Rabah Benabid, Pierre Henneaux, Pierre-Etienne Labeau
{"title":"对核电厂以开关站为中心的 LOOP 事件频率和持续时间进行概率评估","authors":"Rabah Benabid, Pierre Henneaux, Pierre-Etienne Labeau","doi":"10.1007/s13198-024-02416-6","DOIUrl":null,"url":null,"abstract":"<p>The occurrence of a Loss Of Offsite Power (LOOP) event can be a major threat to nuclear safety due to the dependence of auxiliary systems on electrical energy. Probabilistic safety assessments of nuclear power plants require, thus, estimates of the frequencies and durations of such LOOP events. These estimates are usually based on past statistical data, which is not always relevant. Model-based approaches are thus needed. This paper proposes an analytical method to estimate the frequency and duration of switchyard-centered LOOP events, which constitute one of the four main categories of LOOP events. The proposed method is mainly based on the identification of active minimal cut sets, considering the behavior of circuit breakers against faults according to their coordination and selectivity. Adapted versions of the Risk Reduction Worth and Fussel–Vesely importance factors are proposed to evaluate the impact of components on the switchyard-centered LOOP event frequency. Furthermore, uncertainty analysis is developed and performed. Various generic plant connection schemes are used for application. Results demonstrate the applicability of the methodology to estimate the frequency and duration of switchyard-centered LOOP events, and to identify optimal ways to reduce the risk by modifying the switchyard configuration.</p>","PeriodicalId":14463,"journal":{"name":"International Journal of System Assurance Engineering and Management","volume":"37 1","pages":""},"PeriodicalIF":1.6000,"publicationDate":"2024-07-17","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Probabilistic assessment of switchyard-centered LOOP event frequency and duration in an NPP\",\"authors\":\"Rabah Benabid, Pierre Henneaux, Pierre-Etienne Labeau\",\"doi\":\"10.1007/s13198-024-02416-6\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"<p>The occurrence of a Loss Of Offsite Power (LOOP) event can be a major threat to nuclear safety due to the dependence of auxiliary systems on electrical energy. Probabilistic safety assessments of nuclear power plants require, thus, estimates of the frequencies and durations of such LOOP events. These estimates are usually based on past statistical data, which is not always relevant. Model-based approaches are thus needed. This paper proposes an analytical method to estimate the frequency and duration of switchyard-centered LOOP events, which constitute one of the four main categories of LOOP events. The proposed method is mainly based on the identification of active minimal cut sets, considering the behavior of circuit breakers against faults according to their coordination and selectivity. Adapted versions of the Risk Reduction Worth and Fussel–Vesely importance factors are proposed to evaluate the impact of components on the switchyard-centered LOOP event frequency. Furthermore, uncertainty analysis is developed and performed. Various generic plant connection schemes are used for application. Results demonstrate the applicability of the methodology to estimate the frequency and duration of switchyard-centered LOOP events, and to identify optimal ways to reduce the risk by modifying the switchyard configuration.</p>\",\"PeriodicalId\":14463,\"journal\":{\"name\":\"International Journal of System Assurance Engineering and Management\",\"volume\":\"37 1\",\"pages\":\"\"},\"PeriodicalIF\":1.6000,\"publicationDate\":\"2024-07-17\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"International Journal of System Assurance Engineering and Management\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.1007/s13198-024-02416-6\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"Q2\",\"JCRName\":\"ENGINEERING, MULTIDISCIPLINARY\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"International Journal of System Assurance Engineering and Management","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1007/s13198-024-02416-6","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"Q2","JCRName":"ENGINEERING, MULTIDISCIPLINARY","Score":null,"Total":0}
Probabilistic assessment of switchyard-centered LOOP event frequency and duration in an NPP
The occurrence of a Loss Of Offsite Power (LOOP) event can be a major threat to nuclear safety due to the dependence of auxiliary systems on electrical energy. Probabilistic safety assessments of nuclear power plants require, thus, estimates of the frequencies and durations of such LOOP events. These estimates are usually based on past statistical data, which is not always relevant. Model-based approaches are thus needed. This paper proposes an analytical method to estimate the frequency and duration of switchyard-centered LOOP events, which constitute one of the four main categories of LOOP events. The proposed method is mainly based on the identification of active minimal cut sets, considering the behavior of circuit breakers against faults according to their coordination and selectivity. Adapted versions of the Risk Reduction Worth and Fussel–Vesely importance factors are proposed to evaluate the impact of components on the switchyard-centered LOOP event frequency. Furthermore, uncertainty analysis is developed and performed. Various generic plant connection schemes are used for application. Results demonstrate the applicability of the methodology to estimate the frequency and duration of switchyard-centered LOOP events, and to identify optimal ways to reduce the risk by modifying the switchyard configuration.
期刊介绍:
This Journal is established with a view to cater to increased awareness for high quality research in the seamless integration of heterogeneous technologies to formulate bankable solutions to the emergent complex engineering problems.
Assurance engineering could be thought of as relating to the provision of higher confidence in the reliable and secure implementation of a system’s critical characteristic features through the espousal of a holistic approach by using a wide variety of cross disciplinary tools and techniques. Successful realization of sustainable and dependable products, systems and services involves an extensive adoption of Reliability, Quality, Safety and Risk related procedures for achieving high assurancelevels of performance; also pivotal are the management issues related to risk and uncertainty that govern the practical constraints encountered in their deployment. It is our intention to provide a platform for the modeling and analysis of large engineering systems, among the other aforementioned allied goals of systems assurance engineering, leading to the enforcement of performance enhancement measures. Achieving a fine balance between theory and practice is the primary focus. The Journal only publishes high quality papers that have passed the rigorous peer review procedure of an archival scientific Journal. The aim is an increasing number of submissions, wide circulation and a high impact factor.