Alejandro Palpan, Sandra Vega, F. Quiroz, Mark Vicuña, Rodrigo Tuesta, A. A. Del Savio
{"title":"VDC management in the industrialization process using prefabricated reinforcement cages. Case Study: Ovalo Monitor Bridge","authors":"Alejandro Palpan, Sandra Vega, F. Quiroz, Mark Vicuña, Rodrigo Tuesta, A. A. Del Savio","doi":"10.29173/mocs285","DOIUrl":null,"url":null,"abstract":"Reworks and delays in production processes are commonly found in construction projects associated with a low level of industrialization and a lack of design constructability. To promote industrialization, improve project constructability, and reduce the execution time, we implemented the Virtual Design and Construction (VDC) methodology. An industrialization strategy was established using a prefabricated reinforcement cages system (PRC) elements in an 870-meters bridge construction project in Lima, Peru. The objective was to improve the project buildability with high industrialization of the steel rebar works. We replaced the traditional on-site cutting and bending steel reinforcement processes with an industrial process that integrates construction management with the supply chain through Building Information Model (BIM). As a result, the level of industrialization of the PRC elements of the bridge substructure and superstructure reached 85% and 40%, respectively, aligned with a 16% execution time reduction of the project.","PeriodicalId":422911,"journal":{"name":"Modular and Offsite Construction (MOC) Summit Proceedings","volume":"17 2","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2022-09-14","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Modular and Offsite Construction (MOC) Summit Proceedings","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.29173/mocs285","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0
Abstract
Reworks and delays in production processes are commonly found in construction projects associated with a low level of industrialization and a lack of design constructability. To promote industrialization, improve project constructability, and reduce the execution time, we implemented the Virtual Design and Construction (VDC) methodology. An industrialization strategy was established using a prefabricated reinforcement cages system (PRC) elements in an 870-meters bridge construction project in Lima, Peru. The objective was to improve the project buildability with high industrialization of the steel rebar works. We replaced the traditional on-site cutting and bending steel reinforcement processes with an industrial process that integrates construction management with the supply chain through Building Information Model (BIM). As a result, the level of industrialization of the PRC elements of the bridge substructure and superstructure reached 85% and 40%, respectively, aligned with a 16% execution time reduction of the project.