减吃水梁:浮动海上风力涡轮机的一种经济有效的新概念

S. Guzman, M. Taboada, Albino Pombo, R. Martín, Ana Bezunartea, Andy Knights-Cooper, J. Moreu
{"title":"减吃水梁:浮动海上风力涡轮机的一种经济有效的新概念","authors":"S. Guzman, M. Taboada, Albino Pombo, R. Martín, Ana Bezunartea, Andy Knights-Cooper, J. Moreu","doi":"10.4043/29495-MS","DOIUrl":null,"url":null,"abstract":"\n This paper describes the conceptual design and estimates the CAPEX breakdown of a novel floater type for offshore wind turbines: the Reduced-Draft Spar (RDS). This floater, which resembles a GBS although it is in essence a spar, has excellent seakeeping at a reduced draft.\n Aiming at reducing the CAPEX, the RDS design allows the installation of the wind turbine at the manufacturing site. Furthermore, no auxiliary means are required to provide stability during towing and in-place installation (mooring and electric hook-up, and ballasting to the operational draft). It also promotes the use of structural concrete and cost-effective high-density ballast for its construction. In addition, the whole concept benefits from the implementation of an Active Ballast System (ABS) to compensate the mean tilt angle while operating.\n An extensive model test campaign was carried out in summer 2018 at INTA-CEHIPAR model basin to validate the concept. The tests scope was focused on calibrating a state-of-the-art numerical hydrodynamic model for further stages of development. An 8MW RDS model, with a scale factor of 1:50 and a 3-line spread mooring system, was tested in Transport and Installation (T&I), operational and survival conditions to assess the concept feasibility. The ABS was simulated using pre-calibrated counteracting weights. Stability during T&I was also checked.\n In addition, the unit CAPEX was estimated and compared to equivalent semi and spar units made of steel. The RDS can operate at intermediate water depths (60 to 80 m, where spars cannot) and deep waters, and also avoids the use of expensive auxiliary means for T&I. The results from the model tests confirm a dynamic behavior of the RDS similar to that of classic spars, which is beneficial for the offshore WT. Regarding the CAPEX, estimations indicate relevant savings compared to classic spars or semis.\n Although it is a large massive unit, the use of concrete combined with heavy ballast makes the concept feasible. Due to the ABS, the required platform's size is smaller and the fatigue life of the WT components increases. Furthermore, an adequate ABS control system increases the net energy production since the energy consumption is negligible compared to the extra generated power. The use of civil construction manufacturing technologies such as floating docks and assemble of pre-manufactured parts leads to major CAPEX savings.\n The US coast has a huge offshore wind energy resource at water depths greater than 60m, where the RDS floating concept has a promising future. The concept could be used as well in the Offshore Oil& Gas.","PeriodicalId":10968,"journal":{"name":"Day 3 Wed, May 08, 2019","volume":"108 1","pages":""},"PeriodicalIF":0.0000,"publicationDate":"2019-04-26","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"1","resultStr":"{\"title\":\"The Reduced-Draft Spar: A Novel Cost-Effective Concept for Floating Offshore Wind Turbines\",\"authors\":\"S. Guzman, M. Taboada, Albino Pombo, R. Martín, Ana Bezunartea, Andy Knights-Cooper, J. Moreu\",\"doi\":\"10.4043/29495-MS\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"\\n This paper describes the conceptual design and estimates the CAPEX breakdown of a novel floater type for offshore wind turbines: the Reduced-Draft Spar (RDS). This floater, which resembles a GBS although it is in essence a spar, has excellent seakeeping at a reduced draft.\\n Aiming at reducing the CAPEX, the RDS design allows the installation of the wind turbine at the manufacturing site. Furthermore, no auxiliary means are required to provide stability during towing and in-place installation (mooring and electric hook-up, and ballasting to the operational draft). It also promotes the use of structural concrete and cost-effective high-density ballast for its construction. In addition, the whole concept benefits from the implementation of an Active Ballast System (ABS) to compensate the mean tilt angle while operating.\\n An extensive model test campaign was carried out in summer 2018 at INTA-CEHIPAR model basin to validate the concept. The tests scope was focused on calibrating a state-of-the-art numerical hydrodynamic model for further stages of development. An 8MW RDS model, with a scale factor of 1:50 and a 3-line spread mooring system, was tested in Transport and Installation (T&I), operational and survival conditions to assess the concept feasibility. The ABS was simulated using pre-calibrated counteracting weights. Stability during T&I was also checked.\\n In addition, the unit CAPEX was estimated and compared to equivalent semi and spar units made of steel. The RDS can operate at intermediate water depths (60 to 80 m, where spars cannot) and deep waters, and also avoids the use of expensive auxiliary means for T&I. The results from the model tests confirm a dynamic behavior of the RDS similar to that of classic spars, which is beneficial for the offshore WT. Regarding the CAPEX, estimations indicate relevant savings compared to classic spars or semis.\\n Although it is a large massive unit, the use of concrete combined with heavy ballast makes the concept feasible. Due to the ABS, the required platform's size is smaller and the fatigue life of the WT components increases. Furthermore, an adequate ABS control system increases the net energy production since the energy consumption is negligible compared to the extra generated power. The use of civil construction manufacturing technologies such as floating docks and assemble of pre-manufactured parts leads to major CAPEX savings.\\n The US coast has a huge offshore wind energy resource at water depths greater than 60m, where the RDS floating concept has a promising future. The concept could be used as well in the Offshore Oil& Gas.\",\"PeriodicalId\":10968,\"journal\":{\"name\":\"Day 3 Wed, May 08, 2019\",\"volume\":\"108 1\",\"pages\":\"\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2019-04-26\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"1\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Day 3 Wed, May 08, 2019\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.4043/29495-MS\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Day 3 Wed, May 08, 2019","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.4043/29495-MS","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 1

摘要

本文描述了一种新型海上风力涡轮机浮子的概念设计,并估计了资本支出分解:减吃水Spar (RDS)。这种漂浮物,虽然本质上是一根桅杆,但它类似于GBS,在减少吃水的情况下具有出色的耐水性。为了降低资本支出,RDS设计允许在制造现场安装风力涡轮机。此外,在拖曳和现场安装(系泊和电气连接,以及作业吃水的压舱)期间,不需要任何辅助手段来提供稳定性。它还促进了结构混凝土和经济高效的高密度压载物的使用。此外,整个概念得益于主动压载系统(ABS)的实施,以补偿运行时的平均倾斜角。2018年夏季,在INTA-CEHIPAR模型盆地进行了广泛的模型测试,以验证这一概念。测试范围的重点是为进一步的开发阶段校准最先进的数值流体动力学模型。一个8MW的RDS模型,比例系数为1:50,采用3线扩展系泊系统,在运输和安装(T&I)、操作和生存条件下进行了测试,以评估概念的可行性。采用预校准的平衡权重对ABS进行了模拟。还检查了T&I期间的稳定性。此外,估计了单位资本支出,并将其与同等的半钢和钢梁单位进行了比较。RDS可以在中等水深(60 - 80米,桅杆不能)和深水中工作,并且还可以避免使用昂贵的T&I辅助手段。模型测试的结果证实,RDS的动态性能与经典桅杆相似,这对海上WT有利。关于资本支出,与经典桅杆或半桅杆相比,估计表明节省了相关的资本支出。虽然它是一个大型的块状单元,但混凝土与重型压载物的结合使用使这个概念变得可行。由于采用了ABS,所需的平台尺寸更小,WT部件的疲劳寿命增加。此外,适当的ABS控制系统增加了净能源产量,因为与额外产生的电力相比,能源消耗微不足道。使用民用建筑制造技术,如浮船坞和预制部件组装,可节省大量资本支出。美国海岸拥有巨大的海上风能资源,水深超过60米,在那里,RDS浮动概念具有广阔的前景。该概念也可用于海上油气行业。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
查看原文
分享 分享
微信好友 朋友圈 QQ好友 复制链接
本刊更多论文
The Reduced-Draft Spar: A Novel Cost-Effective Concept for Floating Offshore Wind Turbines
This paper describes the conceptual design and estimates the CAPEX breakdown of a novel floater type for offshore wind turbines: the Reduced-Draft Spar (RDS). This floater, which resembles a GBS although it is in essence a spar, has excellent seakeeping at a reduced draft. Aiming at reducing the CAPEX, the RDS design allows the installation of the wind turbine at the manufacturing site. Furthermore, no auxiliary means are required to provide stability during towing and in-place installation (mooring and electric hook-up, and ballasting to the operational draft). It also promotes the use of structural concrete and cost-effective high-density ballast for its construction. In addition, the whole concept benefits from the implementation of an Active Ballast System (ABS) to compensate the mean tilt angle while operating. An extensive model test campaign was carried out in summer 2018 at INTA-CEHIPAR model basin to validate the concept. The tests scope was focused on calibrating a state-of-the-art numerical hydrodynamic model for further stages of development. An 8MW RDS model, with a scale factor of 1:50 and a 3-line spread mooring system, was tested in Transport and Installation (T&I), operational and survival conditions to assess the concept feasibility. The ABS was simulated using pre-calibrated counteracting weights. Stability during T&I was also checked. In addition, the unit CAPEX was estimated and compared to equivalent semi and spar units made of steel. The RDS can operate at intermediate water depths (60 to 80 m, where spars cannot) and deep waters, and also avoids the use of expensive auxiliary means for T&I. The results from the model tests confirm a dynamic behavior of the RDS similar to that of classic spars, which is beneficial for the offshore WT. Regarding the CAPEX, estimations indicate relevant savings compared to classic spars or semis. Although it is a large massive unit, the use of concrete combined with heavy ballast makes the concept feasible. Due to the ABS, the required platform's size is smaller and the fatigue life of the WT components increases. Furthermore, an adequate ABS control system increases the net energy production since the energy consumption is negligible compared to the extra generated power. The use of civil construction manufacturing technologies such as floating docks and assemble of pre-manufactured parts leads to major CAPEX savings. The US coast has a huge offshore wind energy resource at water depths greater than 60m, where the RDS floating concept has a promising future. The concept could be used as well in the Offshore Oil& Gas.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
期刊最新文献
Offshore Liquefied Natural Gas LNG and Monetization A Case Study of an Independent Third Party Review of Subsea HPHT Technologies Designed and Qualified by a Joint Development Agreement Optimized SMR Process with Advanced Vessel Economizer Experimental and Numerical Studies on the Drift Velocity of Two-Phase Gas and High-Viscosity-Liquid Slug Flow in Pipelines Applied Optimal Reservoir Management: A Field Case Experience in Campos Basin
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
现在去查看 取消
×
提示
确定
0
微信
客服QQ
Book学术公众号 扫码关注我们
反馈
×
意见反馈
请填写您的意见或建议
请填写您的手机或邮箱
已复制链接
已复制链接
快去分享给好友吧!
我知道了
×
扫码分享
扫码分享
Book学术官方微信
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术
文献互助 智能选刊 最新文献 互助须知 联系我们:info@booksci.cn
Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。
Copyright © 2023 Book学术 All rights reserved.
ghs 京公网安备 11010802042870号 京ICP备2023020795号-1