基于evm方法的高速公路工程打桩多重影响分析

CI-TECH Pub Date : 2022-06-06 DOI:10.33005/ci-tech.v3i01.55
Mik Wanul Khosiin, T. A. Gumanti, Ali Muktiyanto, Widi Hidayat
{"title":"基于evm方法的高速公路工程打桩多重影响分析","authors":"Mik Wanul Khosiin, T. A. Gumanti, Ali Muktiyanto, Widi Hidayat","doi":"10.33005/ci-tech.v3i01.55","DOIUrl":null,"url":null,"abstract":"\n \n \n \nA toll road is one of the economic growth facilities of a country, Indonesia in the last seven years has succeeded in building 1900 km and one of them is Trans-Java. The Gempol-Pasuruan section-2 toll road project is a densely populated route and there are many intersections in the form of roads and rivers so there are many overpass or underpass structures in the project. Although the bridge structure is a sub-project of the main road, if the productivity does not perform well, it will have a significant impact on the overall progress. Therefore, this study wants to analyze the multiple impacts of one of the critical works of the bridge project, such as the pilling work on the total toll road progress through the earn value management (EVM) method. EVM is a technique that is quite popular both among practitioners and academics; however, analysis of complex projects (main projects-sub projects) has never been carried out in-depth and it will be a unique challenge in this study. There are four steps in this research, the first step is project scheduling in which the engineer can use the previous database to prepare the work breakdown structure (WBS), work sequences, and project duration. The second step is the critical path process, at this stage, a slack analysis is carried out for each activity, and setting a network diagram to generate critical paths for the toll-bridge project. Resource management is the third step that involves a lot of documents from the market and internal databases, starting with assigning resources, inputting quantity and unit prices, and doing the leveling process so that the supply chain runs well. The last step is the earn value process, at this stage, the engineer only needs to input the project progress, set the baseline, and finally get the earn value project and project performance index consisting of SPI (schedule) and CPI (cost). Finally, after going through several stages of research, it has been proven that the pilling work is on a critical path and several scenarios must be carried out to maintain its productivity. Then, the average SPI value is 0.94 < 1, while the SPI value is 1 which means that the Gempol-Pasuruan section-2 toll road project is experiencing delays and is within the project budget. In conclusion, the application of the EVM method on MS. Project 2013 is able to evaluate complex projects well and several potential technologies can also be considered in further study to improve the performance. \n  \n \n \n \n","PeriodicalId":265863,"journal":{"name":"CI-TECH","volume":"2016 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2022-06-06","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"MULTIPLE IMPACT ANALYSIS OF PILING WORK ON HIGH WAY PROJECTS USING THE EVM METHOD\",\"authors\":\"Mik Wanul Khosiin, T. A. Gumanti, Ali Muktiyanto, Widi Hidayat\",\"doi\":\"10.33005/ci-tech.v3i01.55\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"\\n \\n \\n \\nA toll road is one of the economic growth facilities of a country, Indonesia in the last seven years has succeeded in building 1900 km and one of them is Trans-Java. The Gempol-Pasuruan section-2 toll road project is a densely populated route and there are many intersections in the form of roads and rivers so there are many overpass or underpass structures in the project. Although the bridge structure is a sub-project of the main road, if the productivity does not perform well, it will have a significant impact on the overall progress. Therefore, this study wants to analyze the multiple impacts of one of the critical works of the bridge project, such as the pilling work on the total toll road progress through the earn value management (EVM) method. EVM is a technique that is quite popular both among practitioners and academics; however, analysis of complex projects (main projects-sub projects) has never been carried out in-depth and it will be a unique challenge in this study. There are four steps in this research, the first step is project scheduling in which the engineer can use the previous database to prepare the work breakdown structure (WBS), work sequences, and project duration. The second step is the critical path process, at this stage, a slack analysis is carried out for each activity, and setting a network diagram to generate critical paths for the toll-bridge project. Resource management is the third step that involves a lot of documents from the market and internal databases, starting with assigning resources, inputting quantity and unit prices, and doing the leveling process so that the supply chain runs well. The last step is the earn value process, at this stage, the engineer only needs to input the project progress, set the baseline, and finally get the earn value project and project performance index consisting of SPI (schedule) and CPI (cost). Finally, after going through several stages of research, it has been proven that the pilling work is on a critical path and several scenarios must be carried out to maintain its productivity. Then, the average SPI value is 0.94 < 1, while the SPI value is 1 which means that the Gempol-Pasuruan section-2 toll road project is experiencing delays and is within the project budget. In conclusion, the application of the EVM method on MS. Project 2013 is able to evaluate complex projects well and several potential technologies can also be considered in further study to improve the performance. \\n  \\n \\n \\n \\n\",\"PeriodicalId\":265863,\"journal\":{\"name\":\"CI-TECH\",\"volume\":\"2016 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2022-06-06\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"CI-TECH\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.33005/ci-tech.v3i01.55\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"CI-TECH","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.33005/ci-tech.v3i01.55","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

摘要

收费公路是一个国家的经济增长设施之一,印度尼西亚在过去的七年里已经成功地建设了1900公里,其中之一是跨爪哇。Gempol-Pasuruan 2段收费公路项目是一条人口密集的路线,有许多道路和河流形式的交叉点,因此项目中有许多立交桥或地下通道结构。桥梁结构虽然是主干道的子项目,但如果生产力表现不好,将对整体进度产生重大影响。因此,本研究希望通过收益价值管理(EVM)方法分析桥梁工程关键工程之一的打桩工程对收费公路总进度的多重影响。EVM是一种在从业者和学术界都很流行的技术;然而,复杂项目(主项目-子项目)的分析从未深入开展,这将是本研究的独特挑战。本研究分为四个步骤,第一步是项目调度,工程师可以使用之前的数据库来准备工作分解结构(WBS)、工作顺序和项目工期。第二步是关键路径流程,在此阶段,对每个活动进行松弛分析,并设置网络图,生成收费桥项目的关键路径。资源管理是第三步,涉及来自市场和内部数据库的大量文档,从分配资源开始,输入数量和单价,并进行平衡过程,使供应链运行良好。最后一步是挣值过程,在这个阶段,工程师只需要输入项目进度,设置基线,最后得到项目的挣值和项目绩效指标,包括SPI(进度)和CPI(成本)。最后,经过几个阶段的研究,证明了造球工作处于关键路径上,必须进行几种场景来保持其生产力。则平均SPI值为0.94 < 1,当SPI值为1时,表示gempal - pasuruan 2段收费公路项目出现延期,且在项目预算范围内。综上所述,EVM方法在ms Project 2013上的应用能够很好地评价复杂项目,并且在进一步的研究中还可以考虑一些潜在的技术来提高性能。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
查看原文
分享 分享
微信好友 朋友圈 QQ好友 复制链接
本刊更多论文
MULTIPLE IMPACT ANALYSIS OF PILING WORK ON HIGH WAY PROJECTS USING THE EVM METHOD
A toll road is one of the economic growth facilities of a country, Indonesia in the last seven years has succeeded in building 1900 km and one of them is Trans-Java. The Gempol-Pasuruan section-2 toll road project is a densely populated route and there are many intersections in the form of roads and rivers so there are many overpass or underpass structures in the project. Although the bridge structure is a sub-project of the main road, if the productivity does not perform well, it will have a significant impact on the overall progress. Therefore, this study wants to analyze the multiple impacts of one of the critical works of the bridge project, such as the pilling work on the total toll road progress through the earn value management (EVM) method. EVM is a technique that is quite popular both among practitioners and academics; however, analysis of complex projects (main projects-sub projects) has never been carried out in-depth and it will be a unique challenge in this study. There are four steps in this research, the first step is project scheduling in which the engineer can use the previous database to prepare the work breakdown structure (WBS), work sequences, and project duration. The second step is the critical path process, at this stage, a slack analysis is carried out for each activity, and setting a network diagram to generate critical paths for the toll-bridge project. Resource management is the third step that involves a lot of documents from the market and internal databases, starting with assigning resources, inputting quantity and unit prices, and doing the leveling process so that the supply chain runs well. The last step is the earn value process, at this stage, the engineer only needs to input the project progress, set the baseline, and finally get the earn value project and project performance index consisting of SPI (schedule) and CPI (cost). Finally, after going through several stages of research, it has been proven that the pilling work is on a critical path and several scenarios must be carried out to maintain its productivity. Then, the average SPI value is 0.94 < 1, while the SPI value is 1 which means that the Gempol-Pasuruan section-2 toll road project is experiencing delays and is within the project budget. In conclusion, the application of the EVM method on MS. Project 2013 is able to evaluate complex projects well and several potential technologies can also be considered in further study to improve the performance.  
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
期刊最新文献
VALUATION OF SAFETY APPLICATION OF LAND TRANSPORTATION ON PORONG ARTERIAL ROAD – PURWOSARI ROADWAY STA 30+00 – STA 61+400 ANALYSIS OF ENVIRONMENTAL NOISE LEVELS IN SONDIR,BORING SOIL WORK AT KADIRI UNIVERSITY The Project Performance Evaluation of Road Construction Project Using Earned Value Method The Effect Of The Use of Aluminum Fiber As A Partial Substitution of Fine Aggregate on The Compressive Strength of Concrete MULTIPLE IMPACT ANALYSIS OF PILING WORK ON HIGH WAY PROJECTS USING THE EVM METHOD
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
现在去查看 取消
×
提示
确定
0
微信
客服QQ
Book学术公众号 扫码关注我们
反馈
×
意见反馈
请填写您的意见或建议
请填写您的手机或邮箱
已复制链接
已复制链接
快去分享给好友吧!
我知道了
×
扫码分享
扫码分享
Book学术官方微信
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术
文献互助 智能选刊 最新文献 互助须知 联系我们:info@booksci.cn
Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。
Copyright © 2023 Book学术 All rights reserved.
ghs 京公网安备 11010802042870号 京ICP备2023020795号-1