Puadi Haming, Arminas Arminas, Nofias Fajri, Dodi Efendi
{"title":"以可靠性为中心的预破碎机关键部件的维修间隔","authors":"Puadi Haming, Arminas Arminas, Nofias Fajri, Dodi Efendi","doi":"10.33536/jiem.v8i1.1268","DOIUrl":null,"url":null,"abstract":"PT XYZ is a crumb rubber company that produces SIR 10 and rubber smoke sheets (RSS). As the biggest crumb rubber-produced company in Indonesia PT XYZ makes the production process sustainable. The often problem in this company is machine breakdown that occurs downtime value to be high. The highest downtime value from October 2020 until March 2021 was the Prebreaker Machine whose total downtime value was 1875 minutes. The Reliability Centered Maintenance (RCM) method is used for decreasing downtime value. The RCM is integrated with Failure Mode Effect Analysis (FMEA) for analyzing The Highest Risk Priority Number (RPN). The research results that the optimal maintenance time of the Prebreaker Machine is 51 hours which means the Prebreaker Machine is maintained after operation for 51 hours.","PeriodicalId":38526,"journal":{"name":"International Journal of Industrial Engineering and Management","volume":"57 1","pages":""},"PeriodicalIF":2.4000,"publicationDate":"2023-04-20","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"THE MAINTENANCE INTERVAL OF PREBREAKER CRITICAL COMPONENTS USING RELIABILITY-CENTERED MAINTENANCE IN PT XYZ\",\"authors\":\"Puadi Haming, Arminas Arminas, Nofias Fajri, Dodi Efendi\",\"doi\":\"10.33536/jiem.v8i1.1268\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"PT XYZ is a crumb rubber company that produces SIR 10 and rubber smoke sheets (RSS). As the biggest crumb rubber-produced company in Indonesia PT XYZ makes the production process sustainable. The often problem in this company is machine breakdown that occurs downtime value to be high. The highest downtime value from October 2020 until March 2021 was the Prebreaker Machine whose total downtime value was 1875 minutes. The Reliability Centered Maintenance (RCM) method is used for decreasing downtime value. The RCM is integrated with Failure Mode Effect Analysis (FMEA) for analyzing The Highest Risk Priority Number (RPN). The research results that the optimal maintenance time of the Prebreaker Machine is 51 hours which means the Prebreaker Machine is maintained after operation for 51 hours.\",\"PeriodicalId\":38526,\"journal\":{\"name\":\"International Journal of Industrial Engineering and Management\",\"volume\":\"57 1\",\"pages\":\"\"},\"PeriodicalIF\":2.4000,\"publicationDate\":\"2023-04-20\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"International Journal of Industrial Engineering and Management\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.33536/jiem.v8i1.1268\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"Q2\",\"JCRName\":\"ENGINEERING, INDUSTRIAL\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"International Journal of Industrial Engineering and Management","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.33536/jiem.v8i1.1268","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"Q2","JCRName":"ENGINEERING, INDUSTRIAL","Score":null,"Total":0}
THE MAINTENANCE INTERVAL OF PREBREAKER CRITICAL COMPONENTS USING RELIABILITY-CENTERED MAINTENANCE IN PT XYZ
PT XYZ is a crumb rubber company that produces SIR 10 and rubber smoke sheets (RSS). As the biggest crumb rubber-produced company in Indonesia PT XYZ makes the production process sustainable. The often problem in this company is machine breakdown that occurs downtime value to be high. The highest downtime value from October 2020 until March 2021 was the Prebreaker Machine whose total downtime value was 1875 minutes. The Reliability Centered Maintenance (RCM) method is used for decreasing downtime value. The RCM is integrated with Failure Mode Effect Analysis (FMEA) for analyzing The Highest Risk Priority Number (RPN). The research results that the optimal maintenance time of the Prebreaker Machine is 51 hours which means the Prebreaker Machine is maintained after operation for 51 hours.
期刊介绍:
International Journal of Industrial Engineering and Management (IJIEM) is an interdisciplinary international academic journal published quarterly. IJIEM serves researchers in the industrial engineering, manufacturing engineering and management fields. The major aims are: To collect and disseminate information on new and advanced developments in the field of industrial engineering and management; To encourage further progress in engineering and management methodology and applications; To cover the range of engineering and management development and usage in their use of managerial policies and strategies. Thus, IJIEM invites the submission of original, high quality, theoretical and application-oriented research; general surveys and critical reviews; educational or training articles including case studies, in the field of industrial engineering and management. The journal covers all aspects of industrial engineering and management, particularly: -Smart Manufacturing & Industry 4.0, -Production Systems, -Service Engineering, -Automation, Robotics and Mechatronics, -Information and Communication Systems, -ICT for Collaborative Manufacturing, -Quality, Maintenance and Logistics, -Safety and Reliability, -Organization and Human Resources, -Engineering Management, -Entrepreneurship and Innovation, -Project Management, -Marketing and Commerce, -Investment, Finance and Accounting, -Insurance Engineering and Management, -Media Engineering and Management, -Education and Practices in Industrial Engineering and Management.