead time and technical aspects of the FPSO. It is expected that new technologies development will add more value to the projects in the near future.\",\"PeriodicalId\":11149,\"journal\":{\"name\":\"Day 1 Mon, May 06, 2019\",\"volume\":null,\"pages\":null},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2019-04-26\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"1\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Day 1 Mon, May 06, 2019\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.4043/29536-MS\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Day 1 Mon, May 06, 2019","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.4043/29536-MS","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 1
摘要
本文介绍了Libra fpso概念设计背后的策略以及未来正在研究的应用技术。与巴西其他盐下地区相比,考虑到新的储层条件,如高GOR、高CO2含量和高产能井,地面设施团队面临着确定最佳工艺装置配置的新挑战。从项目早期开始,就必须解决与上层重量和占地面积有关的问题,以确保FPSO能够在非常有限的区域内以高生产效率安全运行。在Libra区块合同签署后,Libra项目团队制定了租赁第一艘FPSO (EWT FPSO pioneer de Libra)的文件,并开始了FPSO设计的概念研究,这些FPSO将用于开发该油田的生产。除了与产油量增加相关的经济效益外,油田开发早期阶段的概念研究使项目团队对FPSO的交货时间和技术方面更有信心。预计在不久的将来,新技术的发展将为项目增加更多的价值。
This paper presents the strategy behind the conceptual design for Libra FPSOs and the technologies being studied to be applied in the future. Considering new reservoir conditions when compared to other Pre-Salt areas in Brazil, such as high GOR, high CO2 content and high productivity wells, surface facilities team have faced new challenges to define the optimum process plant configuration. Concerns related to topside weight and footprint had to be addressed since the early project phase to make sure that the FPSO would be able to operate safely with high production efficiency in a very restricted area.
Right after Libra block contract signature, Libra Project Team elaborated the documentation to lease the first FPSO (EWT FPSO Pioneiro de Libra) and started conceptual studies for the design of the FPSOs that will develop the production of the field.
Besides the economic benefits related to the increase of the oil capacity, the conceptual studies at an early stage of the field development provided the project team more confidence regarding lead time and technical aspects of the FPSO. It is expected that new technologies development will add more value to the projects in the near future.