Penjadwalan Ulang Pekerjaan Finishing Proyek Shangrila Hotel Resort and Spa Menggunakan Metode PERT dan FLASH

Anita Trisiana, S. Arifin, Khoirunnisai Effendy
{"title":"Penjadwalan Ulang Pekerjaan Finishing Proyek Shangrila Hotel Resort and Spa Menggunakan Metode PERT dan FLASH","authors":"Anita Trisiana, S. Arifin, Khoirunnisai Effendy","doi":"10.19184/jrsl.v6i2.30590","DOIUrl":null,"url":null,"abstract":"A construction project in general always applies the concept of project management. The components of a construction project's success include cost, quality, and time. Planning and management of detailed scheduling of activities are necessary to complete a project to get the most optimal results within a predetermined time period. In the Shangrila Hotel Resort and Spa project, the remaining work is building finishing. The percentage of project completion was still at 3% in July 2019, so in this condition, rescheduling was carried out with the right approach to determine the project time. The Shangrila Hotel, Resort, and Spa project rescheduling use the PERT and FLASH methods. This method uses a probability percentage rather than uncertainty probability when analyzing project completion time. The rescheduling period is 272 days. The PERT method analysis based on activities on the critical path produces a probability percentage of 79.39%. Analysis of the FLASH method by considering all project activity relationships resulted in a probability percentage of 90%. In making a schedule, you can use modifications from other project management applications, such as BIM (Building Information Modeling). \nABSTRAK \nPada umumnya proyek konstruksi selalu menerapkan konsep manajemen proyek. Faktor keberhasilan suatu proyek kontruksi antara lain faktor biaya, mutu, dan waktu. Perencanaan dan manajemen penjadwalan terperinci tentang aktivitas kegiatan sangat diperlukan untuk menyelesaikan suatu proyek yang bertujuan untuk mendapatkan hasil yang paling optimal dalam jangka waktu yang telah ditentukan. Pada proyek Shangrila Hotel Resort and Spa memiliki pekerjaan proyek yang tersisa adalah pekerjaan finishing gedung. Persentase penyelesaian proyek masih 3% pada bulan Juli 2019, maka dalam kondisi ini dilakukan penjadwalan ulang dengan pendekatan yang tepat untuk menentukan waktu proyek. Penjadwalan ulang pada proyek Shangrila Hotel Resort and Spa menggunakan metode PERT dan FLASH. Metode ini menggunakan persentase posibilitas daripada probabilitas ketidakpastian ketika menganalisis waktu penyelesaian proyek. Penjadwalan ulang yang direncanakan adalah 272 hari. Analisa metode PERT berdasarkan kegiatan pada lintasan kritisnya menghasilkan persentase probabilitas sebesar 79,39%. Analisa metode FLASH dengan mempertimbangkan seluruh hubungan kegiatan proyek menghasilkan persentase posibilitas sebesar 90%. Dalam membuat rencana penjadwalan dapat menggunakan modifikasi aplikasi Manajemen Proyek yang lain seperti BIM (Building Information Modeling).","PeriodicalId":247229,"journal":{"name":"Jurnal Rekayasa Sipil dan Lingkungan","volume":"72 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2022-12-26","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Jurnal Rekayasa Sipil dan Lingkungan","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.19184/jrsl.v6i2.30590","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

Abstract

A construction project in general always applies the concept of project management. The components of a construction project's success include cost, quality, and time. Planning and management of detailed scheduling of activities are necessary to complete a project to get the most optimal results within a predetermined time period. In the Shangrila Hotel Resort and Spa project, the remaining work is building finishing. The percentage of project completion was still at 3% in July 2019, so in this condition, rescheduling was carried out with the right approach to determine the project time. The Shangrila Hotel, Resort, and Spa project rescheduling use the PERT and FLASH methods. This method uses a probability percentage rather than uncertainty probability when analyzing project completion time. The rescheduling period is 272 days. The PERT method analysis based on activities on the critical path produces a probability percentage of 79.39%. Analysis of the FLASH method by considering all project activity relationships resulted in a probability percentage of 90%. In making a schedule, you can use modifications from other project management applications, such as BIM (Building Information Modeling). ABSTRAK Pada umumnya proyek konstruksi selalu menerapkan konsep manajemen proyek. Faktor keberhasilan suatu proyek kontruksi antara lain faktor biaya, mutu, dan waktu. Perencanaan dan manajemen penjadwalan terperinci tentang aktivitas kegiatan sangat diperlukan untuk menyelesaikan suatu proyek yang bertujuan untuk mendapatkan hasil yang paling optimal dalam jangka waktu yang telah ditentukan. Pada proyek Shangrila Hotel Resort and Spa memiliki pekerjaan proyek yang tersisa adalah pekerjaan finishing gedung. Persentase penyelesaian proyek masih 3% pada bulan Juli 2019, maka dalam kondisi ini dilakukan penjadwalan ulang dengan pendekatan yang tepat untuk menentukan waktu proyek. Penjadwalan ulang pada proyek Shangrila Hotel Resort and Spa menggunakan metode PERT dan FLASH. Metode ini menggunakan persentase posibilitas daripada probabilitas ketidakpastian ketika menganalisis waktu penyelesaian proyek. Penjadwalan ulang yang direncanakan adalah 272 hari. Analisa metode PERT berdasarkan kegiatan pada lintasan kritisnya menghasilkan persentase probabilitas sebesar 79,39%. Analisa metode FLASH dengan mempertimbangkan seluruh hubungan kegiatan proyek menghasilkan persentase posibilitas sebesar 90%. Dalam membuat rencana penjadwalan dapat menggunakan modifikasi aplikasi Manajemen Proyek yang lain seperti BIM (Building Information Modeling).
查看原文
分享 分享
微信好友 朋友圈 QQ好友 复制链接
本刊更多论文
重新安排香格里拉酒店度假村和水疗项目的完成工作使用第1和FLASH方法
一个建设项目一般都要运用项目管理的概念。建设项目成功的要素包括成本、质量和时间。计划和管理详细的活动日程安排是必要的,以完成一个项目,在预定的时间内获得最优的结果。在香格里拉酒店度假及水疗项目中,剩下的工作是建筑装修。2019年7月,项目完成率仍为3%,因此在这种情况下,采用正确的方法进行重新调度以确定项目时间。香格里拉酒店、度假村和水疗中心项目的重新调度使用PERT和FLASH方法。该方法在分析项目完成时间时使用概率百分比而不是不确定性概率。重调度周期为272天。基于关键路径上活动的PERT方法分析产生的概率百分比为79.39%。通过考虑所有项目活动关系对FLASH方法进行分析,得出的概率百分比为90%。在制定时间表时,您可以使用来自其他项目管理应用程序的修改,例如BIM(建筑信息建模)。摘要/ abstract摘要:Pada umnya项目是指销售管理项目。Faktor keberhasilan suatu proyek kontruksi antara为biaya, mutu, dan waktu。长年累月的管理、管理、管理、管理、管理、管理、管理、管理、管理、管理、管理、管理、管理、管理、管理、管理、管理、管理、管理、管理、管理、管理、管理、管理、管理、管理、管理、管理、管理等。篇proyek香格里拉酒店度假村和水疗memiliki pekerjaan proyek杨tersisa adalah pekerjaan完成gedung。在2019年7月1日,我用了3个月的时间,我用了3个月的时间,我用了3个月的时间,我用了3个月的时间,我用了3个月的时间,我用了3个月的时间,我用了3个月的时间,我用了3个月的时间,我用了3个月的时间。彭杰瓦兰·乌朗帕达·普拉耶克,香格里拉酒店蒙古纳坎度假酒店,帕特丹·FLASH。Metode ini menggunakan表示:可能性、概率、ketika menganalis、ketika menganalis、waktu penyelesan proyek。Penjadwalan ulang yang direncanakan adalah 272 hari。分析方法PERT berdasarkan kegiatan patada lintasan kritisnya menghasilkan的概率为79,39%。分析方法表明,FLASH登登门的概率为90%。Dalam成员rencana penjadwalan dapat menggunakan modifikasi应用管理Proyek yang分别介绍了BIM(建筑信息模型)。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 去求助
来源期刊
自引率
0.00%
发文量
0
期刊最新文献
Penilaian Kriteria Green Building Pada Gedung Pusat Layanan Haji dan Umrah Terpadu (PLHUT) Kota Langsa Berdasarkan Penilaian Greenship Identifikasi dan Analisis Efektivitas Penanganan Blackspot di Jalan Perkotaan (Studi Kasus: Kota Depok) Perancangan Rainwater Harvesting dengan Communal Rainwater Tank di Desa Baturinggit Kabupaten Karangasem Pengembangan Sistem Lidar Pendeteksi Jarak Aman Berkendara Analisis Perubahan Tata Guna Lahan Pada DAS Tanggul Menggunakan Remote Sensing
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
现在去查看 取消
×
提示
确定
0
微信
客服QQ
Book学术公众号 扫码关注我们
反馈
×
意见反馈
请填写您的意见或建议
请填写您的手机或邮箱
已复制链接
已复制链接
快去分享给好友吧!
我知道了
×
扫码分享
扫码分享
Book学术官方微信
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术
文献互助 智能选刊 最新文献 互助须知 联系我们:info@booksci.cn
Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。
Copyright © 2023 Book学术 All rights reserved.
ghs 京公网安备 11010802042870号 京ICP备2023020795号-1