{"title":"采用先进技术,原油储罐翻新周期缩短40%","authors":"S. M. Al Yammahi, Mohamed Obaid Al Kaabi, Rashid Al Zaabi, Sachin A. Shendge, Manly Vista Dizon, Ananda Sarkar","doi":"10.2118/207976-ms","DOIUrl":null,"url":null,"abstract":"\n Crude storage tanks are an important asset in every oil company. Having adequate storage capacities is important economically and ensure steady supply of oil in the market. Hence, taking a huge tank out of service for refurbishment is technically and safety critical, and as much as putting it back into service on time.\n This paper presents an advanced methodology and assessment of tank refurbishment process of large capacity Crude Storage Tanks, in compliance with the International Codes and Standards resulting in optimization of the project schedule by approximately 40% as compared to conventional methodology of refurbishment. By deploying the advance techniques, detailed assessment, and dynamic planning we have been able to accelerate the completion of the project, improve tank availability time without compromising with the Integrity and HSE.","PeriodicalId":10959,"journal":{"name":"Day 3 Wed, November 17, 2021","volume":"32 1","pages":""},"PeriodicalIF":0.0000,"publicationDate":"2021-12-09","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Crude Oil Storage Tank Refurbishment Duration Optimized by 40% Through Advanced Techniques\",\"authors\":\"S. M. Al Yammahi, Mohamed Obaid Al Kaabi, Rashid Al Zaabi, Sachin A. Shendge, Manly Vista Dizon, Ananda Sarkar\",\"doi\":\"10.2118/207976-ms\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"\\n Crude storage tanks are an important asset in every oil company. Having adequate storage capacities is important economically and ensure steady supply of oil in the market. Hence, taking a huge tank out of service for refurbishment is technically and safety critical, and as much as putting it back into service on time.\\n This paper presents an advanced methodology and assessment of tank refurbishment process of large capacity Crude Storage Tanks, in compliance with the International Codes and Standards resulting in optimization of the project schedule by approximately 40% as compared to conventional methodology of refurbishment. By deploying the advance techniques, detailed assessment, and dynamic planning we have been able to accelerate the completion of the project, improve tank availability time without compromising with the Integrity and HSE.\",\"PeriodicalId\":10959,\"journal\":{\"name\":\"Day 3 Wed, November 17, 2021\",\"volume\":\"32 1\",\"pages\":\"\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2021-12-09\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Day 3 Wed, November 17, 2021\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.2118/207976-ms\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Day 3 Wed, November 17, 2021","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.2118/207976-ms","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
Crude Oil Storage Tank Refurbishment Duration Optimized by 40% Through Advanced Techniques
Crude storage tanks are an important asset in every oil company. Having adequate storage capacities is important economically and ensure steady supply of oil in the market. Hence, taking a huge tank out of service for refurbishment is technically and safety critical, and as much as putting it back into service on time.
This paper presents an advanced methodology and assessment of tank refurbishment process of large capacity Crude Storage Tanks, in compliance with the International Codes and Standards resulting in optimization of the project schedule by approximately 40% as compared to conventional methodology of refurbishment. By deploying the advance techniques, detailed assessment, and dynamic planning we have been able to accelerate the completion of the project, improve tank availability time without compromising with the Integrity and HSE.