{"title":"13’x42’水泥磨机断裂及修复,传动装置应变试验","authors":"D. A. Fenton, F. Toffoli","doi":"10.1109/CITCON.1990.111047","DOIUrl":null,"url":null,"abstract":"A cement mill sustained a 42' shear fracture due to a combination of flexural shear and torsional shear. The large fracture of the shell was accompanied by a 5' circumferential crack in the meehanite casting. The shell fracture was successfully repaired using preheat and mechanical bracing. Full thermal stress relief in situ was achieved. The structure was shimmed to achieve good alignment for the drive. The casting was repaired using mechanical fasteners. Strain gauge tests were performed to evaluate the magnitude of torsional shear stress during start-up and steady state running conditions. The strain gauges monitored the clutch engagement time, with the peak stresses measured in the drive shaft. The downtime was 10 weeks.<<ETX>>","PeriodicalId":339195,"journal":{"name":"IEEE Technical Conference on cement Industry","volume":"39 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"1990-05-22","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Fracture of 13'X42' cement mill and its repair, and strain gauge testing of the drive\",\"authors\":\"D. A. Fenton, F. Toffoli\",\"doi\":\"10.1109/CITCON.1990.111047\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"A cement mill sustained a 42' shear fracture due to a combination of flexural shear and torsional shear. The large fracture of the shell was accompanied by a 5' circumferential crack in the meehanite casting. The shell fracture was successfully repaired using preheat and mechanical bracing. Full thermal stress relief in situ was achieved. The structure was shimmed to achieve good alignment for the drive. The casting was repaired using mechanical fasteners. Strain gauge tests were performed to evaluate the magnitude of torsional shear stress during start-up and steady state running conditions. The strain gauges monitored the clutch engagement time, with the peak stresses measured in the drive shaft. The downtime was 10 weeks.<<ETX>>\",\"PeriodicalId\":339195,\"journal\":{\"name\":\"IEEE Technical Conference on cement Industry\",\"volume\":\"39 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"1990-05-22\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"IEEE Technical Conference on cement Industry\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.1109/CITCON.1990.111047\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"IEEE Technical Conference on cement Industry","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/CITCON.1990.111047","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

摘要

由于弯曲剪切和扭转剪切的共同作用,水泥磨机发生了42英尺的剪切断裂。在米汉氏体铸件中,壳体的大断裂伴随着一个5'的周向裂纹。使用预热和机械支撑成功修复了壳体断裂。在原位实现了完全的热应力消除。该结构被摆振以实现驱动器的良好对齐。铸件用机械紧固件修复。在启动和稳态运行条件下,进行应变片试验来评估扭转剪切应力的大小。应变计监测离合器接合时间,在传动轴上测量峰值应力。停机时间为10周。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
查看原文
分享 分享
微信好友 朋友圈 QQ好友 复制链接
本刊更多论文
Fracture of 13'X42' cement mill and its repair, and strain gauge testing of the drive
A cement mill sustained a 42' shear fracture due to a combination of flexural shear and torsional shear. The large fracture of the shell was accompanied by a 5' circumferential crack in the meehanite casting. The shell fracture was successfully repaired using preheat and mechanical bracing. Full thermal stress relief in situ was achieved. The structure was shimmed to achieve good alignment for the drive. The casting was repaired using mechanical fasteners. Strain gauge tests were performed to evaluate the magnitude of torsional shear stress during start-up and steady state running conditions. The strain gauges monitored the clutch engagement time, with the peak stresses measured in the drive shaft. The downtime was 10 weeks.<>
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
期刊最新文献
Operating experience with online analyzer for automatic raw mix control in Belgian cement plant Modifying existing preheater systems for improved productivity and efficiency (cement industry) Solid state energy savers for motors in the cement industry 20 years operating experience with gearless drives Modifying an existing preheater system for improved productivity and efficiency (cement industry)
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
现在去查看 取消
×
提示
确定
0
微信
客服QQ
Book学术公众号 扫码关注我们
反馈
×
意见反馈
请填写您的意见或建议
请填写您的手机或邮箱
已复制链接
已复制链接
快去分享给好友吧!
我知道了
×
扫码分享
扫码分享
Book学术官方微信
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术
文献互助 智能选刊 最新文献 互助须知 联系我们:info@booksci.cn
Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。
Copyright © 2023 Book学术 All rights reserved.
ghs 京公网安备 11010802042870号 京ICP备2023020795号-1