Kajian Pengaruh Percepatan Waktu Pekerjaan Konstruksi Terhadap Biaya Proyek Bess Mansion Apartement Surabaya

A. Jaya, Kusnul Yakin, Maulidya Octaviani Bustamin
{"title":"Kajian Pengaruh Percepatan Waktu Pekerjaan Konstruksi Terhadap Biaya Proyek Bess Mansion Apartement Surabaya","authors":"A. Jaya, Kusnul Yakin, Maulidya Octaviani Bustamin","doi":"10.25139/jprs.v2i2.1930","DOIUrl":null,"url":null,"abstract":"In the implementation of construction project activities there are thre things that influence the success and failure of the project: time, cost and quality. The success of a project is usually seen from the timing of completion which is relatively short but without neglecting the quality of the project work. Appropriate and targeted project management and management are required to ensure the time, cost, and quality of the project. This is certainly to avoid a variety of undesirable things such as late settlement, swelling costs, quality failures, and so on that could have an impact on project failure and the emergence of the cost of fines. The purpose of this study is to calculate changes in cost and time of project implementation with alternatives to additional working hours (overtime) comparing the results between normal and cost changes after the addition of working hours (overtime). The data used in this research is secondary data obtained from contractor implementing. Arrow diagram The results program are critical paths and cost increases due to the addition of working hours (overtime) while the result of the time cost trade off method is the acceleration of duration and the increased cost due to the acceleration of duration in any accelerated activity. The results of this study indicate that the total project time and cost under normal conditions is 508 days at a cost of Rp 22.240.655.701  with the addition of 3 hours of overtime work in the duration of crashing 485 days and at a cost of Rp 23.252.220.373,34","PeriodicalId":111362,"journal":{"name":"Ge-STRAM: Jurnal Perencanaan dan Rekayasa Sipil","volume":"59 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2019-09-30","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Ge-STRAM: Jurnal Perencanaan dan Rekayasa Sipil","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.25139/jprs.v2i2.1930","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

Abstract

In the implementation of construction project activities there are thre things that influence the success and failure of the project: time, cost and quality. The success of a project is usually seen from the timing of completion which is relatively short but without neglecting the quality of the project work. Appropriate and targeted project management and management are required to ensure the time, cost, and quality of the project. This is certainly to avoid a variety of undesirable things such as late settlement, swelling costs, quality failures, and so on that could have an impact on project failure and the emergence of the cost of fines. The purpose of this study is to calculate changes in cost and time of project implementation with alternatives to additional working hours (overtime) comparing the results between normal and cost changes after the addition of working hours (overtime). The data used in this research is secondary data obtained from contractor implementing. Arrow diagram The results program are critical paths and cost increases due to the addition of working hours (overtime) while the result of the time cost trade off method is the acceleration of duration and the increased cost due to the acceleration of duration in any accelerated activity. The results of this study indicate that the total project time and cost under normal conditions is 508 days at a cost of Rp 22.240.655.701  with the addition of 3 hours of overtime work in the duration of crashing 485 days and at a cost of Rp 23.252.220.373,34
查看原文
分享 分享
微信好友 朋友圈 QQ好友 复制链接
本刊更多论文
研究建筑时间加速对贝丝公寓公寓项目成本的影响
在建设项目活动的实施中,影响项目成败的因素有三:时间、成本和质量。一个项目的成功通常从完成时间来看,完成时间相对较短,但不忽视项目工作的质量。需要适当的、有针对性的项目管理和管理,以确保项目的时间、成本和质量。这当然是为了避免各种不希望发生的事情,如延迟结算,膨胀成本,质量失败等,可能会对项目失败和罚款成本的出现产生影响。本研究的目的是计算替代额外工作时间(加班)的项目实施成本和时间的变化,比较增加工作时间(加班)后正常和成本变化的结果。本研究使用的数据是从承包商实施中获得的二手数据。结果程序是关键路径和由于增加工作时间(加班)而增加的成本,而时间成本权衡方法的结果是持续时间的加速和任何加速活动中由于持续时间的加速而增加的成本。本研究结果表明,在正常情况下,项目总时间和成本为508天,成本为22.240.655.701卢比,在485天的工期中,加上3小时的加班,成本为23.252.220.373,34卢比
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 去求助
来源期刊
自引率
0.00%
发文量
0
期刊最新文献
Pengaruh Pemanfaatan Limbah Kulit Kerang Bambu Sebagai Pengganti Sebagian Semen Terhadap Kuat Tekan Beton dengan Penggunaan Agregat Kasar Madura Studi Perbandingan Kadar Ni dan Fe Berdasarkan Sampel Cek Pit dan Sampel Cek Stock Pile Mining Nikel pada PT. Bintangdelapan Mineral Sulawesi Tengah Studi Perancangan Ruang Henti Khusus (RHK) Sepeda Motor Di Simpang Bersinyal (Studi Kasus Simpang Tugu Pecel, Simpang Ruang Terbuka Hijau (RTH) Kartini Dan Simpang Diponegoro Di Kota Madiun) Kajian Desain Struktur Beton Bertulang Dengan Struktur Baja (Studi Kasus Pada Pembangunan Gedung H Unitomo) Kajian Pengetahuan Dan Sikap Pekerja Terhadap Keselamatan Dan Kesehatan Kerja (Studi Kasus Pada Proyek Avian Tower Surabaya)
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
现在去查看 取消
×
提示
确定
0
微信
客服QQ
Book学术公众号 扫码关注我们
反馈
×
意见反馈
请填写您的意见或建议
请填写您的手机或邮箱
已复制链接
已复制链接
快去分享给好友吧!
我知道了
×
扫码分享
扫码分享
Book学术官方微信
Book学术文献互助
Book学术文献互助群
群 号:604180095
Book学术
文献互助 智能选刊 最新文献 互助须知 联系我们:info@booksci.cn
Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。
Copyright © 2023 Book学术 All rights reserved.
ghs 京公网安备 11010802042870号 京ICP备2023020795号-1