Diem-Thuy Vien-Nguyen, Phi-Hung Tran, Quynh-Lam Ngoc-Le, Ngoc-Hien Do
{"title":"Combination of genetic algorithm and shifting bottleneck heuristics to solve a job shop scheduling problem in wood processing company","authors":"Diem-Thuy Vien-Nguyen, Phi-Hung Tran, Quynh-Lam Ngoc-Le, Ngoc-Hien Do","doi":"10.30574/wjaets.2024.11.1.0017","DOIUrl":null,"url":null,"abstract":"The scheduling problem has always been the concern of most companies in the flexible Job shop or Job shop environments because of its complexity. It is really a challenge for researchers to solve or find out the optimum solution. The lead time production at Teak Woods line in a wood processing company, a case study, faced with about 80% of orders which could not be done on time, although its capacity meet requirements. Therefore, it is very useful and necessary to set up a production scheduling model in order to reduce production time and synchronize the product’s parts through efficient modulation in an optimum sequence of jobs on the shopfloor. A combination of Genetic Algorithm and Shifting Bottleneck Heuristics was used to find out high quality solutions. It shows that the productivity increased from 2.32 m3/day to 4.3 m3/day (up 98.27%); Processing time was reduced from 3248.6 minutes to 1352.1 minutes (down 58.38%); The sync time decreased from 7554.8 minutes to 350.8 minutes (down 95.36%).","PeriodicalId":275182,"journal":{"name":"World Journal of Advanced Engineering Technology and Sciences","volume":"13 8","pages":""},"PeriodicalIF":0.0000,"publicationDate":"2024-01-30","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"World Journal of Advanced Engineering Technology and Sciences","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.30574/wjaets.2024.11.1.0017","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0
Abstract
The scheduling problem has always been the concern of most companies in the flexible Job shop or Job shop environments because of its complexity. It is really a challenge for researchers to solve or find out the optimum solution. The lead time production at Teak Woods line in a wood processing company, a case study, faced with about 80% of orders which could not be done on time, although its capacity meet requirements. Therefore, it is very useful and necessary to set up a production scheduling model in order to reduce production time and synchronize the product’s parts through efficient modulation in an optimum sequence of jobs on the shopfloor. A combination of Genetic Algorithm and Shifting Bottleneck Heuristics was used to find out high quality solutions. It shows that the productivity increased from 2.32 m3/day to 4.3 m3/day (up 98.27%); Processing time was reduced from 3248.6 minutes to 1352.1 minutes (down 58.38%); The sync time decreased from 7554.8 minutes to 350.8 minutes (down 95.36%).