贝勒方特主安全壳结构

J. Olyniec
{"title":"贝勒方特主安全壳结构","authors":"J. Olyniec","doi":"10.1061/JCCEAZ.0000997","DOIUrl":null,"url":null,"abstract":"Construction of the reactor building primary containment structure at the Bellefonte Nuclear Plant involved several specialized construction techniques. This two unit plant is one of the nine nuclear units at six different sites now under construction by the Tennessee Valley Authority (TVA). The post-Tensioned, cast-in-place interior steel lined containment structure is unique within TVA. Problems during construction were identified at weekly planning meetings, and options were discussed. Close coordination between craft supervisors and on-site engineering personnel drew together “hands-on” experience and technical background. Details of the construction techniques, problems, and solutions are presented.","PeriodicalId":271903,"journal":{"name":"Journal of the Construction Division","volume":"20 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"1981-12-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"2","resultStr":"{\"title\":\"Bellefonte Primary Containment Structure\",\"authors\":\"J. Olyniec\",\"doi\":\"10.1061/JCCEAZ.0000997\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"Construction of the reactor building primary containment structure at the Bellefonte Nuclear Plant involved several specialized construction techniques. This two unit plant is one of the nine nuclear units at six different sites now under construction by the Tennessee Valley Authority (TVA). The post-Tensioned, cast-in-place interior steel lined containment structure is unique within TVA. Problems during construction were identified at weekly planning meetings, and options were discussed. Close coordination between craft supervisors and on-site engineering personnel drew together “hands-on” experience and technical background. Details of the construction techniques, problems, and solutions are presented.\",\"PeriodicalId\":271903,\"journal\":{\"name\":\"Journal of the Construction Division\",\"volume\":\"20 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"1981-12-01\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"2\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Journal of the Construction Division\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.1061/JCCEAZ.0000997\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Journal of the Construction Division","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1061/JCCEAZ.0000997","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 2

摘要

贝勒丰特核电站反应堆建筑主安全壳结构的建造涉及几种专门的建造技术。田纳西河谷管理局(TVA)目前正在建设6个不同地点的9个核电机组,这两座机组是其中之一。后张,浇筑在地方内部钢内衬安全壳结构是独特的TVA。在每周的计划会议上发现了施工过程中的问题,并讨论了解决方案。工艺监督员和现场工程人员之间的密切协调,汇集了“实践”经验和技术背景。详细介绍了施工技术、问题和解决方案。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
查看原文
分享 分享
微信好友 朋友圈 QQ好友 复制链接
本刊更多论文
Bellefonte Primary Containment Structure
Construction of the reactor building primary containment structure at the Bellefonte Nuclear Plant involved several specialized construction techniques. This two unit plant is one of the nine nuclear units at six different sites now under construction by the Tennessee Valley Authority (TVA). The post-Tensioned, cast-in-place interior steel lined containment structure is unique within TVA. Problems during construction were identified at weekly planning meetings, and options were discussed. Close coordination between craft supervisors and on-site engineering personnel drew together “hands-on” experience and technical background. Details of the construction techniques, problems, and solutions are presented.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
期刊最新文献
Closure of "An optimum Bid Approximation Model" Construction of Offshore Platforms Prevention and Resolution of Construction Claims The Resident Engineer: Intermediary Between Owner and Contractor Graphical Method of Optimization: A Short Cut
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
现在去查看 取消
×
提示
确定
0
微信
客服QQ
Book学术公众号 扫码关注我们
反馈
×
意见反馈
请填写您的意见或建议
请填写您的手机或邮箱
已复制链接
已复制链接
快去分享给好友吧!
我知道了
×
扫码分享
扫码分享
Book学术官方微信
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术
文献互助 智能选刊 最新文献 互助须知 联系我们:info@booksci.cn
Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。
Copyright © 2023 Book学术 All rights reserved.
ghs 京公网安备 11010802042870号 京ICP备2023020795号-1