考虑可中断负荷的变电站容量规划方法

Shiyao Jiang, Yuanyuan Zeng, Lin Cheng, Liting Tian, Jiazhu Zhao, Bowen Yan, Xin Wang, Canbing Li
{"title":"考虑可中断负荷的变电站容量规划方法","authors":"Shiyao Jiang, Yuanyuan Zeng, Lin Cheng, Liting Tian, Jiazhu Zhao, Bowen Yan, Xin Wang, Canbing Li","doi":"10.1109/POWERCON.2018.8602045","DOIUrl":null,"url":null,"abstract":"The implementation of the Interruptible Load(IL) project will change the total power load and thus influence the network planning. Therefore, this paper analyzes the necessity of considering IL in planning, the compensation cost model of the IL project is established, and the substation capacity planning method considering the IL is proposed. Aiming at the complexity of the mixed integer nonlinear programming problem, the particle swarm optimization(PSO) algorithm is used to solve the problem, and the effectiveness of the proposed method is verified in a regional power grid with a main voltage level of $110kV$. The calculation results show that the proposed method can reduce the peak load and reduce the substation capacity allocation under the condition of meeting the regional power balance, which saves the construction cost and improves the economic efficiency of the power grid planning.","PeriodicalId":260947,"journal":{"name":"2018 International Conference on Power System Technology (POWERCON)","volume":"118 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2018-11-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"3","resultStr":"{\"title\":\"Substation Capacity Planning Method Considering Interruptible Load\",\"authors\":\"Shiyao Jiang, Yuanyuan Zeng, Lin Cheng, Liting Tian, Jiazhu Zhao, Bowen Yan, Xin Wang, Canbing Li\",\"doi\":\"10.1109/POWERCON.2018.8602045\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"The implementation of the Interruptible Load(IL) project will change the total power load and thus influence the network planning. Therefore, this paper analyzes the necessity of considering IL in planning, the compensation cost model of the IL project is established, and the substation capacity planning method considering the IL is proposed. Aiming at the complexity of the mixed integer nonlinear programming problem, the particle swarm optimization(PSO) algorithm is used to solve the problem, and the effectiveness of the proposed method is verified in a regional power grid with a main voltage level of $110kV$. The calculation results show that the proposed method can reduce the peak load and reduce the substation capacity allocation under the condition of meeting the regional power balance, which saves the construction cost and improves the economic efficiency of the power grid planning.\",\"PeriodicalId\":260947,\"journal\":{\"name\":\"2018 International Conference on Power System Technology (POWERCON)\",\"volume\":\"118 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2018-11-01\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"3\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"2018 International Conference on Power System Technology (POWERCON)\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.1109/POWERCON.2018.8602045\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"2018 International Conference on Power System Technology (POWERCON)","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/POWERCON.2018.8602045","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 3

摘要

可中断负荷工程的实施将改变电力负荷总量,从而影响电网规划。因此,本文分析了在规划中考虑IL的必要性,建立了IL项目的补偿成本模型,提出了考虑IL的变电站容量规划方法。针对混合整数非线性规划问题的复杂性,采用粒子群优化(PSO)算法求解该问题,并在主电压水平为110kV的区域电网中验证了所提方法的有效性。计算结果表明,该方法在满足区域电力均衡的条件下,可以降低峰值负荷,减少变电站容量分配,节省了建设成本,提高了电网规划的经济效益。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
查看原文
分享 分享
微信好友 朋友圈 QQ好友 复制链接
本刊更多论文
Substation Capacity Planning Method Considering Interruptible Load
The implementation of the Interruptible Load(IL) project will change the total power load and thus influence the network planning. Therefore, this paper analyzes the necessity of considering IL in planning, the compensation cost model of the IL project is established, and the substation capacity planning method considering the IL is proposed. Aiming at the complexity of the mixed integer nonlinear programming problem, the particle swarm optimization(PSO) algorithm is used to solve the problem, and the effectiveness of the proposed method is verified in a regional power grid with a main voltage level of $110kV$. The calculation results show that the proposed method can reduce the peak load and reduce the substation capacity allocation under the condition of meeting the regional power balance, which saves the construction cost and improves the economic efficiency of the power grid planning.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
期刊最新文献
Consistency of damping torque and energy flow dissipation coefficient in oscillation stability analysis Optimization of grid-related protection setting for thermal power units in regional power grid including new energy Research on Analytic Method of Power System Frequency Response Characteristics under Large Power Disturbance A Transmission System Planning Method Considering Fuzzy Model of Load and Interval Model of Renewable Power Analysis of the Impact of Trading Pattern on PV Plant Investment in Spot Market
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
现在去查看 取消
×
提示
确定
0
微信
客服QQ
Book学术公众号 扫码关注我们
反馈
×
意见反馈
请填写您的意见或建议
请填写您的手机或邮箱
已复制链接
已复制链接
快去分享给好友吧!
我知道了
×
扫码分享
扫码分享
Book学术官方微信
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术
文献互助 智能选刊 最新文献 互助须知 联系我们:info@booksci.cn
Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。
Copyright © 2023 Book学术 All rights reserved.
ghs 京公网安备 11010802042870号 京ICP备2023020795号-1