{"title":"灾后应急重建项目存在问题的原因分析——以伊拉克为例","authors":"Rasha A Waheeb, B. Andersen","doi":"10.1177/1087724X21990034","DOIUrl":null,"url":null,"abstract":"This study examines the causes of time delays and cost overruns in a selection of thirty post-disaster reconstruction projects in Iraq. Although delay factors have been studied in many countries and contexts, little data exists from countries under the conditions characterizing Iraq during the last 10-15 years. A case study approach was used, with thirty construction projects of different types and sizes selected from the Baghdad region. Project data was gathered from a survey which was used to build statistical relationships between time and cost delay ratios and delay factors in post disaster projects. The most important delay factors identified were contractor failure, redesigning of designs/plans and change orders, security issues, selection of low-price bids, weather factors, and owner failures. Some of these are in line with findings from similar studies in other countries and regions, but some are unique to the Iraqi project sample, such as security issues and low-price bid selection. While many studies have examined factors causing delays and cost overruns, this study offers unique insights into factors that need to be considered when implementing projects for post disaster emergency reconstruction in areas impacted by wars and terrorism.","PeriodicalId":45483,"journal":{"name":"Public Works Management & Policy","volume":"27 1","pages":"61 - 97"},"PeriodicalIF":1.0000,"publicationDate":"2021-02-08","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"https://sci-hub-pdf.com/10.1177/1087724X21990034","citationCount":"17","resultStr":"{\"title\":\"Causes of Problems in Post-Disaster Emergency Re-Construction Projects—Iraq as a Case Study\",\"authors\":\"Rasha A Waheeb, B. Andersen\",\"doi\":\"10.1177/1087724X21990034\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"This study examines the causes of time delays and cost overruns in a selection of thirty post-disaster reconstruction projects in Iraq. Although delay factors have been studied in many countries and contexts, little data exists from countries under the conditions characterizing Iraq during the last 10-15 years. A case study approach was used, with thirty construction projects of different types and sizes selected from the Baghdad region. Project data was gathered from a survey which was used to build statistical relationships between time and cost delay ratios and delay factors in post disaster projects. The most important delay factors identified were contractor failure, redesigning of designs/plans and change orders, security issues, selection of low-price bids, weather factors, and owner failures. Some of these are in line with findings from similar studies in other countries and regions, but some are unique to the Iraqi project sample, such as security issues and low-price bid selection. While many studies have examined factors causing delays and cost overruns, this study offers unique insights into factors that need to be considered when implementing projects for post disaster emergency reconstruction in areas impacted by wars and terrorism.\",\"PeriodicalId\":45483,\"journal\":{\"name\":\"Public Works Management & Policy\",\"volume\":\"27 1\",\"pages\":\"61 - 97\"},\"PeriodicalIF\":1.0000,\"publicationDate\":\"2021-02-08\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"https://sci-hub-pdf.com/10.1177/1087724X21990034\",\"citationCount\":\"17\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Public Works Management & Policy\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.1177/1087724X21990034\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"Q3\",\"JCRName\":\"PUBLIC ADMINISTRATION\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Public Works Management & Policy","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1177/1087724X21990034","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"Q3","JCRName":"PUBLIC ADMINISTRATION","Score":null,"Total":0}
Causes of Problems in Post-Disaster Emergency Re-Construction Projects—Iraq as a Case Study
This study examines the causes of time delays and cost overruns in a selection of thirty post-disaster reconstruction projects in Iraq. Although delay factors have been studied in many countries and contexts, little data exists from countries under the conditions characterizing Iraq during the last 10-15 years. A case study approach was used, with thirty construction projects of different types and sizes selected from the Baghdad region. Project data was gathered from a survey which was used to build statistical relationships between time and cost delay ratios and delay factors in post disaster projects. The most important delay factors identified were contractor failure, redesigning of designs/plans and change orders, security issues, selection of low-price bids, weather factors, and owner failures. Some of these are in line with findings from similar studies in other countries and regions, but some are unique to the Iraqi project sample, such as security issues and low-price bid selection. While many studies have examined factors causing delays and cost overruns, this study offers unique insights into factors that need to be considered when implementing projects for post disaster emergency reconstruction in areas impacted by wars and terrorism.
期刊介绍:
PUBLIC WORKS MANAGEMENT & POLICY: RESEARCH AND PRACTICE IN TRANSPORTATION, INFRASTRUCTURE, AND THE ENVIRONMENT is a peer-reviewed journal for academics and practitioners in public works and the public and private infrastructure industries. This journal addresses the planning, financing, development, and operations of civil infrastructure systems at all levels of society— from federal policy to the demand for, and delivery of, state and local public works services. PWMP solicits manuscripts that convey research results, evaluate management innovations, suggest methods of analysis and evaluation, and examine policy issues.