Status of Plant Construction in ITER Tokamak Complex Buildings

IF 1.5 4区 物理与天体物理 Q3 PHYSICS, FLUIDS & PLASMAS IEEE Transactions on Plasma Science Pub Date : 2024-07-31 DOI:10.1109/TPS.2024.3430481
Ingo Kuehn;David Beltran;Pascal De Boe;Giovanni Di Giuseppe;Federico Fortunato;Armand Gjoklaj;Duco Jansen;Claudio La Barbera;Alfonso Marquez;Sergio Orlandi;Bertrand Roques;Seiji Terada;Nick Woods
{"title":"Status of Plant Construction in ITER Tokamak Complex Buildings","authors":"Ingo Kuehn;David Beltran;Pascal De Boe;Giovanni Di Giuseppe;Federico Fortunato;Armand Gjoklaj;Duco Jansen;Claudio La Barbera;Alfonso Marquez;Sergio Orlandi;Bertrand Roques;Seiji Terada;Nick Woods","doi":"10.1109/TPS.2024.3430481","DOIUrl":null,"url":null,"abstract":"The ITER Project is currently in its construction phase. All plant systems required for the first plasma phase, including captive components in the Tokamak Complex buildings, are being installed. The main activities of this construction phase are in the Tokamak and Diagnostic building, now that the civil structure of the Tritium building roof is finalized. In order to launch the construction phase of the plant systems, the engineering has to be completed and documentation compiled in the form of engineering work packages (EWPs). These EWPs need to be approved, in line with the construction schedule, and must then be provided to the construction contractor for them to prepare the detailed installation work packages (IWPs). The material has to be made available and the manufacturing of the systems, structures, and components (SSCs) has to be completed, according to the requirements, as defined in the technical specifications. The Tokamak Complex as a facility has to be managed accordingly, to allow the construction of multiple building openings and penetrations. Installation of piping and mechanical systems, as well as electrical instrumentation and control (I&C) and cable pulling can then take place. This article describes the handover from engineering to the construction domain, utilizing the “EWP Toolbox” in order to provide the required content in the EWPs. The simplifications implemented in the document production have resulted in an overall cost reduction. This demonstrates that processes must be as simple as possible, providing the necessary documentation at an appropriate level of information and quality. The process of material procurement, on-time, for a large-scale project is described with the mitigation categories herein defined. The constraints to be considered in the construction phase are also described, along with the daily management of the facility and the environmental conditions that must be respected for the Tokamak machine assembly. Due to the sheer size and scale of the ITER project, these aspects can all be considered unique. The effectiveness of the visual management and the coordination of operations are, in the context of an international project such as ITER, described with “Lessons Learned” up to the construction phase provided. This article is concluded with a summary of the current status of the construction phase in the Tokamak Complex with some figures relating to the various building levels.","PeriodicalId":450,"journal":{"name":"IEEE Transactions on Plasma Science","volume":"52 9","pages":"3528-3534"},"PeriodicalIF":1.5000,"publicationDate":"2024-07-31","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"IEEE Transactions on Plasma Science","FirstCategoryId":"101","ListUrlMain":"https://ieeexplore.ieee.org/document/10618916/","RegionNum":4,"RegionCategory":"物理与天体物理","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"Q3","JCRName":"PHYSICS, FLUIDS & PLASMAS","Score":null,"Total":0}
引用次数: 0

Abstract

The ITER Project is currently in its construction phase. All plant systems required for the first plasma phase, including captive components in the Tokamak Complex buildings, are being installed. The main activities of this construction phase are in the Tokamak and Diagnostic building, now that the civil structure of the Tritium building roof is finalized. In order to launch the construction phase of the plant systems, the engineering has to be completed and documentation compiled in the form of engineering work packages (EWPs). These EWPs need to be approved, in line with the construction schedule, and must then be provided to the construction contractor for them to prepare the detailed installation work packages (IWPs). The material has to be made available and the manufacturing of the systems, structures, and components (SSCs) has to be completed, according to the requirements, as defined in the technical specifications. The Tokamak Complex as a facility has to be managed accordingly, to allow the construction of multiple building openings and penetrations. Installation of piping and mechanical systems, as well as electrical instrumentation and control (I&C) and cable pulling can then take place. This article describes the handover from engineering to the construction domain, utilizing the “EWP Toolbox” in order to provide the required content in the EWPs. The simplifications implemented in the document production have resulted in an overall cost reduction. This demonstrates that processes must be as simple as possible, providing the necessary documentation at an appropriate level of information and quality. The process of material procurement, on-time, for a large-scale project is described with the mitigation categories herein defined. The constraints to be considered in the construction phase are also described, along with the daily management of the facility and the environmental conditions that must be respected for the Tokamak machine assembly. Due to the sheer size and scale of the ITER project, these aspects can all be considered unique. The effectiveness of the visual management and the coordination of operations are, in the context of an international project such as ITER, described with “Lessons Learned” up to the construction phase provided. This article is concluded with a summary of the current status of the construction phase in the Tokamak Complex with some figures relating to the various building levels.
查看原文
分享 分享
微信好友 朋友圈 QQ好友 复制链接
本刊更多论文
国际热核聚变实验堆托卡马克建筑群的工厂建设状况
ITER项目目前处于建设阶段。第一等离子体阶段所需的所有设备系统,包括托卡马克综合大楼的专用组件,正在安装中。这个建设阶段的主要活动是在托卡马克和诊断大楼,现在Tritium建筑屋顶的土木结构已经完成。为了启动工厂系统的建设阶段,必须完成工程并以工程工作包(ewp)的形式编制文件。这些ewp需要根据施工进度获得批准,然后必须提供给施工承包商,以便他们准备详细的安装工作包(IWPs)。材料必须可用,系统、结构和部件(ssc)的制造必须根据技术规范中定义的要求完成。托卡马克综合体作为一个设施,必须进行相应的管理,以允许建造多个建筑开口和穿透。然后可以进行管道和机械系统的安装,以及电气仪表和控制(I&C)和电缆拉拔。本文描述了从工程到施工领域的交接,利用“EWP工具箱”在EWP中提供所需的内容。在文件制作中实施的简化导致了总体成本的降低。这表明过程必须尽可能简单,在适当的信息水平和质量上提供必要的文档。描述了大型项目按时采购材料的过程,并在此定义了缓解类别。还描述了在施工阶段要考虑的限制,以及设施的日常管理和托卡马克机器组装必须尊重的环境条件。由于ITER项目的庞大规模,这些方面都可以被认为是独一无二的。在国际项目(如ITER)的背景下,可视化管理和操作协调的有效性用“经验教训”来描述,直至提供建设阶段。本文最后总结了托卡马克综合大楼建设阶段的现状,并提供了与不同建筑水平有关的一些数字。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 去求助
来源期刊
IEEE Transactions on Plasma Science
IEEE Transactions on Plasma Science 物理-物理:流体与等离子体
CiteScore
3.00
自引率
20.00%
发文量
538
审稿时长
3.8 months
期刊介绍: The scope covers all aspects of the theory and application of plasma science. It includes the following areas: magnetohydrodynamics; thermionics and plasma diodes; basic plasma phenomena; gaseous electronics; microwave/plasma interaction; electron, ion, and plasma sources; space plasmas; intense electron and ion beams; laser-plasma interactions; plasma diagnostics; plasma chemistry and processing; solid-state plasmas; plasma heating; plasma for controlled fusion research; high energy density plasmas; industrial/commercial applications of plasma physics; plasma waves and instabilities; and high power microwave and submillimeter wave generation.
期刊最新文献
IEEE Transactions on Plasma Science information for authors Blank Page IEEE Transactions on Plasma Science Special Issue on Discharges and Electrical Insulation in Vacuum Special Issue on the 40th PSSI National Symposium on Plasma Science and Technology (PLASMA 2025) Special Issue on Selected Papers from APSPT-14 May 2027
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
现在去查看 取消
×
提示
确定
0
微信
客服QQ
Book学术公众号 扫码关注我们
反馈
×
意见反馈
请填写您的意见或建议
请填写您的手机或邮箱
已复制链接
已复制链接
快去分享给好友吧!
我知道了
×
扫码分享
扫码分享
Book学术官方微信
Book学术文献互助
Book学术文献互助群
群 号:604180095
Book学术
文献互助 智能选刊 最新文献 互助须知 联系我们:info@booksci.cn
Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。
Copyright © 2023 Book学术 All rights reserved.
ghs 京公网安备 11010802042870号 京ICP备2023020795号-1