Anwar Widiyanto Nugroho, Tukiyo Tukiyo, Herman Fithra
{"title":"普罗嘉洞工程时间延误风险因素的识别","authors":"Anwar Widiyanto Nugroho, Tukiyo Tukiyo, Herman Fithra","doi":"10.52088/ijesty.v2i2.247","DOIUrl":null,"url":null,"abstract":"To provide livable housing for the residents of DKI Jakarta, especially in urban areas with minimal land availability, the DKI Jakarta Provincial Government supports the development of vertical housing to offset the high demand for housing and limited land. Through the Department of Public Housing and Settlement Areas, the Provincial Government of DKI Jakarta is implementing the Pulogadung-East Jakarta PIK Flats Construction Project. When this research was carried out, the Pulogadung-East Jakarta PIK Flats Construction Project was entering week 63, with work progress reaching 47.689% of the planned 48.725%, or in other words, this project experienced a delay of 1.036% of the scheduled. Therefore, it is necessary to conduct research that aims to identify the factors that cause the risk of time delays, analyze the most dominant factors that lead to the risk of time delays, and look for the necessary handling actions so that the risk of time delays that occur does not increase or can also be prevented or resolved. In this study, the descriptive quantitative method is carried out by surveys, interviews, and distributing questionnaires to respondents. The risk rating was analyzed using MS. Excel is based on a probability and impact matrix, which aims to determine variables with a high level of risk, then expert validation is carried out regarding risk management. And from the analysis results obtained, six variables that cause the risk of time delays in the Pulogadung-East Jakarta PIK Flats Development Project work can occur, namely Late Payment of Term by Owner, Design Changes, Lack of Coordination While Working, Inaccuracy of Material Order, Time, Limited Material Availability in the Market, and the Occurrence of the Corona Outbreak (Covid 19). The results of expert recommendations for the six variables can be expressed in handling actions.","PeriodicalId":14149,"journal":{"name":"International Journal of Engineering, Science and Information Technology","volume":"69 1","pages":""},"PeriodicalIF":0.0000,"publicationDate":"2022-04-30","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Identification of Factors Caused The Risk of Time Delays in The Pulogadung\",\"authors\":\"Anwar Widiyanto Nugroho, Tukiyo Tukiyo, Herman Fithra\",\"doi\":\"10.52088/ijesty.v2i2.247\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"To provide livable housing for the residents of DKI Jakarta, especially in urban areas with minimal land availability, the DKI Jakarta Provincial Government supports the development of vertical housing to offset the high demand for housing and limited land. Through the Department of Public Housing and Settlement Areas, the Provincial Government of DKI Jakarta is implementing the Pulogadung-East Jakarta PIK Flats Construction Project. When this research was carried out, the Pulogadung-East Jakarta PIK Flats Construction Project was entering week 63, with work progress reaching 47.689% of the planned 48.725%, or in other words, this project experienced a delay of 1.036% of the scheduled. Therefore, it is necessary to conduct research that aims to identify the factors that cause the risk of time delays, analyze the most dominant factors that lead to the risk of time delays, and look for the necessary handling actions so that the risk of time delays that occur does not increase or can also be prevented or resolved. In this study, the descriptive quantitative method is carried out by surveys, interviews, and distributing questionnaires to respondents. The risk rating was analyzed using MS. Excel is based on a probability and impact matrix, which aims to determine variables with a high level of risk, then expert validation is carried out regarding risk management. And from the analysis results obtained, six variables that cause the risk of time delays in the Pulogadung-East Jakarta PIK Flats Development Project work can occur, namely Late Payment of Term by Owner, Design Changes, Lack of Coordination While Working, Inaccuracy of Material Order, Time, Limited Material Availability in the Market, and the Occurrence of the Corona Outbreak (Covid 19). The results of expert recommendations for the six variables can be expressed in handling actions.\",\"PeriodicalId\":14149,\"journal\":{\"name\":\"International Journal of Engineering, Science and Information Technology\",\"volume\":\"69 1\",\"pages\":\"\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2022-04-30\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"International Journal of Engineering, Science and Information Technology\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.52088/ijesty.v2i2.247\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"International Journal of Engineering, Science and Information Technology","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.52088/ijesty.v2i2.247","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0
摘要
为了给雅加达DKI的居民提供宜居的住房,特别是在土地可用性最低的城市地区,雅加达DKI省政府支持垂直住房的发展,以抵消对住房的高需求和有限的土地。通过公共住房和住区部,雅加达DKI省政府正在实施普洛加东-东雅加达PIK公寓建设项目。当本研究进行时,Pulogadung-East Jakarta PIK Flats Construction Project进入第63周,工作进度达到了计划的48.725%的47.689%,换句话说,该项目经历了计划的1.036%的延迟。因此,有必要进行研究,找出造成时间延误风险的因素,分析导致时间延误风险的最主要因素,并寻找必要的处理措施,使发生的时间延误风险不增加或也可以预防或解决。在本研究中,描述性定量方法是通过调查,访谈,并向受访者发放问卷。MS. Excel基于概率和影响矩阵对风险等级进行分析,确定风险等级较高的变量,并对风险管理进行专家验证。从获得的分析结果来看,导致Pulogadung-East Jakarta PIK公寓开发项目工作出现时间延迟风险的六个变量可能发生,即业主逾期付款、设计变更、工作时缺乏协调、材料订单不准确、时间、市场上材料供应有限以及发生冠状病毒爆发(Covid - 19)。专家对这六个变量的建议结果可以用处理动作来表示。
Identification of Factors Caused The Risk of Time Delays in The Pulogadung
To provide livable housing for the residents of DKI Jakarta, especially in urban areas with minimal land availability, the DKI Jakarta Provincial Government supports the development of vertical housing to offset the high demand for housing and limited land. Through the Department of Public Housing and Settlement Areas, the Provincial Government of DKI Jakarta is implementing the Pulogadung-East Jakarta PIK Flats Construction Project. When this research was carried out, the Pulogadung-East Jakarta PIK Flats Construction Project was entering week 63, with work progress reaching 47.689% of the planned 48.725%, or in other words, this project experienced a delay of 1.036% of the scheduled. Therefore, it is necessary to conduct research that aims to identify the factors that cause the risk of time delays, analyze the most dominant factors that lead to the risk of time delays, and look for the necessary handling actions so that the risk of time delays that occur does not increase or can also be prevented or resolved. In this study, the descriptive quantitative method is carried out by surveys, interviews, and distributing questionnaires to respondents. The risk rating was analyzed using MS. Excel is based on a probability and impact matrix, which aims to determine variables with a high level of risk, then expert validation is carried out regarding risk management. And from the analysis results obtained, six variables that cause the risk of time delays in the Pulogadung-East Jakarta PIK Flats Development Project work can occur, namely Late Payment of Term by Owner, Design Changes, Lack of Coordination While Working, Inaccuracy of Material Order, Time, Limited Material Availability in the Market, and the Occurrence of the Corona Outbreak (Covid 19). The results of expert recommendations for the six variables can be expressed in handling actions.