{"title":"哥伦比亚可再生能源拍卖政策评估:聚光太阳能发电厂的促进因素还是障碍","authors":"Richard Rangel , Adriana Arango-Manrique , Lesme Corredor , Marco Sanjuan","doi":"10.1016/j.enpol.2024.114300","DOIUrl":null,"url":null,"abstract":"<div><p>Auctions are an alternative for introducing renewable energy (RE) projects into electricity markets at competitive prices. Colombia added 2.2 GW capacity of RE through this mechanism. Nevertheless, 94% of the awarded generation is allocated between 12 a.m. and 5 p.m. because of a lack of low-cost storage. Integrating concentrating solar power plants (CSP) could be relevant in tackling this issue. Therefore, a preliminary step is to determine if Colombian instruments benefit the deployment of CSP and trigger the discussion about its future in the country. In this work, we evaluate how auction mechanisms and fiscal incentives (FI) influence the Levelized Cost of Electricity (LCOE) and Internal Rate of Return (IRR) for two CSP configurations. The results indicate that FIs reduce capital expenditures between 17.11% and 19.45%, reaching similar LCOEs to those reported internationally. However, energy prices higher than USD 150/MWh are required to achieve an adequate IRR. Regarding the auction design, it is observed that a “security criterion” leads to a significant loss of competitiveness for CSP as it neglects its possibility to support demand at night. Policy suggestions are provided for a level playing field where low-cost solutions can coexist with dispatchable renewable power generation.</p></div>","PeriodicalId":11672,"journal":{"name":"Energy Policy","volume":"193 ","pages":"Article 114300"},"PeriodicalIF":9.3000,"publicationDate":"2024-08-27","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Assessment of Colombian renewable energy auctions policy: Enabler or barrier for concentrating solar power plants\",\"authors\":\"Richard Rangel , Adriana Arango-Manrique , Lesme Corredor , Marco Sanjuan\",\"doi\":\"10.1016/j.enpol.2024.114300\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"<div><p>Auctions are an alternative for introducing renewable energy (RE) projects into electricity markets at competitive prices. Colombia added 2.2 GW capacity of RE through this mechanism. Nevertheless, 94% of the awarded generation is allocated between 12 a.m. and 5 p.m. because of a lack of low-cost storage. Integrating concentrating solar power plants (CSP) could be relevant in tackling this issue. Therefore, a preliminary step is to determine if Colombian instruments benefit the deployment of CSP and trigger the discussion about its future in the country. In this work, we evaluate how auction mechanisms and fiscal incentives (FI) influence the Levelized Cost of Electricity (LCOE) and Internal Rate of Return (IRR) for two CSP configurations. The results indicate that FIs reduce capital expenditures between 17.11% and 19.45%, reaching similar LCOEs to those reported internationally. However, energy prices higher than USD 150/MWh are required to achieve an adequate IRR. Regarding the auction design, it is observed that a “security criterion” leads to a significant loss of competitiveness for CSP as it neglects its possibility to support demand at night. Policy suggestions are provided for a level playing field where low-cost solutions can coexist with dispatchable renewable power generation.</p></div>\",\"PeriodicalId\":11672,\"journal\":{\"name\":\"Energy Policy\",\"volume\":\"193 \",\"pages\":\"Article 114300\"},\"PeriodicalIF\":9.3000,\"publicationDate\":\"2024-08-27\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Energy Policy\",\"FirstCategoryId\":\"96\",\"ListUrlMain\":\"https://www.sciencedirect.com/science/article/pii/S0301421524003203\",\"RegionNum\":2,\"RegionCategory\":\"经济学\",\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"Q1\",\"JCRName\":\"ECONOMICS\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Energy Policy","FirstCategoryId":"96","ListUrlMain":"https://www.sciencedirect.com/science/article/pii/S0301421524003203","RegionNum":2,"RegionCategory":"经济学","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"Q1","JCRName":"ECONOMICS","Score":null,"Total":0}
Assessment of Colombian renewable energy auctions policy: Enabler or barrier for concentrating solar power plants
Auctions are an alternative for introducing renewable energy (RE) projects into electricity markets at competitive prices. Colombia added 2.2 GW capacity of RE through this mechanism. Nevertheless, 94% of the awarded generation is allocated between 12 a.m. and 5 p.m. because of a lack of low-cost storage. Integrating concentrating solar power plants (CSP) could be relevant in tackling this issue. Therefore, a preliminary step is to determine if Colombian instruments benefit the deployment of CSP and trigger the discussion about its future in the country. In this work, we evaluate how auction mechanisms and fiscal incentives (FI) influence the Levelized Cost of Electricity (LCOE) and Internal Rate of Return (IRR) for two CSP configurations. The results indicate that FIs reduce capital expenditures between 17.11% and 19.45%, reaching similar LCOEs to those reported internationally. However, energy prices higher than USD 150/MWh are required to achieve an adequate IRR. Regarding the auction design, it is observed that a “security criterion” leads to a significant loss of competitiveness for CSP as it neglects its possibility to support demand at night. Policy suggestions are provided for a level playing field where low-cost solutions can coexist with dispatchable renewable power generation.
期刊介绍:
Energy policy is the manner in which a given entity (often governmental) has decided to address issues of energy development including energy conversion, distribution and use as well as reduction of greenhouse gas emissions in order to contribute to climate change mitigation. The attributes of energy policy may include legislation, international treaties, incentives to investment, guidelines for energy conservation, taxation and other public policy techniques.
Energy policy is closely related to climate change policy because totalled worldwide the energy sector emits more greenhouse gas than other sectors.