Project ambidexterity: case of recovering schedule delay in a brownfield airport project in India

K. Iyer, P. Banerjee
{"title":"Project ambidexterity: case of recovering schedule delay in a brownfield airport project in India","authors":"K. Iyer, P. Banerjee","doi":"10.1515/otmcj-2016-0012","DOIUrl":null,"url":null,"abstract":"Abstract Planning deficiencies and consequent execution delays are likely to persist in infrastructure development projects. However, recovery of schedule delay is a less researched area. This case research, using a two-stage inquiry modeled on the grounded theory, studied the schedule delay recovery during the execution phase of a brownfield airport construction project. The analyses generated contextual evidence and ambidexterity was found to be the key underlying phenomenon for successful recovery measures. The empirical learning was validated with literature and can be used by practitioners looking to institute schedule recovery measures.","PeriodicalId":42309,"journal":{"name":"Organization Technology and Management in Construction","volume":"8 1","pages":"1464 - 1481"},"PeriodicalIF":1.6000,"publicationDate":"2016-12-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"https://sci-hub-pdf.com/10.1515/otmcj-2016-0012","citationCount":"1","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Organization Technology and Management in Construction","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1515/otmcj-2016-0012","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"Q3","JCRName":"MANAGEMENT","Score":null,"Total":0}
引用次数: 1

Abstract

Abstract Planning deficiencies and consequent execution delays are likely to persist in infrastructure development projects. However, recovery of schedule delay is a less researched area. This case research, using a two-stage inquiry modeled on the grounded theory, studied the schedule delay recovery during the execution phase of a brownfield airport construction project. The analyses generated contextual evidence and ambidexterity was found to be the key underlying phenomenon for successful recovery measures. The empirical learning was validated with literature and can be used by practitioners looking to institute schedule recovery measures.
查看原文
分享 分享
微信好友 朋友圈 QQ好友 复制链接
本刊更多论文
项目的两面性:印度棕地机场项目恢复进度延迟的案例
在基础设施开发项目中,规划缺陷和随之而来的执行延迟可能会持续存在。然而,进度延迟的恢复是一个研究较少的领域。本案例研究采用基于扎根理论的两阶段调查模型,研究棕地机场建设项目执行阶段的进度延误恢复问题。分析产生了背景证据,发现二元性是成功恢复措施的关键潜在现象。通过文献验证了经验学习,并且可以被寻求制定时间表恢复措施的从业者使用。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 去求助
来源期刊
CiteScore
3.10
自引率
0.00%
发文量
8
审稿时长
16 weeks
期刊最新文献
Project success and critical success factors of construction projects: project practitioners’ perspectives Exploring the social legitimacy of urban road PPPs in Nigeria Capability improvement measures of the public sector for implementation of building information modeling in construction projects Linking life cycle BIM data to a facility management system using Revit Dynamo Investigation of the poor-quality practices on building construction sites in Malaysia
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
现在去查看 取消
×
提示
确定
0
微信
客服QQ
Book学术公众号 扫码关注我们
反馈
×
意见反馈
请填写您的意见或建议
请填写您的手机或邮箱
已复制链接
已复制链接
快去分享给好友吧!
我知道了
×
扫码分享
扫码分享
Book学术官方微信
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术
文献互助 智能选刊 最新文献 互助须知 联系我们:info@booksci.cn
Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。
Copyright © 2023 Book学术 All rights reserved.
ghs 京公网安备 11010802042870号 京ICP备2023020795号-1