丹绒霹雳海防基地和二级海滩建设项目中钻孔灌注桩和桩基与施工时间和成本的对比分析

Alifiandi Varian, Putri Suci Mawariza
{"title":"丹绒霹雳海防基地和二级海滩建设项目中钻孔灌注桩和桩基与施工时间和成本的对比分析","authors":"Alifiandi Varian, Putri Suci Mawariza","doi":"10.30736/cvl.v8i2.1099","DOIUrl":null,"url":null,"abstract":"In this project using a pile foundation, but during the foundation work there were several obstacles, namely hydraulic tools that were still not ready to use, hydraulic tool repairs, and piles that were one week late, causing delays in foundation work.Therefore workers cannot work optimally while waiting for the tools to arrive. In addition to delays, there are also cost overruns where workers are still being paid for work that is not optimal, so it is necessary to compare these foundations with other foundations in order to find differences in foundations that are more efficient and minimize the problems that have occurred. From the results of data processing, it can be seen that the duration of time required for the preparatory work to the 30x30cm pile foundation with a depth of 16m for 65 points on the class 2 marine and beach guard base of Tanjung Perak is 56 days and requires a fee of IDR 655,305,366.00. For the duration of the preparatory work up to the 30cm bore pile foundation with a depth of 16m as many as 65 points on the class 2 marine and beach guard base Tanjung Perak is 59 days and requires a fee of IDR 520,779,603.00. Then the difference in time between the pile foundation and the bore pile foundation is 12 days. The pile foundation can save as much as 21.4% or 12 days of time from the bore pile foundation.","PeriodicalId":282199,"journal":{"name":"Civilla : Jurnal Teknik Sipil Universitas Islam Lamongan","volume":"55 1","pages":""},"PeriodicalIF":0.0000,"publicationDate":"2023-09-15","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Comparison Analysis of Bore Pile Foundations and Piles to Time and Cost of Construction in Tanjung Perak Sea Keeping Base and Class II Beach Construction Project\",\"authors\":\"Alifiandi Varian, Putri Suci Mawariza\",\"doi\":\"10.30736/cvl.v8i2.1099\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"In this project using a pile foundation, but during the foundation work there were several obstacles, namely hydraulic tools that were still not ready to use, hydraulic tool repairs, and piles that were one week late, causing delays in foundation work.Therefore workers cannot work optimally while waiting for the tools to arrive. In addition to delays, there are also cost overruns where workers are still being paid for work that is not optimal, so it is necessary to compare these foundations with other foundations in order to find differences in foundations that are more efficient and minimize the problems that have occurred. From the results of data processing, it can be seen that the duration of time required for the preparatory work to the 30x30cm pile foundation with a depth of 16m for 65 points on the class 2 marine and beach guard base of Tanjung Perak is 56 days and requires a fee of IDR 655,305,366.00. For the duration of the preparatory work up to the 30cm bore pile foundation with a depth of 16m as many as 65 points on the class 2 marine and beach guard base Tanjung Perak is 59 days and requires a fee of IDR 520,779,603.00. Then the difference in time between the pile foundation and the bore pile foundation is 12 days. The pile foundation can save as much as 21.4% or 12 days of time from the bore pile foundation.\",\"PeriodicalId\":282199,\"journal\":{\"name\":\"Civilla : Jurnal Teknik Sipil Universitas Islam Lamongan\",\"volume\":\"55 1\",\"pages\":\"\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2023-09-15\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Civilla : Jurnal Teknik Sipil Universitas Islam Lamongan\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.30736/cvl.v8i2.1099\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Civilla : Jurnal Teknik Sipil Universitas Islam Lamongan","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.30736/cvl.v8i2.1099","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

摘要

在该项目中,使用的是桩基础,但在基础工程中出现了几个障碍,即液压工具仍未准备就绪,液压工具维修,以及桩迟了一周,导致基础工程延误。因此,工人在等待工具到达时无法进行最佳工作。除了延误,还出现了成本超支的情况,即工人仍在为并非最佳的工作支付报酬,因此有必要将这些地基与其他地基进行比较,以便找到效率更高的地基的差异,并尽量减少已出现的问题。从数据处理结果可以看出,丹绒霹雳二级海事和海滩警卫基地 65 个点的 30x30cm 桩基(深度 16 米)的准备工作所需时间为 56 天,所需费用为 655,305,366.00 印尼盾。在丹绒霹雳二级海事和海滩警卫基地的 65 个点上,桩基深度为 16 米,钻孔深度为 30 厘米的准备工作持续时间为 59 天,所需费用为 520,779,603.00 印尼盾。那么,桩基础与钻孔桩基础的时间差为 12 天。桩基础可比钻孔桩基础节省 21.4% 或 12 天的时间。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
查看原文
分享 分享
微信好友 朋友圈 QQ好友 复制链接
本刊更多论文
Comparison Analysis of Bore Pile Foundations and Piles to Time and Cost of Construction in Tanjung Perak Sea Keeping Base and Class II Beach Construction Project
In this project using a pile foundation, but during the foundation work there were several obstacles, namely hydraulic tools that were still not ready to use, hydraulic tool repairs, and piles that were one week late, causing delays in foundation work.Therefore workers cannot work optimally while waiting for the tools to arrive. In addition to delays, there are also cost overruns where workers are still being paid for work that is not optimal, so it is necessary to compare these foundations with other foundations in order to find differences in foundations that are more efficient and minimize the problems that have occurred. From the results of data processing, it can be seen that the duration of time required for the preparatory work to the 30x30cm pile foundation with a depth of 16m for 65 points on the class 2 marine and beach guard base of Tanjung Perak is 56 days and requires a fee of IDR 655,305,366.00. For the duration of the preparatory work up to the 30cm bore pile foundation with a depth of 16m as many as 65 points on the class 2 marine and beach guard base Tanjung Perak is 59 days and requires a fee of IDR 520,779,603.00. Then the difference in time between the pile foundation and the bore pile foundation is 12 days. The pile foundation can save as much as 21.4% or 12 days of time from the bore pile foundation.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
期刊最新文献
Analysis of Concrete Strength Analysis K-250 With Additional Asbestos Waste Powder as a Substitute of Fine Aggregate The Shear Strength of Clay Stabilized with Palm Bunch Ash and Cement Evaluation of Wastewater Management System Implementation in Tarakan City Selumit Beach Area Analysis of Determinants of Consumer Decisions on the Use of Trans Banyumas and Gojek Cost and Time Comparison Analysis Using Microsoft Project (Case Study: Phase VII Work of the Surabaya Tanjung Perak Berlian Pier Structure Strengthening Project)
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
现在去查看 取消
×
提示
确定
0
微信
客服QQ
Book学术公众号 扫码关注我们
反馈
×
意见反馈
请填写您的意见或建议
请填写您的手机或邮箱
已复制链接
已复制链接
快去分享给好友吧!
我知道了
×
扫码分享
扫码分享
Book学术官方微信
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术
文献互助 智能选刊 最新文献 互助须知 联系我们:info@booksci.cn
Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。
Copyright © 2023 Book学术 All rights reserved.
ghs 京公网安备 11010802042870号 京ICP备2023020795号-1