{"title":"使用IFM方法的电信项目组合调度","authors":"D. Tselios, P. Ipsilandis","doi":"10.1109/TELFOR.2017.8249431","DOIUrl":null,"url":null,"abstract":"Project management methodologies are geared towards managing individual projects. However, modern project-oriented firms execute more than one project at a time. This is a common characteristic in the service sector, like telecommunication companies, which run a bundle of projects concurrently. Hence, project scheduling gradually becomes project portfolio scheduling. It must be underlined that projects within a given portfolio are usually interconnected with relationships and dependencies and share common resources. Maximizing the overall value generated from project completion and operation is a main objective in portfolio scheduling. A modification of the IFM approach is used in order to confront this scheduling problem. A set of problem instances is generated in order to instigate a comparison study. The obtained results are quite promising and the method seems to scale well regarding the size of the project portfolio.","PeriodicalId":422501,"journal":{"name":"2017 25th Telecommunication Forum (TELFOR)","volume":"40 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2017-11-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"2","resultStr":"{\"title\":\"Telecommunication projects portfolio scheduling using the IFM approach\",\"authors\":\"D. Tselios, P. Ipsilandis\",\"doi\":\"10.1109/TELFOR.2017.8249431\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"Project management methodologies are geared towards managing individual projects. However, modern project-oriented firms execute more than one project at a time. This is a common characteristic in the service sector, like telecommunication companies, which run a bundle of projects concurrently. Hence, project scheduling gradually becomes project portfolio scheduling. It must be underlined that projects within a given portfolio are usually interconnected with relationships and dependencies and share common resources. Maximizing the overall value generated from project completion and operation is a main objective in portfolio scheduling. A modification of the IFM approach is used in order to confront this scheduling problem. A set of problem instances is generated in order to instigate a comparison study. The obtained results are quite promising and the method seems to scale well regarding the size of the project portfolio.\",\"PeriodicalId\":422501,\"journal\":{\"name\":\"2017 25th Telecommunication Forum (TELFOR)\",\"volume\":\"40 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2017-11-01\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"2\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"2017 25th Telecommunication Forum (TELFOR)\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.1109/TELFOR.2017.8249431\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"2017 25th Telecommunication Forum (TELFOR)","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/TELFOR.2017.8249431","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 2

摘要

项目管理方法是面向管理单个项目的。然而,现代以项目为导向的公司一次执行多个项目。这是服务行业的一个共同特点,比如电信公司,它们同时经营一系列项目。因此,项目计划逐渐成为项目组合计划。必须强调的是,给定投资组合中的项目通常具有相互关联和依赖关系,并共享公共资源。最大化项目完成和运行所产生的整体价值是项目组合调度的主要目标。为了解决这个调度问题,使用了对IFM方法的修改。生成一组问题实例,以便进行比较研究。获得的结果非常有希望,并且该方法似乎可以很好地扩展到项目组合的大小。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
查看原文
分享 分享
微信好友 朋友圈 QQ好友 复制链接
本刊更多论文
Telecommunication projects portfolio scheduling using the IFM approach
Project management methodologies are geared towards managing individual projects. However, modern project-oriented firms execute more than one project at a time. This is a common characteristic in the service sector, like telecommunication companies, which run a bundle of projects concurrently. Hence, project scheduling gradually becomes project portfolio scheduling. It must be underlined that projects within a given portfolio are usually interconnected with relationships and dependencies and share common resources. Maximizing the overall value generated from project completion and operation is a main objective in portfolio scheduling. A modification of the IFM approach is used in order to confront this scheduling problem. A set of problem instances is generated in order to instigate a comparison study. The obtained results are quite promising and the method seems to scale well regarding the size of the project portfolio.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
期刊最新文献
Proposing bat inspired heuristic algorithm for the optimization of GMPLS networks Investigation on temporal skewing among O-CDMA code carriers under fiber temperature variations Survey on machine learning algorithms as cloud service for CIDPS Identity provider deployment based on container technology Enhanced bandwidth PIFA antennas for 900/1800 MHz and WiFi 2400 MHz band with a dielectric cover
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
现在去查看 取消
×
提示
确定
0
微信
客服QQ
Book学术公众号 扫码关注我们
反馈
×
意见反馈
请填写您的意见或建议
请填写您的手机或邮箱
已复制链接
已复制链接
快去分享给好友吧!
我知道了
×
扫码分享
扫码分享
Book学术官方微信
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术
文献互助 智能选刊 最新文献 互助须知 联系我们:info@booksci.cn
Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。
Copyright © 2023 Book学术 All rights reserved.
ghs 京公网安备 11010802042870号 京ICP备2023020795号-1