Yu. V. Smolkin, S. A. Kanatov, D. A. Sobolev, D. V. Stepanov, E. N. Kulakov
{"title":"通过更准确地监测热效率指标提高 VVER 型核电厂的发电量","authors":"Yu. V. Smolkin, S. A. Kanatov, D. A. Sobolev, D. V. Stepanov, E. N. Kulakov","doi":"10.1134/S0040601524030091","DOIUrl":null,"url":null,"abstract":"<p>Monitoring of thermal efficiency is of utmost importance for securing efficient NPP operation. To this end, the measurement instruments should have accuracy sufficient for the possibility of determining the actual values of thermal cycle circuit parameters, thermal efficiency, and deviations of the turbine set characteristics from their standardized indicators. The error with which the reactor thermal power is determined using the reactor core thermal-physical parameters and the steam generator parameters is estimated. It is shown that the best accuracy of determining the reactor thermal power can only be achieved through improving the accuracy of determining the steam generator thermal power. An analysis has shown that the error of determining the reactor thermal power is by more than 95% due to the error of determining the feed water flowrate. If we succeed in achieving more accurate determination of the reactor thermal power, it will be possible to obtain more accurate data on the electricity generation during operation at the nominal parameters in the mode with a specified neutron power due to maintaining of the reactor plant’s actual thermal power closest to its design value; in addition, it will be possible to extend the range of power outputs available for operation during operation in the mode of maintaining the specified electric power output by increasing its maximal value. Given the specified period of NPP operation, the maximum of its energy production serves as one of the criteria for economically efficient NPP operation. By using the developed mathematical model of the turbine set used in the NPP constructed according to the AES-2006 conceptual design (with a VVER-1200 reactor), the authors have revealed the effect of the error of determining the thermal cycle circuit parameters on the power unit electric power output and the parameters that have the highest influence on the error of estimating the electric power output. The influence of the error of determining the turbine thermal parameters, moisture separation and steam reheating, high- and low-pressure regeneration, and the turbine set low-grade heat part was analyzed, and the total error of determining the electric power output has been obtained based on the analysis results. These data make it possible to formulate the requirements for the accuracy of flowrate, temperature, and pressure measurements depending on the allowable error of determining the electric power output. An analysis of the operational data of the Leningrad-2 NPP, Novovoronezh-2 NPP, and Belarussian NPP power units has shown that the potential of increasing the electric power output due to improved accuracy of determining the thermal cycle circuit parameters makes 10–15 MW.</p>","PeriodicalId":799,"journal":{"name":"Thermal Engineering","volume":"71 3","pages":"215 - 222"},"PeriodicalIF":0.9000,"publicationDate":"2024-04-09","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Increasing the Power Output of VVER-Based NPPs through More Accurately Monitoring the Thermal Efficiency Indicators\",\"authors\":\"Yu. V. Smolkin, S. A. Kanatov, D. A. Sobolev, D. V. Stepanov, E. N. Kulakov\",\"doi\":\"10.1134/S0040601524030091\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"<p>Monitoring of thermal efficiency is of utmost importance for securing efficient NPP operation. To this end, the measurement instruments should have accuracy sufficient for the possibility of determining the actual values of thermal cycle circuit parameters, thermal efficiency, and deviations of the turbine set characteristics from their standardized indicators. The error with which the reactor thermal power is determined using the reactor core thermal-physical parameters and the steam generator parameters is estimated. It is shown that the best accuracy of determining the reactor thermal power can only be achieved through improving the accuracy of determining the steam generator thermal power. An analysis has shown that the error of determining the reactor thermal power is by more than 95% due to the error of determining the feed water flowrate. If we succeed in achieving more accurate determination of the reactor thermal power, it will be possible to obtain more accurate data on the electricity generation during operation at the nominal parameters in the mode with a specified neutron power due to maintaining of the reactor plant’s actual thermal power closest to its design value; in addition, it will be possible to extend the range of power outputs available for operation during operation in the mode of maintaining the specified electric power output by increasing its maximal value. Given the specified period of NPP operation, the maximum of its energy production serves as one of the criteria for economically efficient NPP operation. By using the developed mathematical model of the turbine set used in the NPP constructed according to the AES-2006 conceptual design (with a VVER-1200 reactor), the authors have revealed the effect of the error of determining the thermal cycle circuit parameters on the power unit electric power output and the parameters that have the highest influence on the error of estimating the electric power output. The influence of the error of determining the turbine thermal parameters, moisture separation and steam reheating, high- and low-pressure regeneration, and the turbine set low-grade heat part was analyzed, and the total error of determining the electric power output has been obtained based on the analysis results. These data make it possible to formulate the requirements for the accuracy of flowrate, temperature, and pressure measurements depending on the allowable error of determining the electric power output. An analysis of the operational data of the Leningrad-2 NPP, Novovoronezh-2 NPP, and Belarussian NPP power units has shown that the potential of increasing the electric power output due to improved accuracy of determining the thermal cycle circuit parameters makes 10–15 MW.</p>\",\"PeriodicalId\":799,\"journal\":{\"name\":\"Thermal Engineering\",\"volume\":\"71 3\",\"pages\":\"215 - 222\"},\"PeriodicalIF\":0.9000,\"publicationDate\":\"2024-04-09\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Thermal Engineering\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://link.springer.com/article/10.1134/S0040601524030091\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"Q4\",\"JCRName\":\"ENERGY & FUELS\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Thermal Engineering","FirstCategoryId":"1085","ListUrlMain":"https://link.springer.com/article/10.1134/S0040601524030091","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"Q4","JCRName":"ENERGY & FUELS","Score":null,"Total":0}
引用次数: 0
摘要
Abstract-Monitoring of thermal efficiency is of utmost importance for ensuring efficient NPP operation.为此,测量仪器的精度应足以确定热循环回路参数的实际值、热效率以及汽轮机组特性与其标准化指标的偏差。利用反应堆堆芯热物理参数和蒸汽发生器参数对反应堆热功率的误差进行了估算。结果表明,只有通过提高确定蒸汽发生器热功率的精度,才能达到确定反应堆热功率的最佳精度。分析表明,由于给水流量的确定存在误差,反应堆热功率的确定误差超过 95%。如果我们能够更准确地确定反应堆热功率,就有可能获得更准确的发电量数据,使反应堆厂房的实际热功率保持在最接近其设计值的水平,从而在中子功率模式下以额定参数运行。在指定的核电厂运行周期内,最大发电量是核电厂经济高效运行的标准之一。通过使用所开发的根据 AES-2006 概念设计(配备 VVER-1200 反应堆)建造的核电站所用汽轮机组的数学模型,作者揭示了热循环回路参数的确定误差对机组电力输出的影响,以及对电力输出估计误差影响最大的参数。分析了确定汽轮机热力参数、水分分离和蒸汽再加热、高低压再生和汽轮机组低档热量部分的误差的影响,并根据分析结果得出了确定电力输出的总误差。通过这些数据,可以根据确定电力输出的允许误差来制定流量、温度和压力测量精度的要求。对列宁格勒-2 号核电厂、新沃罗涅日-2 号核电厂和白俄罗斯核电厂机组运行数据的分析表明,通过提高热循环回路参数的确定精度,可增加 10-15 兆瓦的电力输出。
Increasing the Power Output of VVER-Based NPPs through More Accurately Monitoring the Thermal Efficiency Indicators
Monitoring of thermal efficiency is of utmost importance for securing efficient NPP operation. To this end, the measurement instruments should have accuracy sufficient for the possibility of determining the actual values of thermal cycle circuit parameters, thermal efficiency, and deviations of the turbine set characteristics from their standardized indicators. The error with which the reactor thermal power is determined using the reactor core thermal-physical parameters and the steam generator parameters is estimated. It is shown that the best accuracy of determining the reactor thermal power can only be achieved through improving the accuracy of determining the steam generator thermal power. An analysis has shown that the error of determining the reactor thermal power is by more than 95% due to the error of determining the feed water flowrate. If we succeed in achieving more accurate determination of the reactor thermal power, it will be possible to obtain more accurate data on the electricity generation during operation at the nominal parameters in the mode with a specified neutron power due to maintaining of the reactor plant’s actual thermal power closest to its design value; in addition, it will be possible to extend the range of power outputs available for operation during operation in the mode of maintaining the specified electric power output by increasing its maximal value. Given the specified period of NPP operation, the maximum of its energy production serves as one of the criteria for economically efficient NPP operation. By using the developed mathematical model of the turbine set used in the NPP constructed according to the AES-2006 conceptual design (with a VVER-1200 reactor), the authors have revealed the effect of the error of determining the thermal cycle circuit parameters on the power unit electric power output and the parameters that have the highest influence on the error of estimating the electric power output. The influence of the error of determining the turbine thermal parameters, moisture separation and steam reheating, high- and low-pressure regeneration, and the turbine set low-grade heat part was analyzed, and the total error of determining the electric power output has been obtained based on the analysis results. These data make it possible to formulate the requirements for the accuracy of flowrate, temperature, and pressure measurements depending on the allowable error of determining the electric power output. An analysis of the operational data of the Leningrad-2 NPP, Novovoronezh-2 NPP, and Belarussian NPP power units has shown that the potential of increasing the electric power output due to improved accuracy of determining the thermal cycle circuit parameters makes 10–15 MW.