{"title":"随机活动网络中关键路径和弧概率的估计","authors":"G. S. Fishman","doi":"10.1002/NAV.3800320206","DOIUrl":null,"url":null,"abstract":"This article describes a new procedure for estimating parameters of a stochastic activity network of N arcs. The parameters include the probability that path m is the longest path, the probability that path m is the shortest path, the probability that arc i is on the longest path, and the probability that arc i is on the shortest path. The proposed procedure uses quasirandom points together with information on a cutset ℋ of the network to produce an upper bound of O[(log K)N−|ℋ|+1/K] on the absolute error of approximation, where K denotes the number of replications. This is a deterministic bound and is more favorable than the convergence rate of 1/K1/2 that one obtains from the standard error for K independent replications using random sampling. It is also shown how series reduction can improve the convergence rate by reducing the exponent on log K. The technique is illustrated using a Monte Carlo sampling experiment for a network of 16 relevant arcs with a cutset of ℋ = 7 arcs. The illustration shows the superior performance of using quasirandom points with a cutset (plan A) and the even better performance of using quasirandom points with the cutset together with series reduction (plan B) with regard to mean square error. However, it also shows that computation time considerations favor plan A when K is small and plan B when K is large.","PeriodicalId":431817,"journal":{"name":"Naval Research Logistics Quarterly","volume":"15 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"1985-05-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"23","resultStr":"{\"title\":\"Estimating critical path and arc probabilities in stochastic activity networks\",\"authors\":\"G. S. Fishman\",\"doi\":\"10.1002/NAV.3800320206\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"This article describes a new procedure for estimating parameters of a stochastic activity network of N arcs. The parameters include the probability that path m is the longest path, the probability that path m is the shortest path, the probability that arc i is on the longest path, and the probability that arc i is on the shortest path. The proposed procedure uses quasirandom points together with information on a cutset ℋ of the network to produce an upper bound of O[(log K)N−|ℋ|+1/K] on the absolute error of approximation, where K denotes the number of replications. This is a deterministic bound and is more favorable than the convergence rate of 1/K1/2 that one obtains from the standard error for K independent replications using random sampling. It is also shown how series reduction can improve the convergence rate by reducing the exponent on log K. The technique is illustrated using a Monte Carlo sampling experiment for a network of 16 relevant arcs with a cutset of ℋ = 7 arcs. The illustration shows the superior performance of using quasirandom points with a cutset (plan A) and the even better performance of using quasirandom points with the cutset together with series reduction (plan B) with regard to mean square error. However, it also shows that computation time considerations favor plan A when K is small and plan B when K is large.\",\"PeriodicalId\":431817,\"journal\":{\"name\":\"Naval Research Logistics Quarterly\",\"volume\":\"15 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"1985-05-01\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"23\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Naval Research Logistics Quarterly\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.1002/NAV.3800320206\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Naval Research Logistics Quarterly","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1002/NAV.3800320206","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 23
摘要
本文描述了一种估计N个圆弧随机活动网络参数的新方法。参数包括路径m是最长路径的概率,路径m是最短路径的概率,路径i在最长路径上的概率,以及路径i在最短路径上的概率。该方法利用准随机点和网络割集h上的信息,得到近似绝对误差的上界为O[(log K)N−| h |+1/K],其中K表示重复次数。这是一个确定性界,比从使用随机抽样的K个独立复制的标准误差中得到的1/K1/2的收敛率更有利。本文还展示了级数约简是如何通过减少log k的指数来提高收敛速度的。本文用蒙特卡罗抽样实验对一个由16个相关弧组成的网络进行了说明,该网络的割集为h = 7弧。该图显示了使用准随机点与切割集(方案a)的优越性能,以及使用准随机点与切割集以及序列约简(方案B)在均方误差方面的更好性能。然而,它也表明,当K较小时,计算时间的考虑更倾向于方案A,而当K较大时,则倾向于方案B。
Estimating critical path and arc probabilities in stochastic activity networks
This article describes a new procedure for estimating parameters of a stochastic activity network of N arcs. The parameters include the probability that path m is the longest path, the probability that path m is the shortest path, the probability that arc i is on the longest path, and the probability that arc i is on the shortest path. The proposed procedure uses quasirandom points together with information on a cutset ℋ of the network to produce an upper bound of O[(log K)N−|ℋ|+1/K] on the absolute error of approximation, where K denotes the number of replications. This is a deterministic bound and is more favorable than the convergence rate of 1/K1/2 that one obtains from the standard error for K independent replications using random sampling. It is also shown how series reduction can improve the convergence rate by reducing the exponent on log K. The technique is illustrated using a Monte Carlo sampling experiment for a network of 16 relevant arcs with a cutset of ℋ = 7 arcs. The illustration shows the superior performance of using quasirandom points with a cutset (plan A) and the even better performance of using quasirandom points with the cutset together with series reduction (plan B) with regard to mean square error. However, it also shows that computation time considerations favor plan A when K is small and plan B when K is large.