Optimizing the delivery schedule of equipment in a project environment considering resource leveling of storage space and its constraint: a case study

Debadyuti Das, Aditya Singh
{"title":"Optimizing the delivery schedule of equipment in a project environment considering resource leveling of storage space and its constraint: a case study","authors":"Debadyuti Das, Aditya Singh","doi":"10.1108/jamr-02-2023-0045","DOIUrl":null,"url":null,"abstract":"PurposeThe present work seeks to determine the optimal delivery schedule of equipment at a project site in the backdrop of limited storage space, at a minimum cost, and without disturbing the overall project schedule. In addition, the optimized delivery schedule helps in minimizing the fluctuating requirements of space at the project site across the entire project lifespan.Design/methodology/approachThe study is carried out at a Steel plant operating in a constrained space but undergoing a production capacity expansion. The problem motivated us to explore the possibility of postponing the delivery dates of certain equipment closer to the erection dates without compromising on the project schedule. Given the versatility of linear programming models in dealing with such schedule optimization problems, the authors formulated the above problem as a Zero-One Integer Linear Programming problem.FindingsThe model is implemented for all the new equipment arriving for two major units – the Hot Strip Mill (HSM) and the Blast Furnace (BF). It generates an optimized delivery schedule by delaying the delivery of some equipment by a certain number of periods, without compromising the overall project schedule and at a minimum storage cost. The average space utilization increases by 25.85 and 14.79% in HSM and BF units respectively. The fluctuations in space requirements are reduced substantially in both units.Originality/valueThe study shows a timeline in the form of a Gantt chart for the delivery of equipment, storage of equipment across different periods, and the number of periods for which the delivery of certain equipment needs to be postponed. The study uses linearly increasing storage costs with the increase in the number of periods for storage of the equipment in the temporary shed.HighlightsDetermined the optimal delivery schedule of the equipment in a project environment in the backdrop of limited storage space in the project site.Formulated the above problem as a Zero-One Integer Linear Programming (ILP) problem.The average space utilization has increased by 25.85 and 14.79% in HSM and BF units respectively.The optimized delivery schedule helps in reducing the fluctuations in space requirements substantially across the entire lifespan of the project.The timeline of delivery of equipment, storage of equipment across different periods and periods of postponement of the equipment are shown in the form of a Gantt Chart.","PeriodicalId":46158,"journal":{"name":"Journal of Advances in Management Research","volume":" ","pages":""},"PeriodicalIF":2.6000,"publicationDate":"2023-06-07","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Journal of Advances in Management Research","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1108/jamr-02-2023-0045","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"Q3","JCRName":"MANAGEMENT","Score":null,"Total":0}
引用次数: 0

Abstract

PurposeThe present work seeks to determine the optimal delivery schedule of equipment at a project site in the backdrop of limited storage space, at a minimum cost, and without disturbing the overall project schedule. In addition, the optimized delivery schedule helps in minimizing the fluctuating requirements of space at the project site across the entire project lifespan.Design/methodology/approachThe study is carried out at a Steel plant operating in a constrained space but undergoing a production capacity expansion. The problem motivated us to explore the possibility of postponing the delivery dates of certain equipment closer to the erection dates without compromising on the project schedule. Given the versatility of linear programming models in dealing with such schedule optimization problems, the authors formulated the above problem as a Zero-One Integer Linear Programming problem.FindingsThe model is implemented for all the new equipment arriving for two major units – the Hot Strip Mill (HSM) and the Blast Furnace (BF). It generates an optimized delivery schedule by delaying the delivery of some equipment by a certain number of periods, without compromising the overall project schedule and at a minimum storage cost. The average space utilization increases by 25.85 and 14.79% in HSM and BF units respectively. The fluctuations in space requirements are reduced substantially in both units.Originality/valueThe study shows a timeline in the form of a Gantt chart for the delivery of equipment, storage of equipment across different periods, and the number of periods for which the delivery of certain equipment needs to be postponed. The study uses linearly increasing storage costs with the increase in the number of periods for storage of the equipment in the temporary shed.HighlightsDetermined the optimal delivery schedule of the equipment in a project environment in the backdrop of limited storage space in the project site.Formulated the above problem as a Zero-One Integer Linear Programming (ILP) problem.The average space utilization has increased by 25.85 and 14.79% in HSM and BF units respectively.The optimized delivery schedule helps in reducing the fluctuations in space requirements substantially across the entire lifespan of the project.The timeline of delivery of equipment, storage of equipment across different periods and periods of postponement of the equipment are shown in the form of a Gantt Chart.
查看原文
分享 分享
微信好友 朋友圈 QQ好友 复制链接
本刊更多论文
考虑存储空间资源均衡及其约束的项目环境下设备交付进度优化:一个案例研究
目的本工作旨在在存储空间有限的情况下,以最低的成本,在不干扰整个项目进度的情况下确定项目现场设备的最佳交付时间表。此外,优化的交付时间表有助于在整个项目使用寿命内最大限度地减少项目现场对空间的波动需求。设计/方法/方法该研究是在一家钢铁厂进行的,该钢铁厂在有限的空间内运营,但正在进行产能扩张。这个问题促使我们探索在不影响项目进度的情况下,将某些设备的交付日期推迟到更接近安装日期的可能性。考虑到线性规划模型在处理此类调度优化问题时的通用性,作者将上述问题公式化为零一整数线性规划问题。发现该模型适用于两个主要机组——热轧带钢机(HSM)和高炉(BF)的所有新设备。它通过将某些设备的交付延迟一定数量的周期来生成优化的交付时间表,而不会影响整个项目进度并以最低的存储成本。HSM和BF装置的平均空间利用率分别提高了25.85%和14.79%。两个单元的空间需求波动都大大减少。独创性/价值该研究以甘特图的形式显示了设备交付、不同时期的设备存储以及某些设备需要推迟交付的时期数量的时间表。该研究使用了随着设备在临时棚中储存周期的增加而线性增加的储存成本。亮点在项目现场存储空间有限的背景下,确定了项目环境中设备的最佳交付时间表。将上述问题公式化为零一整数线性规划(ILP)问题。HSM和BF装置的平均空间利用率分别提高了25.85%和14.79%。优化的交付时间表有助于在项目的整个生命周期内大幅减少空间需求的波动。设备交付时间表、不同时期的设备储存以及设备延期期以甘特图的形式显示。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 去求助
来源期刊
CiteScore
6.50
自引率
3.20%
发文量
30
期刊最新文献
The type of supplier involvement in new product development in the automotive industry: metaheuristic-based K-means clustering and analytic hierarchical process methods Resilience of developing economies to external shocks: empirical evidence from CEMAC countries Unbraiding the effect of policy benefits on subjective well-being: the mediating role of work-related well-being Development and psychometric validation of a scale for sources of resistance to change in higher education institutions Assessment of bus fleet service quality: a graph theoretical approach
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
现在去查看 取消
×
提示
确定
0
微信
客服QQ
Book学术公众号 扫码关注我们
反馈
×
意见反馈
请填写您的意见或建议
请填写您的手机或邮箱
已复制链接
已复制链接
快去分享给好友吧!
我知道了
×
扫码分享
扫码分享
Book学术官方微信
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术
文献互助 智能选刊 最新文献 互助须知 联系我们:info@booksci.cn
Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。
Copyright © 2023 Book学术 All rights reserved.
ghs 京公网安备 11010802042870号 京ICP备2023020795号-1