The Construction of the Cross Bay Link Bridge in Hong Kong

Yangtian Wang, Haijuan Liu, S. Mak, Chengrui Hu
{"title":"The Construction of the Cross Bay Link Bridge in Hong Kong","authors":"Yangtian Wang, Haijuan Liu, S. Mak, Chengrui Hu","doi":"10.1680/jbren.22.00016","DOIUrl":null,"url":null,"abstract":"The Cross Bay Link (CBL) bridge is a 1km sea crossing that forms the centrepiece of the new East-West express highway link in Hong Kong. This £250 million project features an iconic 200m-span butterfly double-arch bridge and a series of concrete box girder spans supported on the specially-sculpted V-piers and large-size piled foundations. This paper describes the innovative construction methods adopted for building the bridge safely and efficiently in an extremely challenging marine environment, which leveraged on the extensive use of the Design for Manufacture and Assembly (DfMA) solutions with most of the bridge elements above the sea level being prefabricated or precast offsite. This includes the construction of the 10,000 tonnes steel arch bridge, which was fully prefabricated near Shanghai, then transported to Hong Kong by a semi-submersible barge, and eventually erected onto the piers by using the float-over method. In addition, most of the concrete decks, piers and the pile cap shells were precast offsite and then lifted into position on site. This project holds a number of engineering records in Hong Kong, including the longest arch bridge, the first-time adoption of S690QL high-strength steel for major bridge elements and the largest-scale implementation of the float-over erection method.","PeriodicalId":44437,"journal":{"name":"Proceedings of the Institution of Civil Engineers-Bridge Engineering","volume":"1995 1","pages":""},"PeriodicalIF":1.5000,"publicationDate":"2022-07-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"1","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Proceedings of the Institution of Civil Engineers-Bridge Engineering","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1680/jbren.22.00016","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"Q3","JCRName":"ENGINEERING, CIVIL","Score":null,"Total":0}
引用次数: 1

Abstract

The Cross Bay Link (CBL) bridge is a 1km sea crossing that forms the centrepiece of the new East-West express highway link in Hong Kong. This £250 million project features an iconic 200m-span butterfly double-arch bridge and a series of concrete box girder spans supported on the specially-sculpted V-piers and large-size piled foundations. This paper describes the innovative construction methods adopted for building the bridge safely and efficiently in an extremely challenging marine environment, which leveraged on the extensive use of the Design for Manufacture and Assembly (DfMA) solutions with most of the bridge elements above the sea level being prefabricated or precast offsite. This includes the construction of the 10,000 tonnes steel arch bridge, which was fully prefabricated near Shanghai, then transported to Hong Kong by a semi-submersible barge, and eventually erected onto the piers by using the float-over method. In addition, most of the concrete decks, piers and the pile cap shells were precast offsite and then lifted into position on site. This project holds a number of engineering records in Hong Kong, including the longest arch bridge, the first-time adoption of S690QL high-strength steel for major bridge elements and the largest-scale implementation of the float-over erection method.
查看原文
分享 分享
微信好友 朋友圈 QQ好友 复制链接
本刊更多论文
在香港兴建跨湾连接大桥
跨湾连接大桥是全长1公里的跨海大桥,是香港新东西高速公路连接的核心部分。这个耗资2.5亿英镑的项目以标志性的200米跨度蝶形双拱桥和一系列混凝土箱梁跨度为特色,这些箱梁跨度由特殊雕刻的v型桥墩和大型桩基础支撑。本文介绍了在极具挑战性的海洋环境中安全高效地建造桥梁所采用的创新施工方法,该方法利用了广泛使用的制造和组装设计(DfMA)解决方案,大多数海平面以上的桥梁元件都是预制或预制的。这包括建造一座1万吨的钢拱桥,这座桥是在上海附近完全预制的,然后由一艘半潜式驳船运到香港,最后用浮式方法安装在码头上。此外,大部分混凝土甲板、桥墩和桩帽壳均在现场预制,然后在现场吊装到位。该项目在香港创下多项工程纪录,包括最长的拱桥、首次采用S690QL高强度钢作为桥梁主要构件,以及最大规模地采用浮式架设法。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 去求助
来源期刊
CiteScore
3.00
自引率
10.00%
发文量
48
期刊最新文献
Hybrid machine learning model for prediction of vertical deflection of composite bridges A control chart to evaluate the control effect of a bridge under active control Design of stone masonry bridges in European treatises: Part 1 – The geometrical configuration Extreme fjord-crossings development in the E39 coastal highway route project – a review The replacement of the Kosciuszko Bridge
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
现在去查看 取消
×
提示
确定
0
微信
客服QQ
Book学术公众号 扫码关注我们
反馈
×
意见反馈
请填写您的意见或建议
请填写您的手机或邮箱
已复制链接
已复制链接
快去分享给好友吧!
我知道了
×
扫码分享
扫码分享
Book学术官方微信
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术
文献互助 智能选刊 最新文献 互助须知 联系我们:info@booksci.cn
Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。
Copyright © 2023 Book学术 All rights reserved.
ghs 京公网安备 11010802042870号 京ICP备2023020795号-1