{"title":"具有特定机器预防性维护的有序优先约束流水车间调度问题","authors":"T. J. Kumar, M. Thangaraj","doi":"10.5267/j.jpm.2022.8.002","DOIUrl":null,"url":null,"abstract":"In reality, the machines may interrupt because of the nature of deterioration of the machines. Thus, it is inevitable to perform maintenance alongside production planning. The preventive maintenance is a schedule of strategic operations that are performed prior to the failure occurring, to retain the system operating at the preferred level of consistency. Thus, preventive maintenance plays a significant role in flow shop scheduling models. With its practical significance, this study addresses a practical three-machine n jobs flow shop-scheduling problem (FSSP) in which machine specific preventive maintenance, where each machine is given with a maintenance schedule is considered. In addition, a practical ordered precedence constraint in which some set of jobs has to process in the specified order irrespective of their processing times is also considered. The problem’s goal is to establish the optimal job sequence and preventive maintenance such that the overall cost of tardiness and preventive maintenance is as minimum as possible. An efficient heuristic approach is designed to tackle the present model, resulting in total cost savings. A comparative analysis is not conducted due to absence of studies on the current problem in the literature. However, Computational experiments are carried out on some test instances and results are reported. The reported results may be useful for future studies.","PeriodicalId":42333,"journal":{"name":"Journal of Project Management","volume":null,"pages":null},"PeriodicalIF":1.3000,"publicationDate":"2023-01-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"3","resultStr":"{\"title\":\"An ordered precedence constrained flow shop scheduling problem with machine specific preventive maintenance\",\"authors\":\"T. J. Kumar, M. Thangaraj\",\"doi\":\"10.5267/j.jpm.2022.8.002\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"In reality, the machines may interrupt because of the nature of deterioration of the machines. Thus, it is inevitable to perform maintenance alongside production planning. The preventive maintenance is a schedule of strategic operations that are performed prior to the failure occurring, to retain the system operating at the preferred level of consistency. Thus, preventive maintenance plays a significant role in flow shop scheduling models. With its practical significance, this study addresses a practical three-machine n jobs flow shop-scheduling problem (FSSP) in which machine specific preventive maintenance, where each machine is given with a maintenance schedule is considered. In addition, a practical ordered precedence constraint in which some set of jobs has to process in the specified order irrespective of their processing times is also considered. The problem’s goal is to establish the optimal job sequence and preventive maintenance such that the overall cost of tardiness and preventive maintenance is as minimum as possible. An efficient heuristic approach is designed to tackle the present model, resulting in total cost savings. A comparative analysis is not conducted due to absence of studies on the current problem in the literature. However, Computational experiments are carried out on some test instances and results are reported. The reported results may be useful for future studies.\",\"PeriodicalId\":42333,\"journal\":{\"name\":\"Journal of Project Management\",\"volume\":null,\"pages\":null},\"PeriodicalIF\":1.3000,\"publicationDate\":\"2023-01-01\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"3\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Journal of Project Management\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.5267/j.jpm.2022.8.002\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"Q4\",\"JCRName\":\"ENGINEERING, INDUSTRIAL\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Journal of Project Management","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.5267/j.jpm.2022.8.002","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"Q4","JCRName":"ENGINEERING, INDUSTRIAL","Score":null,"Total":0}
An ordered precedence constrained flow shop scheduling problem with machine specific preventive maintenance
In reality, the machines may interrupt because of the nature of deterioration of the machines. Thus, it is inevitable to perform maintenance alongside production planning. The preventive maintenance is a schedule of strategic operations that are performed prior to the failure occurring, to retain the system operating at the preferred level of consistency. Thus, preventive maintenance plays a significant role in flow shop scheduling models. With its practical significance, this study addresses a practical three-machine n jobs flow shop-scheduling problem (FSSP) in which machine specific preventive maintenance, where each machine is given with a maintenance schedule is considered. In addition, a practical ordered precedence constraint in which some set of jobs has to process in the specified order irrespective of their processing times is also considered. The problem’s goal is to establish the optimal job sequence and preventive maintenance such that the overall cost of tardiness and preventive maintenance is as minimum as possible. An efficient heuristic approach is designed to tackle the present model, resulting in total cost savings. A comparative analysis is not conducted due to absence of studies on the current problem in the literature. However, Computational experiments are carried out on some test instances and results are reported. The reported results may be useful for future studies.