从海上电网到岸上电力的电气化转型——两个大型海上油田减少碳排放的案例研究

Yiru Hu, H. Zhang, Yinfeng Qiu
{"title":"从海上电网到岸上电力的电气化转型——两个大型海上油田减少碳排放的案例研究","authors":"Yiru Hu, H. Zhang, Yinfeng Qiu","doi":"10.4043/31550-ms","DOIUrl":null,"url":null,"abstract":"\n With China committing to achieve carbon neutrality before 2060, the operator has set ambitious targets for minimizing carbon emissions from its oil and gas operations. Two extensive offshore oil fields – QHD32-6 and CDF 11-1 oil fields have been modified to transform its power solution from offshore generation to power from shore (PFS) to reduce carbon emission, improve offshore energy efficiency etc. The two fields comprise 25 production platforms, 2 FPSO with 21 crude oil generators and 9 gas turbine generators. The total peak power demand is about 200MW. Both QHD32-6 and CDF 11-1 oil fields have established their own offshore micro power grid by interlinking centralized offshore generation platforms via 35kV and 10kV submarine cables.\n This paper first reviews the company strategic factors as well as the national regulatory drivers behind the decision to pursue whole-scale electrification of two super complex offshore oil fields. It then explores technology challenges and solutions by means of a high voltage AC PFS such as tie-in point selection, reactive compensation considerations, key economic criteria such as operation and energy costs, and asset depreciation etc. Considering the consequences of production loss due to power outage, stringent reliability requirements were adopted. A high-speed transfer combine with a 62.3km 110kV interconnecting submarine cable between QHD32-6 and CFD11-1 offshore substations is first introduced in offshore PFS installations. Detailed configuration and its power supply continuity benefit will be discussed. Finally, major cost reduction measures such as unman and digitalization design of 220kV PFS substation are summarized, with lessons learned in a successful development of extensive on-stream oil fields electrification transformation.\n This electrification transformation is expected to reduce about a total 2.52 million tons of CO2 and 0.067 million tons of NOx emissions, save 2.17 billion cubic meters of fuel gas and 1.13 million tons of standard coals. In September 2021, QHD32-6 and CFD11-1 offshore oil fields have been completed the transformation and back into production. Although on account of a total 132km submarine cables and 200MW power demand, high voltage D.C. is traditionally the first choice, this paper demonstrates high voltage A.C. can be flexibly utilized for long distance large power demand by careful design.\n While for many upcoming offshore projects, PFS solutions have become attractive in an effort to reduce environmental footprint, this paper presents an on-stream offshore oil fields PFS transformation, extra considerations need to be addressed. The high-speed transfer solution is first used in PFS engineering that can limit a power switching time to milliseconds, exploring a new way to significantly improve power supply continuity with limited investment. Another new information is the unmanned and intelligent design of substations to increase asset adaptability, maintain system reliability and minimize labor costs.","PeriodicalId":11011,"journal":{"name":"Day 3 Thu, March 24, 2022","volume":"114 1","pages":""},"PeriodicalIF":0.0000,"publicationDate":"2022-03-18","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"1","resultStr":"{\"title\":\"Electrification Transformation from Offshore Power Grid to Power from Shore, a Case Study to Minimize Carbon Emissions for Two Extensive Offshore Oil Fields\",\"authors\":\"Yiru Hu, H. Zhang, Yinfeng Qiu\",\"doi\":\"10.4043/31550-ms\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"\\n With China committing to achieve carbon neutrality before 2060, the operator has set ambitious targets for minimizing carbon emissions from its oil and gas operations. Two extensive offshore oil fields – QHD32-6 and CDF 11-1 oil fields have been modified to transform its power solution from offshore generation to power from shore (PFS) to reduce carbon emission, improve offshore energy efficiency etc. The two fields comprise 25 production platforms, 2 FPSO with 21 crude oil generators and 9 gas turbine generators. The total peak power demand is about 200MW. Both QHD32-6 and CDF 11-1 oil fields have established their own offshore micro power grid by interlinking centralized offshore generation platforms via 35kV and 10kV submarine cables.\\n This paper first reviews the company strategic factors as well as the national regulatory drivers behind the decision to pursue whole-scale electrification of two super complex offshore oil fields. It then explores technology challenges and solutions by means of a high voltage AC PFS such as tie-in point selection, reactive compensation considerations, key economic criteria such as operation and energy costs, and asset depreciation etc. Considering the consequences of production loss due to power outage, stringent reliability requirements were adopted. A high-speed transfer combine with a 62.3km 110kV interconnecting submarine cable between QHD32-6 and CFD11-1 offshore substations is first introduced in offshore PFS installations. Detailed configuration and its power supply continuity benefit will be discussed. Finally, major cost reduction measures such as unman and digitalization design of 220kV PFS substation are summarized, with lessons learned in a successful development of extensive on-stream oil fields electrification transformation.\\n This electrification transformation is expected to reduce about a total 2.52 million tons of CO2 and 0.067 million tons of NOx emissions, save 2.17 billion cubic meters of fuel gas and 1.13 million tons of standard coals. In September 2021, QHD32-6 and CFD11-1 offshore oil fields have been completed the transformation and back into production. Although on account of a total 132km submarine cables and 200MW power demand, high voltage D.C. is traditionally the first choice, this paper demonstrates high voltage A.C. can be flexibly utilized for long distance large power demand by careful design.\\n While for many upcoming offshore projects, PFS solutions have become attractive in an effort to reduce environmental footprint, this paper presents an on-stream offshore oil fields PFS transformation, extra considerations need to be addressed. The high-speed transfer solution is first used in PFS engineering that can limit a power switching time to milliseconds, exploring a new way to significantly improve power supply continuity with limited investment. Another new information is the unmanned and intelligent design of substations to increase asset adaptability, maintain system reliability and minimize labor costs.\",\"PeriodicalId\":11011,\"journal\":{\"name\":\"Day 3 Thu, March 24, 2022\",\"volume\":\"114 1\",\"pages\":\"\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2022-03-18\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"1\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Day 3 Thu, March 24, 2022\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.4043/31550-ms\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Day 3 Thu, March 24, 2022","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.4043/31550-ms","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 1

摘要

随着中国承诺在2060年之前实现碳中和,该运营商制定了雄心勃勃的目标,以最大限度地减少其油气业务的碳排放。两个大型海上油田——QHD32-6和CDF 11-1油田已经被改造,将其电力解决方案从海上发电转变为岸上发电(PFS),以减少碳排放,提高海上能源效率等。这两个油田包括25个生产平台,2个FPSO, 21个原油发电机和9个燃气轮机发电机。总峰值电力需求约200MW。QHD32-6和CDF 11-1油田都通过35kV和10kV海底电缆将海上集中发电平台互联,建立了自己的海上微电网。本文首先回顾了公司的战略因素以及国家监管驱动因素,决定在两个超级复杂的海上油田进行全面电气化。然后,通过高压交流PFS探讨技术挑战和解决方案,如接入点选择,无功补偿考虑,关键经济标准,如运营和能源成本,以及资产折旧等。考虑到停电造成的生产损失,采用了严格的可靠性要求。QHD32-6和CFD11-1海上变电站之间的高速传输组合和62.3公里110kV海底互连电缆首次引入海上PFS装置。详细的配置和它的电源连续性效益将讨论。最后总结了220kV PFS变电站的人性化设计、数字化设计等主要降本措施,总结了油田大范围电气化改造的成功发展经验。此次电气化改造预计将减少约252万吨二氧化碳和0.067万吨氮氧化物排放,节约21.7亿立方米燃气和113万吨标准煤。2021年9月,QHD32-6和CFD11-1海上油田完成改造并恢复生产。虽然由于海底电缆总长132km,电力需求200MW,传统上高压直流是首选,但通过精心设计,可以灵活地利用高压交流来满足长距离大电力需求。虽然对于许多即将到来的海上项目来说,PFS解决方案在减少环境足迹方面变得越来越有吸引力,但本文提出了海上油田的PFS改造,需要解决额外的考虑因素。高速传输解决方案首次用于PFS工程,可以将电源切换时间限制在毫秒级,探索了以有限投资显着提高电源连续性的新方法。另一个新信息是变电站的无人和智能设计,以增加资产适应性,保持系统可靠性并最大限度地降低人工成本。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
查看原文
分享 分享
微信好友 朋友圈 QQ好友 复制链接
本刊更多论文
Electrification Transformation from Offshore Power Grid to Power from Shore, a Case Study to Minimize Carbon Emissions for Two Extensive Offshore Oil Fields
With China committing to achieve carbon neutrality before 2060, the operator has set ambitious targets for minimizing carbon emissions from its oil and gas operations. Two extensive offshore oil fields – QHD32-6 and CDF 11-1 oil fields have been modified to transform its power solution from offshore generation to power from shore (PFS) to reduce carbon emission, improve offshore energy efficiency etc. The two fields comprise 25 production platforms, 2 FPSO with 21 crude oil generators and 9 gas turbine generators. The total peak power demand is about 200MW. Both QHD32-6 and CDF 11-1 oil fields have established their own offshore micro power grid by interlinking centralized offshore generation platforms via 35kV and 10kV submarine cables. This paper first reviews the company strategic factors as well as the national regulatory drivers behind the decision to pursue whole-scale electrification of two super complex offshore oil fields. It then explores technology challenges and solutions by means of a high voltage AC PFS such as tie-in point selection, reactive compensation considerations, key economic criteria such as operation and energy costs, and asset depreciation etc. Considering the consequences of production loss due to power outage, stringent reliability requirements were adopted. A high-speed transfer combine with a 62.3km 110kV interconnecting submarine cable between QHD32-6 and CFD11-1 offshore substations is first introduced in offshore PFS installations. Detailed configuration and its power supply continuity benefit will be discussed. Finally, major cost reduction measures such as unman and digitalization design of 220kV PFS substation are summarized, with lessons learned in a successful development of extensive on-stream oil fields electrification transformation. This electrification transformation is expected to reduce about a total 2.52 million tons of CO2 and 0.067 million tons of NOx emissions, save 2.17 billion cubic meters of fuel gas and 1.13 million tons of standard coals. In September 2021, QHD32-6 and CFD11-1 offshore oil fields have been completed the transformation and back into production. Although on account of a total 132km submarine cables and 200MW power demand, high voltage D.C. is traditionally the first choice, this paper demonstrates high voltage A.C. can be flexibly utilized for long distance large power demand by careful design. While for many upcoming offshore projects, PFS solutions have become attractive in an effort to reduce environmental footprint, this paper presents an on-stream offshore oil fields PFS transformation, extra considerations need to be addressed. The high-speed transfer solution is first used in PFS engineering that can limit a power switching time to milliseconds, exploring a new way to significantly improve power supply continuity with limited investment. Another new information is the unmanned and intelligent design of substations to increase asset adaptability, maintain system reliability and minimize labor costs.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
期刊最新文献
Integrated Advance Petrophysical Evaluation for Heterolithic Clastics Reservoir Characterization Optimization in Malay Basin The Transformation Journey and Key Critical Success Factors of Turbomachinery Digital Remote Monitoring Biggest Wells Plug and Abandonment Campaign – Effective Management & Best Practices Implementation Zawtika Deferment Management Enhancement: A Systematic Way to Unlock Gas Potential for Optimized Operations Breakthrough Integration of 3-1/2? Tubing in 8-1/2? Hole Cemented Monobore for Successful Tubing Stem Test TST
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
现在去查看 取消
×
提示
确定
0
微信
客服QQ
Book学术公众号 扫码关注我们
反馈
×
意见反馈
请填写您的意见或建议
请填写您的手机或邮箱
已复制链接
已复制链接
快去分享给好友吧!
我知道了
×
扫码分享
扫码分享
Book学术官方微信
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术
文献互助 智能选刊 最新文献 互助须知 联系我们:info@booksci.cn
Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。
Copyright © 2023 Book学术 All rights reserved.
ghs 京公网安备 11010802042870号 京ICP备2023020795号-1