{"title":"Efficient Placement of Relief Well Using Combination of Tools","authors":"A. Pedro, D. Feltracco, A. Pasquale, E. Gravante","doi":"10.2118/198760-MS","DOIUrl":null,"url":null,"abstract":"\n A Well with plug set in both tubing was sabotaged and even after initially capping the well, it was observed that attempting to kill the Target Well via surface pumping was abortive.\n Therefore, in order to achieve well control, drilling a relief well became imperative and required some critical decision to be taken. This include location selection, type fluid to be used in drilling, the casing setting depth, downhole measuring tools for use, as well as contractors needed in achieving success in a suitation of incomplete well survey data.\n This paper presents how this keys needs were met in drilling the Relief Well planned for 97days trouble free and performed in 107days from spud to hitting Target Well. The success was on single attempt in spite of it having an incomplete survey record acquired 49 years earlier.","PeriodicalId":11250,"journal":{"name":"Day 3 Wed, August 07, 2019","volume":"78 1","pages":""},"PeriodicalIF":0.0000,"publicationDate":"2019-08-05","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Day 3 Wed, August 07, 2019","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.2118/198760-MS","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0
Abstract
A Well with plug set in both tubing was sabotaged and even after initially capping the well, it was observed that attempting to kill the Target Well via surface pumping was abortive.
Therefore, in order to achieve well control, drilling a relief well became imperative and required some critical decision to be taken. This include location selection, type fluid to be used in drilling, the casing setting depth, downhole measuring tools for use, as well as contractors needed in achieving success in a suitation of incomplete well survey data.
This paper presents how this keys needs were met in drilling the Relief Well planned for 97days trouble free and performed in 107days from spud to hitting Target Well. The success was on single attempt in spite of it having an incomplete survey record acquired 49 years earlier.