Odchylenia i wykonania budżetu oraz harmonogramu przedsięwzięć budowlanych monitorowanych przez nadzór bankowy na przykładzie budynków zbiorowego zamieszkania
{"title":"Odchylenia i wykonania budżetu oraz harmonogramu przedsięwzięć budowlanych monitorowanych przez nadzór bankowy na przykładzie budynków zbiorowego zamieszkania","authors":"J. Konior, M. Szóstak","doi":"10.22630/pniks.2020.29.4.42","DOIUrl":null,"url":null,"abstract":"Time and cost are key elements that determine the success or failure of construction projects. The aim of the article is to analyze and assessment of the course of various construction projects in the field deviations and implementation of the budget and schedule of construction projects. Calculations made in accordance with the Earned Value Method methodology allowed the assessment of the actual cost of the work performed and scheduled for the analyzed construction projects. The data for analysis was obtained from the authors' own experience and professional work. The authors carried out Bank Investment Supervision in the years 2006 - 2019 on behalf of the banks that grant investment loans for non-public contracts.","PeriodicalId":38397,"journal":{"name":"Scientific Review Engineering and Environmental Sciences","volume":"1 1","pages":""},"PeriodicalIF":0.0000,"publicationDate":"2020-12-16","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Scientific Review Engineering and Environmental Sciences","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.22630/pniks.2020.29.4.42","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"Q3","JCRName":"Earth and Planetary Sciences","Score":null,"Total":0}
引用次数: 0
Abstract
Time and cost are key elements that determine the success or failure of construction projects. The aim of the article is to analyze and assessment of the course of various construction projects in the field deviations and implementation of the budget and schedule of construction projects. Calculations made in accordance with the Earned Value Method methodology allowed the assessment of the actual cost of the work performed and scheduled for the analyzed construction projects. The data for analysis was obtained from the authors' own experience and professional work. The authors carried out Bank Investment Supervision in the years 2006 - 2019 on behalf of the banks that grant investment loans for non-public contracts.
期刊介绍:
Scientific Review Engineering and Environmental Sciences [Przegląd Naukowy Inżynieria i Kształtowanie Środowiska] covers broad area of knowledge and practice on fields such as: sustainable development, landscaping of non-urbanized lands, environmental engineering, construction projects engineering land management, protection and land reclamation, environmental impact of investments, ecology, hydrology and water management, ground-water monitoring and restoration, geotechnical engineering, meteorology and connecting subjects. Authors are welcome to submit theoretical and practice-oriented papers containing detailed case studies within above mentioned disciplines. However, theoretical papers should contain part with practical application of the theory presented. Papers (in Polish or English languages) are accepted for publication after obtaining positive opinions of two reviewers. Papers published elsewhere are not accepted.