Corrosion of carbon steel rebar in binary blended concrete with accelerated chloride transport

Kazi Naimul Hoque, Francisco Presuel-Moreno, Manzurul Nazim
{"title":"Corrosion of carbon steel rebar in binary blended concrete with accelerated chloride transport","authors":"Kazi Naimul Hoque, Francisco Presuel-Moreno, Manzurul Nazim","doi":"10.1186/s43065-023-00092-7","DOIUrl":null,"url":null,"abstract":"Samples with two different binary blended concrete mixes were prepared, one containing cement replacement of 50% slag (referred here as SL mix) and the other containing cement replacement of 20% fly ash (termed here as FA mix). The water to cementitious ratio used to produce concrete specimens was 0.41. On the top surface of each specimen, various reservoir lengths that ranged from 2.5 cm to 17.5 cm were fitted, and these reservoirs were filled with a 10% NaCl solution. Electromigration was used to accelerate the transport of chlorides, with an applied potential of 9 V at first, and subsequently reduced to 3 V after about a week. The electromigration was applied for a short period (few weeks to a couple of months). For a period of about 1100 days, the corrosion related parameters such as concrete solution resistance, rebar potential, and corrosion current were monitored via the rebar potential measurements, linear polarization resistance (LPR) and electrochemical impedance spectroscopy (EIS) measurements, the latter used only to obtain the solution resistance. The corrosion current values determined through experimental observations were then converted to mass loss using Faraday’s law. The readings of corrosion current values (last 7 sets of readings) as well as the calculated mass loss values were found to be larger for the rebars embedded in specimens prepared with SL mix, followed by rebars embedded in specimens prepared with FA mix. Corrosion current and calculated mass loss values in general tended to increase with increasing solution reservoir lengths. No cracks or corrosion products that reached the surface of the concrete were observed on the specimens for the duration of the reported monitored propagation period. This study offers a framework for future studies on accelerated steel corrosion in concrete.","PeriodicalId":73793,"journal":{"name":"Journal of infrastructure preservation and resilience","volume":null,"pages":null},"PeriodicalIF":0.0000,"publicationDate":"2023-11-29","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"1","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Journal of infrastructure preservation and resilience","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1186/s43065-023-00092-7","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 1

Abstract

Samples with two different binary blended concrete mixes were prepared, one containing cement replacement of 50% slag (referred here as SL mix) and the other containing cement replacement of 20% fly ash (termed here as FA mix). The water to cementitious ratio used to produce concrete specimens was 0.41. On the top surface of each specimen, various reservoir lengths that ranged from 2.5 cm to 17.5 cm were fitted, and these reservoirs were filled with a 10% NaCl solution. Electromigration was used to accelerate the transport of chlorides, with an applied potential of 9 V at first, and subsequently reduced to 3 V after about a week. The electromigration was applied for a short period (few weeks to a couple of months). For a period of about 1100 days, the corrosion related parameters such as concrete solution resistance, rebar potential, and corrosion current were monitored via the rebar potential measurements, linear polarization resistance (LPR) and electrochemical impedance spectroscopy (EIS) measurements, the latter used only to obtain the solution resistance. The corrosion current values determined through experimental observations were then converted to mass loss using Faraday’s law. The readings of corrosion current values (last 7 sets of readings) as well as the calculated mass loss values were found to be larger for the rebars embedded in specimens prepared with SL mix, followed by rebars embedded in specimens prepared with FA mix. Corrosion current and calculated mass loss values in general tended to increase with increasing solution reservoir lengths. No cracks or corrosion products that reached the surface of the concrete were observed on the specimens for the duration of the reported monitored propagation period. This study offers a framework for future studies on accelerated steel corrosion in concrete.
查看原文
分享 分享
微信好友 朋友圈 QQ好友 复制链接
本刊更多论文
氯离子加速输送对二元混合混凝土中碳钢钢筋腐蚀的影响
制备了两种不同的二元混合混凝土,一种是水泥置换50%矿渣(简称SL),另一种是水泥置换20%粉煤灰(简称FA)。用于制作混凝土试件的水胶比为0.41。在每个样品的上表面都安装了长度从2.5 cm到17.5 cm不等的储层,这些储层被10%的NaCl溶液填充。电迁移用于加速氯化物的迁移,最初的施加电位为9v,随后在大约一周后降至3v。电迁移的应用时间很短(几周到几个月)。在1100天的时间里,通过钢筋电位测量、线性极化电阻(LPR)和电化学阻抗谱(EIS)测量(后者仅用于获得溶液电阻),监测混凝土溶液电阻、钢筋电位和腐蚀电流等腐蚀相关参数。通过实验观察确定的腐蚀电流值,然后使用法拉第定律转换为质量损失。结果表明,SL混合料中预埋钢筋的腐蚀电流值(前7组读数)和计算的质量损失值较大,FA混合料中预埋钢筋的腐蚀电流值次之。腐蚀电流和计算的质量损失值一般随溶液储层长度的增加而增加。在报告的监测传播期间,没有观察到试件上的裂缝或腐蚀产物到达混凝土表面。本研究为今后混凝土中钢筋加速腐蚀的研究提供了一个框架。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 去求助
来源期刊
CiteScore
5.70
自引率
0.00%
发文量
0
审稿时长
13 weeks
期刊最新文献
Automated crack identification in structures using acoustic waveforms and deep learning Inspection prioritization of gravity sanitary sewer systems using supervised machine learning algorithms Numerical investigation on the deformation of railway embankment under normal faulting Evaluation of the physical characteristics of reinforced concrete subject to corrosion using a poro-elastic acoustic model inversion technique applied to ultrasonic measurements An investigation of belief-free DRL and MCTS for inspection and maintenance planning
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
现在去查看 取消
×
提示
确定
0
微信
客服QQ
Book学术公众号 扫码关注我们
反馈
×
意见反馈
请填写您的意见或建议
请填写您的手机或邮箱
已复制链接
已复制链接
快去分享给好友吧!
我知道了
×
扫码分享
扫码分享
Book学术官方微信
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术
文献互助 智能选刊 最新文献 互助须知 联系我们:info@booksci.cn
Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。
Copyright © 2023 Book学术 All rights reserved.
ghs 京公网安备 11010802042870号 京ICP备2023020795号-1