Azraii Fikrie Azraii, A. Adhi, Thian Hui Chie Hui Chie, C. Claire, Ridzuan Shaedin Ridzuan, C. H. Roh, M. Z. M. Zarir, Firdaus Firdaus
{"title":"马来西亚Sarawak海上7英寸单孔完井安全卸载和测试高速率海上含硫气井的新技术","authors":"Azraii Fikrie Azraii, A. Adhi, Thian Hui Chie Hui Chie, C. Claire, Ridzuan Shaedin Ridzuan, C. H. Roh, M. Z. M. Zarir, Firdaus Firdaus","doi":"10.2118/192815-MS","DOIUrl":null,"url":null,"abstract":"\n Sarawak, Malaysia first offshore high rate dry gas field has an over pressured reservoir. Successful pressure control during drilling required the use of barite in the water based drilling mud in PMCD mode inside carbonate. Barite is very abrasive and is insoluble in any acid or solvent. Any barite left in the reservoir due to mud losses has to be produced back to surface after completing the wells. This cleanup is crucial for the safety and longevity of permanent facilities, especially when high rate gas wells are involved; due to the high rate of impact of any solids that may be produced with the gas. It is also critical to design the cleanup job carefully to ensure proper equipment and safety measures are taken to avoid washouts and related safety hazards.\n To ensure solids free production from day one, a procedure was implemented and successfully executed during the development of this first offshore high rate high-pressure sour gas field. This was achieved by using the tender rig as a main support and complementing the safety with the incorporation of the selected well testing equipment management system. In addition to the proper equipment, a detailed cleanup procedure, which covered systematic production ramp up and defined solids free criteria, was implemented from well owner or asset. So far, this well cleanup setup and program has been implemented on several wells on platforms with minor erosion and no safety issues.\n One platform with several wells is already producing and is flowing trouble free. This paper will describe the details of the setup of the rig facilities to clean these barite fluids from the wells, and the solids control equipment used and the cleanup procedure.","PeriodicalId":11079,"journal":{"name":"Day 4 Thu, November 15, 2018","volume":"21 1","pages":""},"PeriodicalIF":0.0000,"publicationDate":"2018-11-12","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"New Techniques Developed to Safely Unload and Test High Rate Offshore Sour Gas Well With 7-in Monobore Completions-Lessons Learned Gas Wells Offshore Sarawak Malaysia\",\"authors\":\"Azraii Fikrie Azraii, A. Adhi, Thian Hui Chie Hui Chie, C. Claire, Ridzuan Shaedin Ridzuan, C. H. Roh, M. Z. M. Zarir, Firdaus Firdaus\",\"doi\":\"10.2118/192815-MS\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"\\n Sarawak, Malaysia first offshore high rate dry gas field has an over pressured reservoir. Successful pressure control during drilling required the use of barite in the water based drilling mud in PMCD mode inside carbonate. Barite is very abrasive and is insoluble in any acid or solvent. Any barite left in the reservoir due to mud losses has to be produced back to surface after completing the wells. This cleanup is crucial for the safety and longevity of permanent facilities, especially when high rate gas wells are involved; due to the high rate of impact of any solids that may be produced with the gas. It is also critical to design the cleanup job carefully to ensure proper equipment and safety measures are taken to avoid washouts and related safety hazards.\\n To ensure solids free production from day one, a procedure was implemented and successfully executed during the development of this first offshore high rate high-pressure sour gas field. This was achieved by using the tender rig as a main support and complementing the safety with the incorporation of the selected well testing equipment management system. In addition to the proper equipment, a detailed cleanup procedure, which covered systematic production ramp up and defined solids free criteria, was implemented from well owner or asset. So far, this well cleanup setup and program has been implemented on several wells on platforms with minor erosion and no safety issues.\\n One platform with several wells is already producing and is flowing trouble free. This paper will describe the details of the setup of the rig facilities to clean these barite fluids from the wells, and the solids control equipment used and the cleanup procedure.\",\"PeriodicalId\":11079,\"journal\":{\"name\":\"Day 4 Thu, November 15, 2018\",\"volume\":\"21 1\",\"pages\":\"\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2018-11-12\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Day 4 Thu, November 15, 2018\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.2118/192815-MS\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Day 4 Thu, November 15, 2018","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.2118/192815-MS","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
New Techniques Developed to Safely Unload and Test High Rate Offshore Sour Gas Well With 7-in Monobore Completions-Lessons Learned Gas Wells Offshore Sarawak Malaysia
Sarawak, Malaysia first offshore high rate dry gas field has an over pressured reservoir. Successful pressure control during drilling required the use of barite in the water based drilling mud in PMCD mode inside carbonate. Barite is very abrasive and is insoluble in any acid or solvent. Any barite left in the reservoir due to mud losses has to be produced back to surface after completing the wells. This cleanup is crucial for the safety and longevity of permanent facilities, especially when high rate gas wells are involved; due to the high rate of impact of any solids that may be produced with the gas. It is also critical to design the cleanup job carefully to ensure proper equipment and safety measures are taken to avoid washouts and related safety hazards.
To ensure solids free production from day one, a procedure was implemented and successfully executed during the development of this first offshore high rate high-pressure sour gas field. This was achieved by using the tender rig as a main support and complementing the safety with the incorporation of the selected well testing equipment management system. In addition to the proper equipment, a detailed cleanup procedure, which covered systematic production ramp up and defined solids free criteria, was implemented from well owner or asset. So far, this well cleanup setup and program has been implemented on several wells on platforms with minor erosion and no safety issues.
One platform with several wells is already producing and is flowing trouble free. This paper will describe the details of the setup of the rig facilities to clean these barite fluids from the wells, and the solids control equipment used and the cleanup procedure.