Unconventional Approach Simplifies Steel Catenary Riser Decommissioning

Ansel Orr, S. Olmos, D. Cheek, Mike Coyne, Nagu Tatineni, Yc. Park, D. Seal
{"title":"Unconventional Approach Simplifies Steel Catenary Riser Decommissioning","authors":"Ansel Orr, S. Olmos, D. Cheek, Mike Coyne, Nagu Tatineni, Yc. Park, D. Seal","doi":"10.4043/31029-ms","DOIUrl":null,"url":null,"abstract":"\n A major pipeline company was tasked with decommissioning the Morpeth tension leg platform (TLP) in the Gulf of Mexico (GoM) and needed to abandon a 22-year-old, 8-in gas export steel catenary riser (SCR).\n The conventional approach to decommissioning an SCR is to mobilize a topside winch package, which sometimes requires the removal of platform equipment. The next step is to carry out structural engineering checks on the platform, determine the wire's various drop point routes through the platform, and provide the engineering analysis necessary to handshake the load from the winch to a heavy lift vessel for abandonment. This was the original plan for the Morpeth TLP SCR decommissioning program.\n Instead of employing this traditional approach to remove the riser using a topside winch package and heavy lift vessel, the pipeline owner requested an alternative method that had been used previously for an international operator. This novel method employed ROVs and divers to install a series of clamps to grip and secure the riser prior to cutting and used a Multiservice Vessel (MSV) to manage the disconnected riser for abandonment on the seafloor. The appeal of this integrated solution is that it does not interfere with the platform's topside operations or equipment layout and can provide potential cost savings.\n This methodology was used for the first time in the GoM to remove a riser to make space for a new one to be installed. For this installation, a clamp was designed by the operator to sit on the J-lay collar and to support the weight of the riser being removed. The project was modeled in OrcaFlex to determine safety requirements and the service company carried out the riser removal. Following adaptations to accommodate the differences presented by the Morpeth TLP SCR, a similar approach was used in the SCR decommissioning project, with the service company's engineering team designing a combination of a friction and through-pin box clamp, determining their placement, mapping out the role of divers, and defining the necessary vessel movements for each phase of the operation.\n Following an initial survey to determine the profile of the SCR, the service company created an OrcaFlex model and decommissioning plan that would allow the vessel to safely execute the program. The model allowed the team to incorporate safety factors to ensure that the load of the riser could be managed and that the riser could be handled without jeopardizing the safety of the vessel or creating riser clashing during the process of cutting and swinging the riser away from the TLP. It was determined that a winch wire could be cantilevered off the stern of the vessel to provide overhead access to the riser and clamp connection point. With the clamps properly connected, the riser was severed in a controlled manner by ROVs and then abandoned within the right-of-way (along the pre-approved area) of the pipeline prior to the ends being plugged and covered.\n In comparing the actual dynamic loads monitored during the operation with a line rider, it was confirmed that the model was within 5% of the expected loads, estimated at 54 metric tons.\n This paper explains how an unconventional method of SCR decommissioning allowed execution entirely from the MSV without impeding the operator's decommissioning schedule or conflicting with the work of other contractors on the platform to provide substantial cost savings.\n The solution also can be used to replace existing risers, whether the useful life of the platform exceeds the useful life of the riser and/or in the case where new field development requires a new tie-in. Other deepwater, vessel-based decommissioning solutions include the abandonment and/or recovery of flushed umbilicals and potentially the abandonment of flexible catenary risers.\n Following successful execution of the SCR decommissioning project, the pipeline company requested a FEED for using this integrated decommissioning solution for additional offshore assets. It was also requested that the clamp design be ROV installable. The study is for a three-year program to abandon five export SCRs on multiple TLPs in the GoM with loads upwards of 350 metric tons. The abandonment method to be employed for the upcoming SCR decommissioning program is the same as the one described in this paper, with execution from a single, standalone MSV.","PeriodicalId":11084,"journal":{"name":"Day 4 Thu, August 19, 2021","volume":null,"pages":null},"PeriodicalIF":0.0000,"publicationDate":"2021-08-09","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Day 4 Thu, August 19, 2021","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.4043/31029-ms","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

Abstract

A major pipeline company was tasked with decommissioning the Morpeth tension leg platform (TLP) in the Gulf of Mexico (GoM) and needed to abandon a 22-year-old, 8-in gas export steel catenary riser (SCR). The conventional approach to decommissioning an SCR is to mobilize a topside winch package, which sometimes requires the removal of platform equipment. The next step is to carry out structural engineering checks on the platform, determine the wire's various drop point routes through the platform, and provide the engineering analysis necessary to handshake the load from the winch to a heavy lift vessel for abandonment. This was the original plan for the Morpeth TLP SCR decommissioning program. Instead of employing this traditional approach to remove the riser using a topside winch package and heavy lift vessel, the pipeline owner requested an alternative method that had been used previously for an international operator. This novel method employed ROVs and divers to install a series of clamps to grip and secure the riser prior to cutting and used a Multiservice Vessel (MSV) to manage the disconnected riser for abandonment on the seafloor. The appeal of this integrated solution is that it does not interfere with the platform's topside operations or equipment layout and can provide potential cost savings. This methodology was used for the first time in the GoM to remove a riser to make space for a new one to be installed. For this installation, a clamp was designed by the operator to sit on the J-lay collar and to support the weight of the riser being removed. The project was modeled in OrcaFlex to determine safety requirements and the service company carried out the riser removal. Following adaptations to accommodate the differences presented by the Morpeth TLP SCR, a similar approach was used in the SCR decommissioning project, with the service company's engineering team designing a combination of a friction and through-pin box clamp, determining their placement, mapping out the role of divers, and defining the necessary vessel movements for each phase of the operation. Following an initial survey to determine the profile of the SCR, the service company created an OrcaFlex model and decommissioning plan that would allow the vessel to safely execute the program. The model allowed the team to incorporate safety factors to ensure that the load of the riser could be managed and that the riser could be handled without jeopardizing the safety of the vessel or creating riser clashing during the process of cutting and swinging the riser away from the TLP. It was determined that a winch wire could be cantilevered off the stern of the vessel to provide overhead access to the riser and clamp connection point. With the clamps properly connected, the riser was severed in a controlled manner by ROVs and then abandoned within the right-of-way (along the pre-approved area) of the pipeline prior to the ends being plugged and covered. In comparing the actual dynamic loads monitored during the operation with a line rider, it was confirmed that the model was within 5% of the expected loads, estimated at 54 metric tons. This paper explains how an unconventional method of SCR decommissioning allowed execution entirely from the MSV without impeding the operator's decommissioning schedule or conflicting with the work of other contractors on the platform to provide substantial cost savings. The solution also can be used to replace existing risers, whether the useful life of the platform exceeds the useful life of the riser and/or in the case where new field development requires a new tie-in. Other deepwater, vessel-based decommissioning solutions include the abandonment and/or recovery of flushed umbilicals and potentially the abandonment of flexible catenary risers. Following successful execution of the SCR decommissioning project, the pipeline company requested a FEED for using this integrated decommissioning solution for additional offshore assets. It was also requested that the clamp design be ROV installable. The study is for a three-year program to abandon five export SCRs on multiple TLPs in the GoM with loads upwards of 350 metric tons. The abandonment method to be employed for the upcoming SCR decommissioning program is the same as the one described in this paper, with execution from a single, standalone MSV.
查看原文
分享 分享
微信好友 朋友圈 QQ好友 复制链接
本刊更多论文
非常规方法简化了钢悬链线立管的退役
一家大型管道公司负责墨西哥湾(GoM) Morpeth张力腿平台(TLP)的退役工作,需要废弃一个使用了22年、8英寸的天然气出口钢悬链管(SCR)。SCR的常规退役方法是调动上部绞车包,有时需要移除平台设备。下一步是对平台进行结构工程检查,确定电缆通过平台的各种落点路线,并提供必要的工程分析,以便将负载从绞车转移到重型起重船进行弃船。这是Morpeth张力腿平台SCR退役项目的最初计划。管道所有者要求采用一种替代方法,而不是使用上层绞车包和重型举升船来拆除立管,该方法之前曾用于一家国际运营商。这种新方法使用rov和潜水员在切割之前安装一系列夹子来固定立管,并使用多服务船(MSV)来管理断开的立管,以便在海底废弃。这种集成解决方案的吸引力在于,它不会干扰平台的上部操作或设备布局,并且可以节省潜在的成本。该方法在墨西哥湾首次用于移除立管,为安装新立管腾出空间。在安装过程中,作业者设计了一个夹钳,夹在J-lay接箍上,以支撑正在移除的立管的重量。该项目在OrcaFlex中建模,以确定安全要求,服务公司进行了隔水管移除。为了适应Morpeth TLP SCR所带来的差异,在SCR退役项目中也采用了类似的方法,服务公司的工程团队设计了摩擦和通针盒夹的组合,确定了它们的位置,规划了潜水员的角色,并定义了每个作业阶段所需的船舶运动。在对SCR进行初步调查后,服务公司创建了OrcaFlex模型和退役计划,以确保船舶安全执行该计划。该模型允许团队纳入安全因素,以确保隔水管的负载可以得到控制,并且在处理隔水管时不会危及船舶的安全,也不会在切割隔水管和将隔水管从张力腿平台上摇离的过程中产生隔水管碰撞。最后确定了一根绞车线可以悬挑在船的尾部,以提供到隔水管和卡箍连接点的架空通道。在夹钳正确连接后,隔水管由rov以可控的方式切断,然后在管道末端被堵塞和覆盖之前,在管道的通行权范围内(沿着预先批准的区域)被丢弃。在将运行期间监测到的实际动态载荷与线路骑乘器进行比较后,确认该模型与预期载荷(估计为54公吨)的误差在5%以内。本文介绍了一种非常规的SCR退役方法,该方法可以完全在MSV上执行,而不会妨碍作业者的退役计划,也不会与平台上其他承包商的工作发生冲突,从而节省大量成本。该解决方案还可以用于替换现有立管,无论平台的使用寿命是否超过立管的使用寿命,或者在新油田开发需要新的接箍的情况下。其他深水、基于船舶的退役解决方案包括废弃和/或回收冲洗的脐带缆,以及可能废弃的柔性悬链管。在成功执行SCR退役项目后,管道公司要求为其他海上资产使用该综合退役解决方案提供FEED。还要求夹具设计为ROV安装。该研究是一个为期三年的项目,将在墨西哥湾的多个平台上放弃5个出口scr,装载量超过350吨。即将进行的SCR退役计划采用的废弃方法与本文中描述的方法相同,即在单个独立的MSV上执行。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 去求助
来源期刊
自引率
0.00%
发文量
0
期刊最新文献
Qualification of Barrier Fluidless, Sealless Seawater Canned Motor Pumps Hull Condition Monitoring and Lifetime Estimation by the Combination of On-Board Sensing and Digital Twin Technology Unconventional Approach Simplifies Steel Catenary Riser Decommissioning InspectTM Computed Tomography for NDT of Subsea Pipelines Novel Active Slug Control in Angola - Development & Field Results
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
现在去查看 取消
×
提示
确定
0
微信
客服QQ
Book学术公众号 扫码关注我们
反馈
×
意见反馈
请填写您的意见或建议
请填写您的手机或邮箱
已复制链接
已复制链接
快去分享给好友吧!
我知道了
×
扫码分享
扫码分享
Book学术官方微信
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术
文献互助 智能选刊 最新文献 互助须知 联系我们:info@booksci.cn
Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。
Copyright © 2023 Book学术 All rights reserved.
ghs 京公网安备 11010802042870号 京ICP备2023020795号-1