{"title":"Replacing the deck slab on a post-tensioned, prestressed-concrete composite girder bridge in Japan","authors":"Toshihiko Nagatani, Takeharu Tajiri","doi":"10.1680/jfoen.18.00013","DOIUrl":null,"url":null,"abstract":"Repairs were required to a corroded post-tensioned prestressed-concrete continuous-girder bridge that had been in service for over 35 years in the Chuo Expressway in Japan. The work included reinfo...","PeriodicalId":42902,"journal":{"name":"Proceedings of the Institution of Civil Engineers-Forensic Engineering","volume":null,"pages":null},"PeriodicalIF":0.4000,"publicationDate":"2019-11-07","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"1","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Proceedings of the Institution of Civil Engineers-Forensic Engineering","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1680/jfoen.18.00013","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"Q4","JCRName":"ENGINEERING, CIVIL","Score":null,"Total":0}
引用次数: 1
Abstract
Repairs were required to a corroded post-tensioned prestressed-concrete continuous-girder bridge that had been in service for over 35 years in the Chuo Expressway in Japan. The work included reinfo...