ANALISA PENGENDALIAN BIAYA DAN WAKTU DENGAN METODE KONSEP NILAI HASIL PADA PROYEK PEMBANGUNAN GEDUNG SATPOL PP KABUPATEN MAJALENGKA

Jahar Irawan, Arief Rijaluddin, Eka Juliar
{"title":"ANALISA PENGENDALIAN BIAYA DAN WAKTU DENGAN METODE KONSEP NILAI HASIL PADA PROYEK PEMBANGUNAN GEDUNG SATPOL PP KABUPATEN MAJALENGKA","authors":"Jahar Irawan, Arief Rijaluddin, Eka Juliar","doi":"10.31949/J-ENSITEC.V5I02.1503","DOIUrl":null,"url":null,"abstract":"The success of a project can not be separated from a series of activities that include the stages of planning, implementation and supervision, so that the goals set can be achieved. In an effort to succeed in a construction project, a good technique or management method is needed to improve efficiency, productivity, and quality of work. In connection with that, it is necessary to carry out supervision and control measures in all sectors, especially control of costs and time. This research was conducted at the Majalengka Regency Satpol PP Building Project which aims to determine the project's time performance and the estimated cost and time of the building construction project and the method of concept of the value of the results is effective or not. The data used in this study is the Time Schedule, Cost Budget Plan, and weekly progress reports. From these data can produce BCWP and BCWS values. ACWP, with the help of Microsoft Excel, obtained CP, SV, CPI, SPI, and predicts completion of project costs and end times (ETC, EAC and ECD). From the results of the analysis of the time of the construction of the Satpol PP Building in Majalengka Regency until the 22nd week with a budget of Rp. 2,454,849,000, - resulting in a CPI of 1,1000, SPI obtained at 1,0266, EAC value of Rp. 2.23,681,459.98 and ECD amounted to 126, showing the estimated construction completion time of 126 days, which means the project progressed 24 days from the 150 day plan. Keywords: Earned Value Method, BCWP, BCWS, ETC, EAC","PeriodicalId":448230,"journal":{"name":"J-ENSITEC","volume":"16 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2019-05-10","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"J-ENSITEC","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.31949/J-ENSITEC.V5I02.1503","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

Abstract

The success of a project can not be separated from a series of activities that include the stages of planning, implementation and supervision, so that the goals set can be achieved. In an effort to succeed in a construction project, a good technique or management method is needed to improve efficiency, productivity, and quality of work. In connection with that, it is necessary to carry out supervision and control measures in all sectors, especially control of costs and time. This research was conducted at the Majalengka Regency Satpol PP Building Project which aims to determine the project's time performance and the estimated cost and time of the building construction project and the method of concept of the value of the results is effective or not. The data used in this study is the Time Schedule, Cost Budget Plan, and weekly progress reports. From these data can produce BCWP and BCWS values. ACWP, with the help of Microsoft Excel, obtained CP, SV, CPI, SPI, and predicts completion of project costs and end times (ETC, EAC and ECD). From the results of the analysis of the time of the construction of the Satpol PP Building in Majalengka Regency until the 22nd week with a budget of Rp. 2,454,849,000, - resulting in a CPI of 1,1000, SPI obtained at 1,0266, EAC value of Rp. 2.23,681,459.98 and ECD amounted to 126, showing the estimated construction completion time of 126 days, which means the project progressed 24 days from the 150 day plan. Keywords: Earned Value Method, BCWP, BCWS, ETC, EAC
查看原文
分享 分享
微信好友 朋友圈 QQ好友 复制链接
本刊更多论文
成本和时间控制分析与结果价值概念方法在SATPOL PP区的构建项目MAJALENGKA
一个项目的成功离不开一系列的活动,包括计划、实施和监督阶段,这样设定的目标才能实现。为了在建设项目中取得成功,需要一种良好的技术或管理方法来提高工作效率、生产力和质量。与此相关的是,有必要在各个环节实施监督和控制措施,特别是成本和时间的控制。本研究是在Majalengka Regency Satpol PP Building Project中进行的,旨在确定项目的时间绩效和建筑施工项目的估计成本和时间,以及结果的价值概念的方法是否有效。本研究中使用的数据是时间进度表、成本预算计划和每周进度报告。从这些数据可以得到BCWP和BCWS值。ACWP借助Microsoft Excel获取CP、SV、CPI、SPI,预测项目成本完成情况和结束时间(ETC、EAC、ECD)。从Majalengka Regency的Satpol PP大楼的建设时间分析结果来看,预算为2,454,849,000卢比,直到第22周,导致CPI为1,1000,SPI为1,0266,EAC值为2,23,681,459.98卢比,ECD为126,显示预计施工完成时间为126天,这意味着该项目从150天的计划进展了24天。关键词:挣值法,BCWP, BCWS等,EAC
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 去求助
来源期刊
自引率
0.00%
发文量
0
期刊最新文献
EVALUASI KEGAGALAN HASIL PRODUKSI MESIN POTONG PLASTIK MENGGUNAKAN METODE DMAIC DI PT. XYZ PERANCANGAN PRODUK CONVERTIBLE BAG DENGAN PANEL SURYA YANG ERGONOMIS MENGGUNAKAN METODE QUALITY FUNCTION DEPLOYMENT (QFD) SISTEM INFORMASI PENDAFTARAN SISWA BARU DI SD ISLAM HASANKA PALANGKARAYA BERBASIS WEB PENGARUH KEKERASAN PADA CYBERBULLYING TERHADAP PERILAKU MASYARAKAT PADA MASA COVID-19 PERANCANGAN ALAT MONITORING KONDISI LINGKUNGAN DAN PREDIKSI CUACA BERTENAGA SURYA BERBASIS MIKROKONTROLER MENGGUNAKAN METODE FUZZY LOGIC
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
现在去查看 取消
×
提示
确定
0
微信
客服QQ
Book学术公众号 扫码关注我们
反馈
×
意见反馈
请填写您的意见或建议
请填写您的手机或邮箱
已复制链接
已复制链接
快去分享给好友吧!
我知道了
×
扫码分享
扫码分享
Book学术官方微信
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术
文献互助 智能选刊 最新文献 互助须知 联系我们:info@booksci.cn
Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。
Copyright © 2023 Book学术 All rights reserved.
ghs 京公网安备 11010802042870号 京ICP备2023020795号-1