基于形状约束语言(SHACL)的施工进度约束建模

Ranjith K. Soman
{"title":"基于形状约束语言(SHACL)的施工进度约束建模","authors":"Ranjith K. Soman","doi":"10.35490/EC3.2019.170","DOIUrl":null,"url":null,"abstract":"This paper presents a new approach for modelling construction scheduling constraints using Shapes Constraint Language. Current modelling approaches focuses on modelling precedence and discrete constraints at master planning or phase planning level and lacks the ability to model complex constraints at look ahead planning level. Proposed modelling approach addresses this limitation. Precedence constraints, discrete resource capacity constraints, disjunctive constraints and logical constraints are modelled using shapes constraint language for a simple lifting problem in this paper. The modelled constraints were tested, and the constraints model was able to identify the violations effectively and produce a validation report.","PeriodicalId":126601,"journal":{"name":"Proceedings of the 2019 European Conference on Computing in Construction","volume":"1 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2019-07-10","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"6","resultStr":"{\"title\":\"Modelling construction scheduling constraints using shapes constraint language (SHACL)\",\"authors\":\"Ranjith K. Soman\",\"doi\":\"10.35490/EC3.2019.170\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"This paper presents a new approach for modelling construction scheduling constraints using Shapes Constraint Language. Current modelling approaches focuses on modelling precedence and discrete constraints at master planning or phase planning level and lacks the ability to model complex constraints at look ahead planning level. Proposed modelling approach addresses this limitation. Precedence constraints, discrete resource capacity constraints, disjunctive constraints and logical constraints are modelled using shapes constraint language for a simple lifting problem in this paper. The modelled constraints were tested, and the constraints model was able to identify the violations effectively and produce a validation report.\",\"PeriodicalId\":126601,\"journal\":{\"name\":\"Proceedings of the 2019 European Conference on Computing in Construction\",\"volume\":\"1 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2019-07-10\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"6\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Proceedings of the 2019 European Conference on Computing in Construction\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.35490/EC3.2019.170\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Proceedings of the 2019 European Conference on Computing in Construction","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.35490/EC3.2019.170","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 6

摘要

本文提出了一种利用形状约束语言对施工进度约束进行建模的新方法。目前的建模方法主要集中在总体规划或阶段规划层面上对优先约束和离散约束的建模,缺乏在前瞻性规划层面上对复杂约束的建模能力。提出的建模方法解决了这一限制。本文采用形状约束语言对一个简单的提升问题进行了优先约束、离散资源容量约束、析取约束和逻辑约束的建模。对建模的约束进行了测试,并且约束模型能够有效地识别违例并生成验证报告。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
查看原文
分享 分享
微信好友 朋友圈 QQ好友 复制链接
本刊更多论文
Modelling construction scheduling constraints using shapes constraint language (SHACL)
This paper presents a new approach for modelling construction scheduling constraints using Shapes Constraint Language. Current modelling approaches focuses on modelling precedence and discrete constraints at master planning or phase planning level and lacks the ability to model complex constraints at look ahead planning level. Proposed modelling approach addresses this limitation. Precedence constraints, discrete resource capacity constraints, disjunctive constraints and logical constraints are modelled using shapes constraint language for a simple lifting problem in this paper. The modelled constraints were tested, and the constraints model was able to identify the violations effectively and produce a validation report.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
期刊最新文献
An IFC data preparation workflow for building energy performance simulation BIM-based Holonic System for Real-Time Pathfinding in Building Emergency Scenario Semantic and syntactic interoperability of BIM and asset management data Digital built environment maturity model: Digital twins advancing smart infrastructure asset management Optimum topological configurations of sensor networks
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
现在去查看 取消
×
提示
确定
0
微信
客服QQ
Book学术公众号 扫码关注我们
反馈
×
意见反馈
请填写您的意见或建议
请填写您的手机或邮箱
已复制链接
已复制链接
快去分享给好友吧!
我知道了
×
扫码分享
扫码分享
Book学术官方微信
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术
文献互助 智能选刊 最新文献 互助须知 联系我们:info@booksci.cn
Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。
Copyright © 2023 Book学术 All rights reserved.
ghs 京公网安备 11010802042870号 京ICP备2023020795号-1