Getting Wells Back to Production Using an Innovative Artificial Lift System for Recovering Inactive Wells

A. F. Vargas, J. Duran, A. Simpson, R. Santos, J. Doval, Loewe Muñoz, A. E. P. Jerez, C. Rativa, N. Hernandez, Rozo Rozo, D. Ríos
{"title":"Getting Wells Back to Production Using an Innovative Artificial Lift System for Recovering Inactive Wells","authors":"A. F. Vargas, J. Duran, A. Simpson, R. Santos, J. Doval, Loewe Muñoz, A. E. P. Jerez, C. Rativa, N. Hernandez, Rozo Rozo, D. Ríos","doi":"10.2118/190961-MS","DOIUrl":null,"url":null,"abstract":"\n This paper presents a successful application and the lessons learned during a pilot test under which a new electrical submersible pumping technology was installed in 4 wells. These helico-axial downhole pumps, V-Pump, were installed under a program of new technologies testing, which aimed for artificial lift run life extension in an extremely high sand-producing field under current cost constraints.\n The oil price turndown forced Casabe Field to leave some wells inactive, even though they still have significant reserves. The cause of this decision was the expenses associated to the high frequency of interventions required due to the adverse sand production effects on the artificial lift systems.\n Due to the low run life of conventional artificial lift systems that are customary to use in the field, it was necessary to search for emerging technologies that would meet the challenge presented. A screening process for new technologies were conducted, and after that, these pumps were installed in four wells, which were continuously monitored with downhole temperature, vibration and pressure sensors, fluid levels measurement, VSD readings and production tests, which would allow to understand the technology performance to achieve the desired run life, oil production gain, and to obtain lessons learned to design the second phase of the testing project.\n The use of this innovative pumping technology extended the run life in the pilot wells between 180% and 420%, allowing the production of their remaining oil reserves, and giving a new approach in the production strategy of the field. One well is still running after 13 months.\n Also, based on the on the information collected during the well production phase, through downhole sensors and VSD parameters, and the findings during the pump's dismantle, some recommendations were made to improve the performance in the second phase of the project. Recommendations include both improvements in the pump design and to the screening process of candidate wells.","PeriodicalId":373819,"journal":{"name":"Day 3 Thu, August 30, 2018","volume":"5 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2018-08-20","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"2","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Day 3 Thu, August 30, 2018","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.2118/190961-MS","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 2

Abstract

This paper presents a successful application and the lessons learned during a pilot test under which a new electrical submersible pumping technology was installed in 4 wells. These helico-axial downhole pumps, V-Pump, were installed under a program of new technologies testing, which aimed for artificial lift run life extension in an extremely high sand-producing field under current cost constraints. The oil price turndown forced Casabe Field to leave some wells inactive, even though they still have significant reserves. The cause of this decision was the expenses associated to the high frequency of interventions required due to the adverse sand production effects on the artificial lift systems. Due to the low run life of conventional artificial lift systems that are customary to use in the field, it was necessary to search for emerging technologies that would meet the challenge presented. A screening process for new technologies were conducted, and after that, these pumps were installed in four wells, which were continuously monitored with downhole temperature, vibration and pressure sensors, fluid levels measurement, VSD readings and production tests, which would allow to understand the technology performance to achieve the desired run life, oil production gain, and to obtain lessons learned to design the second phase of the testing project. The use of this innovative pumping technology extended the run life in the pilot wells between 180% and 420%, allowing the production of their remaining oil reserves, and giving a new approach in the production strategy of the field. One well is still running after 13 months. Also, based on the on the information collected during the well production phase, through downhole sensors and VSD parameters, and the findings during the pump's dismantle, some recommendations were made to improve the performance in the second phase of the project. Recommendations include both improvements in the pump design and to the screening process of candidate wells.
查看原文
分享 分享
微信好友 朋友圈 QQ好友 复制链接
本刊更多论文
利用创新的人工举升系统回收闲置井,使油井恢复生产
本文介绍了在4口井中安装新型电潜泵技术的成功应用和经验教训。这些螺旋轴向井下泵(V-Pump)是在新技术测试项目下安装的,该项目旨在在当前成本限制的情况下延长极高出砂油田的人工举升作业寿命。油价下跌迫使Casabe油田闲置了一些油井,尽管它们仍有大量储量。做出这一决定的原因是,由于人工举升系统产生了不利的出砂影响,需要进行高频率的干预,从而增加了费用。由于常规人工举升系统的运行寿命较短,因此有必要寻找能够应对当前挑战的新兴技术。在对新技术进行筛选之后,将这些泵安装在4口井中,通过井下温度、振动和压力传感器、液位测量、VSD读数和生产测试对其进行持续监测,从而了解技术性能,以达到预期的运行寿命、产油量增益,并获得经验教训,用于设计测试项目的第二阶段。使用这种创新的泵送技术,使试验井的运行寿命延长了180%至420%,使其剩余石油储量得以开采,并为该油田的生产策略提供了新的途径。其中一口井在13个月后仍在运行。此外,根据在油井生产阶段收集的信息,通过井下传感器和VSD参数,以及泵拆除过程中的发现,提出了一些建议,以提高项目第二阶段的性能。建议包括改进泵的设计和候选井的筛选过程。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 去求助
来源期刊
自引率
0.00%
发文量
0
期刊最新文献
Use of Run-Life Measures in Estimating Artificial Lift System Reliability Tuning VSDs in ESP Wells to Optimize Oil Production—Case Studies Innovative Well Designs for HGOR: Extending Gas Production with Common Gas Well Deliquification Techniques Innovative Downhole Design for Optimizing ALS Installation at Shale Oil Wells Getting Wells Back to Production Using an Innovative Artificial Lift System for Recovering Inactive Wells
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
现在去查看 取消
×
提示
确定
0
微信
客服QQ
Book学术公众号 扫码关注我们
反馈
×
意见反馈
请填写您的意见或建议
请填写您的手机或邮箱
已复制链接
已复制链接
快去分享给好友吧!
我知道了
×
扫码分享
扫码分享
Book学术官方微信
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术
文献互助 智能选刊 最新文献 互助须知 联系我们:info@booksci.cn
Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。
Copyright © 2023 Book学术 All rights reserved.
ghs 京公网安备 11010802042870号 京ICP备2023020795号-1