结合单个项目风险、进度影响、中断和项目风险相关性的项目组合优化模拟法

IF 6.7 1区 工程技术 Q1 COMPUTER SCIENCE, INTERDISCIPLINARY APPLICATIONS Computers & Industrial Engineering Pub Date : 2024-11-07 DOI:10.1016/j.cie.2024.110694
Miguel Saiz , Laura Calvet , Angel A. Juan , David Lopez-Lopez
{"title":"结合单个项目风险、进度影响、中断和项目风险相关性的项目组合优化模拟法","authors":"Miguel Saiz ,&nbsp;Laura Calvet ,&nbsp;Angel A. Juan ,&nbsp;David Lopez-Lopez","doi":"10.1016/j.cie.2024.110694","DOIUrl":null,"url":null,"abstract":"<div><div>This paper introduces a simheuristic method to the Project Portfolio Selection Problem, designed to maximize the net present value of the portfolio while considering uncertain costs, schedules, interruptions, and inter-project risk correlations. The novel approach combines techniques from Monte Carlo simulation, critical path analysis, queuing theory, and optimization, integrating baseline schedules, project-level uncertainties, budgetary constraints, and risk correlations in a single model. A computational experiment is conducted on a realistic set of ten candidate projects and validated respect to the deterministic version of the problem, demonstrating its ability to select near optimal portfolio proposals with varying combinations of risk and net present value. The findings highlight the significant impact of factors such as contingency reserve allocation policies, operational interruptions, and project risk correlations on portfolio decisions, constituting a helpful framework for the decision-makers at portfolio level.</div></div>","PeriodicalId":55220,"journal":{"name":"Computers & Industrial Engineering","volume":"198 ","pages":"Article 110694"},"PeriodicalIF":6.7000,"publicationDate":"2024-11-07","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"A simheuristic for project portfolio optimization combining individual project risk, scheduling effects, interruptions, and project risk correlations\",\"authors\":\"Miguel Saiz ,&nbsp;Laura Calvet ,&nbsp;Angel A. Juan ,&nbsp;David Lopez-Lopez\",\"doi\":\"10.1016/j.cie.2024.110694\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"<div><div>This paper introduces a simheuristic method to the Project Portfolio Selection Problem, designed to maximize the net present value of the portfolio while considering uncertain costs, schedules, interruptions, and inter-project risk correlations. The novel approach combines techniques from Monte Carlo simulation, critical path analysis, queuing theory, and optimization, integrating baseline schedules, project-level uncertainties, budgetary constraints, and risk correlations in a single model. A computational experiment is conducted on a realistic set of ten candidate projects and validated respect to the deterministic version of the problem, demonstrating its ability to select near optimal portfolio proposals with varying combinations of risk and net present value. The findings highlight the significant impact of factors such as contingency reserve allocation policies, operational interruptions, and project risk correlations on portfolio decisions, constituting a helpful framework for the decision-makers at portfolio level.</div></div>\",\"PeriodicalId\":55220,\"journal\":{\"name\":\"Computers & Industrial Engineering\",\"volume\":\"198 \",\"pages\":\"Article 110694\"},\"PeriodicalIF\":6.7000,\"publicationDate\":\"2024-11-07\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Computers & Industrial Engineering\",\"FirstCategoryId\":\"5\",\"ListUrlMain\":\"https://www.sciencedirect.com/science/article/pii/S0360835224008167\",\"RegionNum\":1,\"RegionCategory\":\"工程技术\",\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"Q1\",\"JCRName\":\"COMPUTER SCIENCE, INTERDISCIPLINARY APPLICATIONS\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Computers & Industrial Engineering","FirstCategoryId":"5","ListUrlMain":"https://www.sciencedirect.com/science/article/pii/S0360835224008167","RegionNum":1,"RegionCategory":"工程技术","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"Q1","JCRName":"COMPUTER SCIENCE, INTERDISCIPLINARY APPLICATIONS","Score":null,"Total":0}
引用次数: 0

摘要

本文针对项目组合选择问题介绍了一种模拟方法,旨在最大化项目组合的净现值,同时考虑不确定的成本、进度、中断和项目间风险相关性。这种新方法结合了蒙特卡罗模拟、关键路径分析、排队理论和优化等技术,将基线进度、项目级不确定性、预算约束和风险相关性整合到一个模型中。计算实验在一组现实的十个候选项目上进行,并对问题的确定性版本进行了验证,证明了该方法能够选择具有不同风险和净现值组合的接近最优的投资组合建议。研究结果强调了应急储备分配政策、运营中断和项目风险相关性等因素对投资组合决策的重要影响,为投资组合层面的决策者提供了一个有用的框架。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
查看原文
分享 分享
微信好友 朋友圈 QQ好友 复制链接
本刊更多论文
A simheuristic for project portfolio optimization combining individual project risk, scheduling effects, interruptions, and project risk correlations
This paper introduces a simheuristic method to the Project Portfolio Selection Problem, designed to maximize the net present value of the portfolio while considering uncertain costs, schedules, interruptions, and inter-project risk correlations. The novel approach combines techniques from Monte Carlo simulation, critical path analysis, queuing theory, and optimization, integrating baseline schedules, project-level uncertainties, budgetary constraints, and risk correlations in a single model. A computational experiment is conducted on a realistic set of ten candidate projects and validated respect to the deterministic version of the problem, demonstrating its ability to select near optimal portfolio proposals with varying combinations of risk and net present value. The findings highlight the significant impact of factors such as contingency reserve allocation policies, operational interruptions, and project risk correlations on portfolio decisions, constituting a helpful framework for the decision-makers at portfolio level.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
Computers & Industrial Engineering
Computers & Industrial Engineering 工程技术-工程:工业
CiteScore
12.70
自引率
12.70%
发文量
794
审稿时长
10.6 months
期刊介绍: Computers & Industrial Engineering (CAIE) is dedicated to researchers, educators, and practitioners in industrial engineering and related fields. Pioneering the integration of computers in research, education, and practice, industrial engineering has evolved to make computers and electronic communication integral to its domain. CAIE publishes original contributions focusing on the development of novel computerized methodologies to address industrial engineering problems. It also highlights the applications of these methodologies to issues within the broader industrial engineering and associated communities. The journal actively encourages submissions that push the boundaries of fundamental theories and concepts in industrial engineering techniques.
期刊最新文献
Blockchain’s role in operation strategy of power battery closed-loop supply chain Exact formulation and two-stage optimisation method for corridor allocation problem consider separated man-vehicle logistics passage in manufacturing workshops Optimizing speed of a green truckload pickup and delivery routing problem with outsourcing: Heuristic and exact approaches Project portfolio selection with relationship considerations: A random walk with restart based on influencing factors Scenario-based multi-objective optimization for manufacturing reliability with production routes and available machine types
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
现在去查看 取消
×
提示
确定
0
微信
客服QQ
Book学术公众号 扫码关注我们
反馈
×
意见反馈
请填写您的意见或建议
请填写您的手机或邮箱
已复制链接
已复制链接
快去分享给好友吧!
我知道了
×
扫码分享
扫码分享
Book学术官方微信
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术
文献互助 智能选刊 最新文献 互助须知 联系我们:info@booksci.cn
Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。
Copyright © 2023 Book学术 All rights reserved.
ghs 京公网安备 11010802042870号 京ICP备2023020795号-1