EVALUASI PENGENDALIAN BIAYA DAN WAKTU PADA PROYEK PEMBANGUNAN JALAN STRATEGIS MATANG SIJUEK-TRIENG PANTANG DENGAN MENGGUNAKAN METODE EARNED VALUE

Alfian Alfian
{"title":"EVALUASI PENGENDALIAN BIAYA DAN WAKTU PADA PROYEK PEMBANGUNAN JALAN STRATEGIS MATANG SIJUEK-TRIENG PANTANG DENGAN MENGGUNAKAN METODE EARNED VALUE","authors":"Alfian Alfian","doi":"10.30811/portal.v8i2.606","DOIUrl":null,"url":null,"abstract":"Time and cost are important aspects in a construcrtion project to achieve a desired success of the project. One way to control cost and time is to use earned value analysis (return value) that informs the data against the cost and time accurately and clearly. The purpose is to evaluate the amount of cost and usage time has been used in the on road paving projects in the Idi city sub district idi rayeuk district east aceh. The method used in this study is the concept of the value of the result (earned value analysis) examines the tendency of schedule variance and cost variance at a period during the project. By conducting this study of earned value project completion with BCWP =Rp.253,429,607.35 BCWS = Rp. 897,091, 753.ll and ACWP = Rp. 306,453,335. 79. Judging from the cost variance (CV) < 0, with cost performance index (CPI) <l in order to get project completion cost of Rp6,564,l 33,232. While aspects of the project Schedule is extra time -29.2% or 31 weeks ahead ofplan indicated SPI value < 1.Keywords : Cost, Performance, earned value, varians, index.","PeriodicalId":378653,"journal":{"name":"Portal: Jurnal Teknik Sipil","volume":"2 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2018-08-06","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"1","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Portal: Jurnal Teknik Sipil","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.30811/portal.v8i2.606","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 1

Abstract

Time and cost are important aspects in a construcrtion project to achieve a desired success of the project. One way to control cost and time is to use earned value analysis (return value) that informs the data against the cost and time accurately and clearly. The purpose is to evaluate the amount of cost and usage time has been used in the on road paving projects in the Idi city sub district idi rayeuk district east aceh. The method used in this study is the concept of the value of the result (earned value analysis) examines the tendency of schedule variance and cost variance at a period during the project. By conducting this study of earned value project completion with BCWP =Rp.253,429,607.35 BCWS = Rp. 897,091, 753.ll and ACWP = Rp. 306,453,335. 79. Judging from the cost variance (CV) < 0, with cost performance index (CPI)
查看原文
分享 分享
微信好友 朋友圈 QQ好友 复制链接
本刊更多论文
使用价值价值模型的策略,评估建筑成本和时间限制项目
时间和成本是建设项目取得预期成功的重要方面。控制成本和时间的一种方法是使用挣值分析(返回值),它可以准确而清晰地根据成本和时间通知数据。目的是对亚齐东部伊迪市街道伊迪拉耶克区道路铺装工程的成本和使用时间进行评价。本研究使用的方法是成果价值的概念(挣值分析),在项目的某一阶段检查进度差异和成本差异的趋势。通过对BCWP =Rp.253,429,607.35的挣值项目完成情况进行研究,BCWS =Rp. 897,091, 753。和ACWP = Rp. 306,453,335。79. 从成本方差(CV) < 0,且成本绩效指数(CPI) < 1可以得到项目完工成本为Rp6,564, l33,232。虽然项目进度方面是额外时间-29.2%或比计划提前31周,但SPI值< 1。关键词:成本,绩效,挣值,变量,指标。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 去求助
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
0
微信
客服QQ
Book学术公众号 扫码关注我们
反馈
×
意见反馈
请填写您的意见或建议
请填写您的手机或邮箱
已复制链接
已复制链接
快去分享给好友吧!
我知道了
×
扫码分享
扫码分享
Book学术官方微信
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术
文献互助 智能选刊 最新文献 互助须知 联系我们:info@booksci.cn
Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。
Copyright © 2023 Book学术 All rights reserved.
ghs 京公网安备 11010802042870号 京ICP备2023020795号-1