Gde Agus Yudha Prawira Adistana, P. Mahardi, Mochamad Firmansyah Sofianto, Dian Eksana Wibowo
{"title":"通过EARN值管理和EARN SCHEDULE(新esa建筑项目案例研究)预测了项目持续时间的准确性","authors":"Gde Agus Yudha Prawira Adistana, P. Mahardi, Mochamad Firmansyah Sofianto, Dian Eksana Wibowo","doi":"10.21831/INERSIA.V14I2.22539","DOIUrl":null,"url":null,"abstract":"ABSTRACT The earn value method (EVM) has been widely recognized and proven to provide an overview of the performance of construction project implementation from the aspects of time and schedule. Specifically EVM is used to evaluate the progress of the work, so identification of deviations both on time and cost can be done early.The Earn Schedule (ES) method is an elaboration to the schedule analysis on the EVM method. This study aimed to examine and compare the capability of the two methods, namely the earn value and earn schedule methods in predicting the completion time of construction project. The research used the real data from the Unesa building project. The results showed that at week 9, the value of CPI was 1.15 or had a variant cost of 13.32% lower than the planned budget. While for the schedule aspect, both methods indicated a delay in the project with the delay variant of 0.16%. The ES method is able to give information of how long the delay in time unit of 0.02 week.Keywords: accuration, actual cost, earn value, earn schedule, planed value ABSTRAKMetode nilai hasil (EVM) telah dikenal luas dan terbukti mampu memberikan gambaran kinerja pelaksanaan proyek konstruksi dari aspek waktu dan jadwal. Secara khusus EVM digunakan untuk mengevaluasi progress pekerjaan sehingga dapat dilakukan identifikasi lebih awal terhadap penyimpangan baik terhadap waktu maupun biaya. Metode Earn Schedule (ES) merupakan pendalaman terhadap analisis jadwal pada metode EVM. Penelitian ini dilakukan untuk menguji dan membandingkan kemampuan dua metode yaitu metode earn value dan earn schedule dalam memprediksi waktu penyelesaian proyek konstruksi. Data penelitian menggunakan data pelaksanaan dari pembangunan proyek bangunan gedung di Unesa. Hasil penelitianmenunjukkan bahwa pada minggu ke-9, nilai CPI adalah sebesar 1,15 atau memiliki varian biaya sebesar 13,32% lebih rendah dari anggaran yang direncanakan. Sedangkan dari aspek jadwal, kedua metode mengindikasikan bahwa terjadi keterlambatan pada proyek yaitu dengan varian keterlambatan sebesar 0,16% . Metode ES mampu memberikan informasi berapa lama keterlambatan yang terjadi dalam satuan waktu yaitu sebesar 0,02 minggu. Kata Kunci: akurasi, biaya aktual, nilai hasil, earn schedule, biaya rencana","PeriodicalId":440737,"journal":{"name":"INERSIA: lNformasi dan Ekspose hasil Riset teknik SIpil dan Arsitektur","volume":"23 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2018-12-21","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"AKURASI PREDIKSI DURASI PENYELESAIAN PROYEK DENGAN EARN VALUE MANAGEMENT DAN EARN SCHEDULE (STUDI KASUS PROYEK BANGUNAN GEDUNG DI UNESA)\",\"authors\":\"Gde Agus Yudha Prawira Adistana, P. Mahardi, Mochamad Firmansyah Sofianto, Dian Eksana Wibowo\",\"doi\":\"10.21831/INERSIA.V14I2.22539\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"ABSTRACT The earn value method (EVM) has been widely recognized and proven to provide an overview of the performance of construction project implementation from the aspects of time and schedule. Specifically EVM is used to evaluate the progress of the work, so identification of deviations both on time and cost can be done early.The Earn Schedule (ES) method is an elaboration to the schedule analysis on the EVM method. This study aimed to examine and compare the capability of the two methods, namely the earn value and earn schedule methods in predicting the completion time of construction project. The research used the real data from the Unesa building project. The results showed that at week 9, the value of CPI was 1.15 or had a variant cost of 13.32% lower than the planned budget. While for the schedule aspect, both methods indicated a delay in the project with the delay variant of 0.16%. The ES method is able to give information of how long the delay in time unit of 0.02 week.Keywords: accuration, actual cost, earn value, earn schedule, planed value ABSTRAKMetode nilai hasil (EVM) telah dikenal luas dan terbukti mampu memberikan gambaran kinerja pelaksanaan proyek konstruksi dari aspek waktu dan jadwal. Secara khusus EVM digunakan untuk mengevaluasi progress pekerjaan sehingga dapat dilakukan identifikasi lebih awal terhadap penyimpangan baik terhadap waktu maupun biaya. Metode Earn Schedule (ES) merupakan pendalaman terhadap analisis jadwal pada metode EVM. Penelitian ini dilakukan untuk menguji dan membandingkan kemampuan dua metode yaitu metode earn value dan earn schedule dalam memprediksi waktu penyelesaian proyek konstruksi. Data penelitian menggunakan data pelaksanaan dari pembangunan proyek bangunan gedung di Unesa. Hasil penelitianmenunjukkan bahwa pada minggu ke-9, nilai CPI adalah sebesar 1,15 atau memiliki varian biaya sebesar 13,32% lebih rendah dari anggaran yang direncanakan. Sedangkan dari aspek jadwal, kedua metode mengindikasikan bahwa terjadi keterlambatan pada proyek yaitu dengan varian keterlambatan sebesar 0,16% . Metode ES mampu memberikan informasi berapa lama keterlambatan yang terjadi dalam satuan waktu yaitu sebesar 0,02 minggu. Kata Kunci: akurasi, biaya aktual, nilai hasil, earn schedule, biaya rencana\",\"PeriodicalId\":440737,\"journal\":{\"name\":\"INERSIA: lNformasi dan Ekspose hasil Riset teknik SIpil dan Arsitektur\",\"volume\":\"23 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2018-12-21\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"INERSIA: lNformasi dan Ekspose hasil Riset teknik SIpil dan Arsitektur\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.21831/INERSIA.V14I2.22539\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"INERSIA: lNformasi dan Ekspose hasil Riset teknik SIpil dan Arsitektur","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.21831/INERSIA.V14I2.22539","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0
摘要
挣值法(EVM)已被广泛认可并证明可以从时间和进度方面对建设项目实施的绩效进行概述。具体来说,EVM用于评估工作的进度,因此可以尽早识别时间和成本上的偏差。获得进度(ES)方法是在EVM方法的基础上对进度分析的一种细化。本研究旨在检验和比较收益值法和收益进度法两种方法在预测建设项目完工时间方面的能力。该研究使用了Unesa建筑项目的真实数据。结果表明,在第9周,CPI值为1.15或变量成本比计划预算低13.32%。而在进度方面,两种方法都表明项目延迟,延迟变量为0.16%。ES方法能够给出延迟多长时间的信息,时间单位为0.02周。【关键词】精度、实际成本、盈利价值、盈利进度、计划价值Secara khusus EVM digunakan untuk mengevaluasprogress pekerjaan sehinga dapat dilakukan identifikasi lebih awal terhadap penyimpangan baik terhadap waktu maupun biaya。方法挣得表(ES)是一种基于方法挣得表分析的方法。Penelitian ini dilakukan untuk menguji dan membandingkan kemampuan dua method yitu method赚取价值和赚取时间表dalam memprediksi waktu penyelesan proyek konstruksi。Data penelitian menggunakan Data pelaksanaan dari pembangunan proyek bangunan gedung di Unesa。Hasil penelitianmenunjukkan bahwa pada minggu ke-9, nilai CPI adalah sebesar 1,15 atau memiliki varian biaya sebesar 13,32 lebih rendah dari anggaran yang direncanakan。Sedangkan dari说jadwal, kedua mede mengindikasikan bahwa terjadi keterlambatan pada proyek yitu dengan varian keterlambatan sebesar 0,16%。Metode ES mampu成员:berapa lama keterlambatan yang terjadi dalam satuan waktu yaitu sebesar, 2002。Kata Kunci: akurasi, biaya aktual, nilai hasil,赚取时间表,biaya rencana
AKURASI PREDIKSI DURASI PENYELESAIAN PROYEK DENGAN EARN VALUE MANAGEMENT DAN EARN SCHEDULE (STUDI KASUS PROYEK BANGUNAN GEDUNG DI UNESA)
ABSTRACT The earn value method (EVM) has been widely recognized and proven to provide an overview of the performance of construction project implementation from the aspects of time and schedule. Specifically EVM is used to evaluate the progress of the work, so identification of deviations both on time and cost can be done early.The Earn Schedule (ES) method is an elaboration to the schedule analysis on the EVM method. This study aimed to examine and compare the capability of the two methods, namely the earn value and earn schedule methods in predicting the completion time of construction project. The research used the real data from the Unesa building project. The results showed that at week 9, the value of CPI was 1.15 or had a variant cost of 13.32% lower than the planned budget. While for the schedule aspect, both methods indicated a delay in the project with the delay variant of 0.16%. The ES method is able to give information of how long the delay in time unit of 0.02 week.Keywords: accuration, actual cost, earn value, earn schedule, planed value ABSTRAKMetode nilai hasil (EVM) telah dikenal luas dan terbukti mampu memberikan gambaran kinerja pelaksanaan proyek konstruksi dari aspek waktu dan jadwal. Secara khusus EVM digunakan untuk mengevaluasi progress pekerjaan sehingga dapat dilakukan identifikasi lebih awal terhadap penyimpangan baik terhadap waktu maupun biaya. Metode Earn Schedule (ES) merupakan pendalaman terhadap analisis jadwal pada metode EVM. Penelitian ini dilakukan untuk menguji dan membandingkan kemampuan dua metode yaitu metode earn value dan earn schedule dalam memprediksi waktu penyelesaian proyek konstruksi. Data penelitian menggunakan data pelaksanaan dari pembangunan proyek bangunan gedung di Unesa. Hasil penelitianmenunjukkan bahwa pada minggu ke-9, nilai CPI adalah sebesar 1,15 atau memiliki varian biaya sebesar 13,32% lebih rendah dari anggaran yang direncanakan. Sedangkan dari aspek jadwal, kedua metode mengindikasikan bahwa terjadi keterlambatan pada proyek yaitu dengan varian keterlambatan sebesar 0,16% . Metode ES mampu memberikan informasi berapa lama keterlambatan yang terjadi dalam satuan waktu yaitu sebesar 0,02 minggu. Kata Kunci: akurasi, biaya aktual, nilai hasil, earn schedule, biaya rencana