Best Practices in Integrity Management of Safety Critical Systems

I. A. Awadhi, S. Narayana, Alya Al Ahmad, S. Qamar, Shahid Rafiq
{"title":"Best Practices in Integrity Management of Safety Critical Systems","authors":"I. A. Awadhi, S. Narayana, Alya Al Ahmad, S. Qamar, Shahid Rafiq","doi":"10.2118/197175-ms","DOIUrl":null,"url":null,"abstract":"\n The rapid induction of Fiber Reinforced Plastics (FRP) into process industry due to high corrosion resistance and cost effectiveness made End Users to overlook FRP's specific design, fabrication and quality control aspects. This also affected various Utility and firewater networks in ADNOC Gas Processing plants. It is addressed by enhancing Vendor pre-qualification, relevant specifications and construction procedures. This paper presents measures adopted to ensure reliable design, supply and installation of FRP piping systems.\n FRP piping systems have unique design/construction requirements that was not followed in totality in AGP past installations. Also, international standards do not offer adequate guidance on design, resins selection, fabrication methods and joint systems. Vendors were trusted upon for complete design. A campaign is initiated to engage FRP pipe manufacturer having binding single point responsibility from beginning of project for particular FRP system design to ensure desired performance of FRP piping system with extended warranty. Measures have been taken to improve quality material supply through enhanced vendor pre-qualification, ADNOC Gas Processing specifications and CONTRACTORS pre-qualification having certified site crew.\n Studies revealed that material quality, velocity/surge pressure were the main contributing factors for failures which were not adequately addressed in design of FRP piping systems. Gaps noticed in previous projects were use of inadequate Codes, Composite's mechanical properties, design approach, inadequate joint preparation and QA/QC in construction phase. During manufacturing using wrong resin can be a cause for premature failure. Absence of certified personnel for project execution and\n Non-compliance of manufacturer's instructions were also key lapses noted in construction phase. The gaps in design process, necessitated improvement and consolidation of ADNOC Gas Processing existing design specifications/criteria and analysis requirements which now mandate that the required hydraulic / surge / static analysis shall be carried out by pre-qualified FRP manufacturer. Material property issues were addressed by clearly specifying the material composition & properties requirements and procedural requirements for storage are incorporated into the manufacturing process, along with mandating minimum prior experience for the manufacturers for material supply and design. Certification of contractor's personnel and presence of FRP manufacturer's representative at site during construction and pre-commissioning has been emphasized as mandatory requirement. In addition Specialist 3rd party inspection/supervision must be deployed to ensure quality control during every step of construction and commissioning\n Design specifications, procedures, manufacturing process, QA/QC and installation methods for FRP piping systems are available, but lacked activity interface between consultant, vendor and contractor. ADNOC Gas Processing enhanced the FRP specification ensuring single point responsibility with Vendor and procedures to ensure consistency from the design phase coherent with manufacturing process and appropriate implementation during the execution phase, in order to ensure the safety and integrity of FRP Piping systems.","PeriodicalId":11061,"journal":{"name":"Day 1 Mon, November 11, 2019","volume":"59 1","pages":""},"PeriodicalIF":0.0000,"publicationDate":"2019-11-11","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Day 1 Mon, November 11, 2019","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.2118/197175-ms","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

Abstract

The rapid induction of Fiber Reinforced Plastics (FRP) into process industry due to high corrosion resistance and cost effectiveness made End Users to overlook FRP's specific design, fabrication and quality control aspects. This also affected various Utility and firewater networks in ADNOC Gas Processing plants. It is addressed by enhancing Vendor pre-qualification, relevant specifications and construction procedures. This paper presents measures adopted to ensure reliable design, supply and installation of FRP piping systems. FRP piping systems have unique design/construction requirements that was not followed in totality in AGP past installations. Also, international standards do not offer adequate guidance on design, resins selection, fabrication methods and joint systems. Vendors were trusted upon for complete design. A campaign is initiated to engage FRP pipe manufacturer having binding single point responsibility from beginning of project for particular FRP system design to ensure desired performance of FRP piping system with extended warranty. Measures have been taken to improve quality material supply through enhanced vendor pre-qualification, ADNOC Gas Processing specifications and CONTRACTORS pre-qualification having certified site crew. Studies revealed that material quality, velocity/surge pressure were the main contributing factors for failures which were not adequately addressed in design of FRP piping systems. Gaps noticed in previous projects were use of inadequate Codes, Composite's mechanical properties, design approach, inadequate joint preparation and QA/QC in construction phase. During manufacturing using wrong resin can be a cause for premature failure. Absence of certified personnel for project execution and Non-compliance of manufacturer's instructions were also key lapses noted in construction phase. The gaps in design process, necessitated improvement and consolidation of ADNOC Gas Processing existing design specifications/criteria and analysis requirements which now mandate that the required hydraulic / surge / static analysis shall be carried out by pre-qualified FRP manufacturer. Material property issues were addressed by clearly specifying the material composition & properties requirements and procedural requirements for storage are incorporated into the manufacturing process, along with mandating minimum prior experience for the manufacturers for material supply and design. Certification of contractor's personnel and presence of FRP manufacturer's representative at site during construction and pre-commissioning has been emphasized as mandatory requirement. In addition Specialist 3rd party inspection/supervision must be deployed to ensure quality control during every step of construction and commissioning Design specifications, procedures, manufacturing process, QA/QC and installation methods for FRP piping systems are available, but lacked activity interface between consultant, vendor and contractor. ADNOC Gas Processing enhanced the FRP specification ensuring single point responsibility with Vendor and procedures to ensure consistency from the design phase coherent with manufacturing process and appropriate implementation during the execution phase, in order to ensure the safety and integrity of FRP Piping systems.
查看原文
分享 分享
微信好友 朋友圈 QQ好友 复制链接
本刊更多论文
安全关键系统完整性管理的最佳实践
由于高耐腐蚀性和成本效益,纤维增强塑料(FRP)迅速进入加工工业,最终用户忽略了FRP的具体设计,制造和质量控制方面。这也影响了ADNOC天然气处理厂的各种公用事业和消防管网。通过加强供应商资格预审、相关规范和施工程序来解决。本文介绍了为保证玻璃钢管道系统的可靠设计、供应和安装所采取的措施。玻璃钢管道系统具有独特的设计/施工要求,在AGP过去的安装中没有完全遵循。此外,国际标准在设计、树脂选择、制造方法和连接系统方面没有提供足够的指导。供应商被信任完成了完整的设计。我们发起了一项运动,要求玻璃钢管道制造商从项目开始就对特定玻璃钢系统设计承担有约束力的单点责任,以确保延长质保期内玻璃钢管道系统的预期性能。已采取措施,通过加强供应商资格预审、ADNOC天然气处理规范和承包商资格预审,提高材料供应质量,并拥有经过认证的现场工作人员。研究表明,材料质量、速度/喘振压力是导致FRP管道系统失效的主要因素,而这些因素在FRP管道系统的设计中没有得到充分解决。在之前的项目中注意到的缺陷是使用不适当的规范、复合材料的机械性能、设计方法、接头准备和施工阶段的QA/QC不充分。在制造过程中,使用错误的树脂可能会导致过早失效。项目执行中缺少认证人员和不遵守制造商的指示也是施工阶段注意到的主要失误。设计过程中的差距,需要改进和巩固ADNOC气体处理现有的设计规范/标准和分析要求,现在要求所需的液压/喘振/静态分析应由预先合格的FRP制造商进行。通过明确规定材料成分和性能要求来解决材料性能问题,并将存储的程序要求纳入制造过程,同时要求制造商具有材料供应和设计的最低经验。在施工和预调试期间,承包商人员的认证和玻璃钢制造商代表在现场的存在被强调为强制性要求。此外,必须部署专业的第三方检查/监督,以确保在施工和调试的每一步都有质量控制,FRP管道系统的设计规范、程序、制造工艺、QA/QC和安装方法是可用的,但顾问、供应商和承包商之间缺乏活动接口。ADNOC气体处理增强了FRP规范,确保了供应商的单点责任和程序,以确保设计阶段与制造过程的一致性,并在执行阶段适当实施,以确保FRP管道系统的安全性和完整性。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 去求助
来源期刊
自引率
0.00%
发文量
0
期刊最新文献
Lessons Learned from History-Matching the First Out-Of-Sequence Fracturing Field Test in North America Energy Saving Challenges and Opportunities in Upstream Operations using Value Methodology An Integrated Solution to Repair Multiple Shallow Leaks in Production Tubing – A Unique Single Trip Well Intervention Technique Openhole Completions as Recovery Case for Drilling Across Salt and High Pressure Floaters The Impact of Dynamic Filtration on Formation Testing in Low Mobility Carbonate Formations. Case Study: Lower Cretaceous Carbonate Reservoir in the UAE
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
现在去查看 取消
×
提示
确定
0
微信
客服QQ
Book学术公众号 扫码关注我们
反馈
×
意见反馈
请填写您的意见或建议
请填写您的手机或邮箱
已复制链接
已复制链接
快去分享给好友吧!
我知道了
×
扫码分享
扫码分享
Book学术官方微信
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术
文献互助 智能选刊 最新文献 互助须知 联系我们:info@booksci.cn
Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。
Copyright © 2023 Book学术 All rights reserved.
ghs 京公网安备 11010802042870号 京ICP备2023020795号-1