考虑合同索赔的建筑材料可追溯采购的稳健优化模型

IF 9.6 1区 工程技术 Q1 CONSTRUCTION & BUILDING TECHNOLOGY Automation in Construction Pub Date : 2024-11-06 DOI:10.1016/j.autcon.2024.105847
{"title":"考虑合同索赔的建筑材料可追溯采购的稳健优化模型","authors":"","doi":"10.1016/j.autcon.2024.105847","DOIUrl":null,"url":null,"abstract":"<div><div>In claim contracts, project owners and contractors set negotiated prices and exemption amounts for price adjustments to deal with the uncertainty of material prices, which is often overlooked in the optimization of procurement strategies. Therefore, considering contract claims, this paper constructs an optimization model for contractors’ traceable procurement strategies to address the multi-stage, multi-source procurement issue. A robust optimization model is used to consider the uncertainty of procurement prices, and the robust parameter is set to flexibly control the robustness of the solutions. The results indicate that contractors with different risk attitudes have the same preference for the exemption amount, but they exhibit varying sensitivities to the exemption amount and also have different preferences regarding the negotiated price. Furthermore, the study reveals that negotiated price exerts an anchoring effect on the procurement strategies of contractors.</div></div>","PeriodicalId":8660,"journal":{"name":"Automation in Construction","volume":null,"pages":null},"PeriodicalIF":9.6000,"publicationDate":"2024-11-06","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Robust optimization model for traceable procurement of construction materials considering contract claims\",\"authors\":\"\",\"doi\":\"10.1016/j.autcon.2024.105847\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"<div><div>In claim contracts, project owners and contractors set negotiated prices and exemption amounts for price adjustments to deal with the uncertainty of material prices, which is often overlooked in the optimization of procurement strategies. Therefore, considering contract claims, this paper constructs an optimization model for contractors’ traceable procurement strategies to address the multi-stage, multi-source procurement issue. A robust optimization model is used to consider the uncertainty of procurement prices, and the robust parameter is set to flexibly control the robustness of the solutions. The results indicate that contractors with different risk attitudes have the same preference for the exemption amount, but they exhibit varying sensitivities to the exemption amount and also have different preferences regarding the negotiated price. Furthermore, the study reveals that negotiated price exerts an anchoring effect on the procurement strategies of contractors.</div></div>\",\"PeriodicalId\":8660,\"journal\":{\"name\":\"Automation in Construction\",\"volume\":null,\"pages\":null},\"PeriodicalIF\":9.6000,\"publicationDate\":\"2024-11-06\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Automation in Construction\",\"FirstCategoryId\":\"5\",\"ListUrlMain\":\"https://www.sciencedirect.com/science/article/pii/S0926580524005831\",\"RegionNum\":1,\"RegionCategory\":\"工程技术\",\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"Q1\",\"JCRName\":\"CONSTRUCTION & BUILDING TECHNOLOGY\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Automation in Construction","FirstCategoryId":"5","ListUrlMain":"https://www.sciencedirect.com/science/article/pii/S0926580524005831","RegionNum":1,"RegionCategory":"工程技术","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"Q1","JCRName":"CONSTRUCTION & BUILDING TECHNOLOGY","Score":null,"Total":0}
引用次数: 0

摘要

在索赔合同中,项目业主和承包商会设定协商价格和价格调整免责金额,以应对材料价格的不确定性,而这在采购策略优化中往往被忽视。因此,考虑到合同索赔,本文构建了承包商可追溯采购策略的优化模型,以解决多阶段、多来源的采购问题。采用稳健优化模型来考虑采购价格的不确定性,并设置稳健参数来灵活控制解决方案的稳健性。结果表明,不同风险态度的承包商对免责金额的偏好相同,但对免责金额的敏感度不同,对谈判价格的偏好也不同。此外,研究还表明,谈判价格对承包商的采购战略具有锚定效应。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
查看原文
分享 分享
微信好友 朋友圈 QQ好友 复制链接
本刊更多论文
Robust optimization model for traceable procurement of construction materials considering contract claims
In claim contracts, project owners and contractors set negotiated prices and exemption amounts for price adjustments to deal with the uncertainty of material prices, which is often overlooked in the optimization of procurement strategies. Therefore, considering contract claims, this paper constructs an optimization model for contractors’ traceable procurement strategies to address the multi-stage, multi-source procurement issue. A robust optimization model is used to consider the uncertainty of procurement prices, and the robust parameter is set to flexibly control the robustness of the solutions. The results indicate that contractors with different risk attitudes have the same preference for the exemption amount, but they exhibit varying sensitivities to the exemption amount and also have different preferences regarding the negotiated price. Furthermore, the study reveals that negotiated price exerts an anchoring effect on the procurement strategies of contractors.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
Automation in Construction
Automation in Construction 工程技术-工程:土木
CiteScore
19.20
自引率
16.50%
发文量
563
审稿时长
8.5 months
期刊介绍: Automation in Construction is an international journal that focuses on publishing original research papers related to the use of Information Technologies in various aspects of the construction industry. The journal covers topics such as design, engineering, construction technologies, and the maintenance and management of constructed facilities. The scope of Automation in Construction is extensive and covers all stages of the construction life cycle. This includes initial planning and design, construction of the facility, operation and maintenance, as well as the eventual dismantling and recycling of buildings and engineering structures.
期刊最新文献
Robust optimization model for traceable procurement of construction materials considering contract claims Editorial Board Rutting extraction from vehicle-borne laser point clouds Self-supervised monocular depth estimation on construction sites in low-light conditions and dynamic scenes Automated reinforcement of 3D-printed engineered cementitious composite beams
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
现在去查看 取消
×
提示
确定
0
微信
客服QQ
Book学术公众号 扫码关注我们
反馈
×
意见反馈
请填写您的意见或建议
请填写您的手机或邮箱
已复制链接
已复制链接
快去分享给好友吧!
我知道了
×
扫码分享
扫码分享
Book学术官方微信
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术
文献互助 智能选刊 最新文献 互助须知 联系我们:info@booksci.cn
Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。
Copyright © 2023 Book学术 All rights reserved.
ghs 京公网安备 11010802042870号 京ICP备2023020795号-1