利用控制图分析设计地面设施的最大允许成本:以印度尼西亚为例

Ahmad Abdul Azizurrofi, Edward Erwanto, A. Asnidar, Rikky Rahmat Firdaus
{"title":"利用控制图分析设计地面设施的最大允许成本:以印度尼西亚为例","authors":"Ahmad Abdul Azizurrofi, Edward Erwanto, A. Asnidar, Rikky Rahmat Firdaus","doi":"10.2118/197644-ms","DOIUrl":null,"url":null,"abstract":"\n During the period from 2005 to 2018, the oil prices had reached the highest level in 2008 (99.67 US$/bbl) and the lowest level in 2016 (43 US$/bbl). The fluctuation in oil prices will affects the cost of investment (drilling and surface facilities) worlwide. Based on this condition, the standardization of the Investment Cost is needed to help the government and contractor in estimating the cost of investment in an oil and gas project.\n As per December 2018, there were 471 projects approved by the government of Indonesia and the 266 of them are projects that producing oil (oil projects) and gas (gas projects). In these projects, there are details of investment costs that are included in the economic evaluation. This paper will calculate and produce the Maximum Allowable Cost (\"MAC\") of surface facilities per boe (US$/boe) based on statistical analysis of 266 projects. Hopefully, this method can be used as a reference (guidance) in giving approval for the cost of surface facilities and providing an overview to contractors regarding the estimated MAC of surface facilities in an oil and gas project.\n For the purpose of this paper is, to divide the areas of Indonesia into 2 areas (Onshore and Offshore) which in each of these areas has 2 different types of projects (oil project and gas project). Then, to collect the data that related to cost of surface facilities and reserves and then the MAC of surface facilities per boe are calculated and produced using the Control Chart Analysis method. Lastly, the result will be distributed to those aforementioned areas.\n Based on the analysis of 266 Projects in Indonesia, the MAC of surface facilities per boe in Onshore area are 20.80 US$/boe (oil project) and 18.59 US$/boe (gas project), while the MAC of surface facilities per boe in Offshore area are 14.32 US$/boe (oil project) and 27.62 US$/boe (gas projects). In general, the MAC of surface facilities per boe still far bellow the oil price.\n Finally, this paper will show how to produce MAC of surface facilities per boe by using control chart analysis. This paper also expected to provide references for the government of Indonesia in giving approval to the cost of surface facilities proposed by contractors and provide contractors a quick look at oil and gas industry in Indonesia especially to those who plan to invest in Indonesia, and also help them create their petroleum exploration and exploitation strategy in Indonesia by considering on this information that will provide benefits for both government and contractor.","PeriodicalId":11091,"journal":{"name":"Day 3 Wed, November 13, 2019","volume":null,"pages":null},"PeriodicalIF":0.0000,"publicationDate":"2019-11-11","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Designing the Maximum Allowable Cost of Surface Facilities Using the Control Chart Analysis: A Case Study in Indonesia\",\"authors\":\"Ahmad Abdul Azizurrofi, Edward Erwanto, A. Asnidar, Rikky Rahmat Firdaus\",\"doi\":\"10.2118/197644-ms\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"\\n During the period from 2005 to 2018, the oil prices had reached the highest level in 2008 (99.67 US$/bbl) and the lowest level in 2016 (43 US$/bbl). The fluctuation in oil prices will affects the cost of investment (drilling and surface facilities) worlwide. Based on this condition, the standardization of the Investment Cost is needed to help the government and contractor in estimating the cost of investment in an oil and gas project.\\n As per December 2018, there were 471 projects approved by the government of Indonesia and the 266 of them are projects that producing oil (oil projects) and gas (gas projects). In these projects, there are details of investment costs that are included in the economic evaluation. This paper will calculate and produce the Maximum Allowable Cost (\\\"MAC\\\") of surface facilities per boe (US$/boe) based on statistical analysis of 266 projects. Hopefully, this method can be used as a reference (guidance) in giving approval for the cost of surface facilities and providing an overview to contractors regarding the estimated MAC of surface facilities in an oil and gas project.\\n For the purpose of this paper is, to divide the areas of Indonesia into 2 areas (Onshore and Offshore) which in each of these areas has 2 different types of projects (oil project and gas project). Then, to collect the data that related to cost of surface facilities and reserves and then the MAC of surface facilities per boe are calculated and produced using the Control Chart Analysis method. Lastly, the result will be distributed to those aforementioned areas.\\n Based on the analysis of 266 Projects in Indonesia, the MAC of surface facilities per boe in Onshore area are 20.80 US$/boe (oil project) and 18.59 US$/boe (gas project), while the MAC of surface facilities per boe in Offshore area are 14.32 US$/boe (oil project) and 27.62 US$/boe (gas projects). In general, the MAC of surface facilities per boe still far bellow the oil price.\\n Finally, this paper will show how to produce MAC of surface facilities per boe by using control chart analysis. This paper also expected to provide references for the government of Indonesia in giving approval to the cost of surface facilities proposed by contractors and provide contractors a quick look at oil and gas industry in Indonesia especially to those who plan to invest in Indonesia, and also help them create their petroleum exploration and exploitation strategy in Indonesia by considering on this information that will provide benefits for both government and contractor.\",\"PeriodicalId\":11091,\"journal\":{\"name\":\"Day 3 Wed, November 13, 2019\",\"volume\":null,\"pages\":null},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2019-11-11\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Day 3 Wed, November 13, 2019\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.2118/197644-ms\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Day 3 Wed, November 13, 2019","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.2118/197644-ms","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

摘要

2005年至2018年期间,油价在2008年达到最高水平(99.67美元/桶),在2016年达到最低水平(43美元/桶)。石油价格的波动将影响全球的投资成本(钻井和地面设施)。在这种情况下,需要投资成本的标准化来帮助政府和承包商估算油气项目的投资成本。截至2018年12月,印度尼西亚政府批准了471个项目,其中266个是生产石油(石油项目)和天然气(天然气项目)的项目。在这些项目中,有详细的投资成本,包括在经济评价中。本文将根据266个项目的统计分析,计算并得出地面设施每桶油当量的最大允许成本(MAC) (US$/boe)。希望这种方法可以作为批准地面设施成本的参考(指导),并为承包商提供有关石油和天然气项目中地面设施的估计MAC的概述。本文的目的是,将印度尼西亚的区域划分为2个区域(陆上和海上),其中每个区域都有2种不同类型的项目(石油项目和天然气项目)。然后,收集与地面设施成本和储量相关的数据,利用控制图分析法计算并生成每桶油当量地面设施的MAC。最后,将结果分发到上述地区。通过对印尼266个项目的分析,发现陆上区域地面设施的MAC为20.80美元/桶(石油项目)和18.59美元/桶(天然气项目),而海上区域地面设施的MAC为14.32美元/桶(石油项目)和27.62美元/桶(天然气项目)。一般来说,地面设施每桶油当量的MAC仍远低于油价。最后,本文将展示如何使用控制图分析来生成地面设施的MAC。本文还希望为印度尼西亚政府批准承包商提出的地面设施成本提供参考,并为承包商提供印度尼西亚石油和天然气行业的快速了解,特别是那些计划在印度尼西亚投资的承包商,并帮助他们通过考虑这些信息来制定他们在印度尼西亚的石油勘探和开发战略,这将为政府和承包商提供利益。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
查看原文
分享 分享
微信好友 朋友圈 QQ好友 复制链接
本刊更多论文
Designing the Maximum Allowable Cost of Surface Facilities Using the Control Chart Analysis: A Case Study in Indonesia
During the period from 2005 to 2018, the oil prices had reached the highest level in 2008 (99.67 US$/bbl) and the lowest level in 2016 (43 US$/bbl). The fluctuation in oil prices will affects the cost of investment (drilling and surface facilities) worlwide. Based on this condition, the standardization of the Investment Cost is needed to help the government and contractor in estimating the cost of investment in an oil and gas project. As per December 2018, there were 471 projects approved by the government of Indonesia and the 266 of them are projects that producing oil (oil projects) and gas (gas projects). In these projects, there are details of investment costs that are included in the economic evaluation. This paper will calculate and produce the Maximum Allowable Cost ("MAC") of surface facilities per boe (US$/boe) based on statistical analysis of 266 projects. Hopefully, this method can be used as a reference (guidance) in giving approval for the cost of surface facilities and providing an overview to contractors regarding the estimated MAC of surface facilities in an oil and gas project. For the purpose of this paper is, to divide the areas of Indonesia into 2 areas (Onshore and Offshore) which in each of these areas has 2 different types of projects (oil project and gas project). Then, to collect the data that related to cost of surface facilities and reserves and then the MAC of surface facilities per boe are calculated and produced using the Control Chart Analysis method. Lastly, the result will be distributed to those aforementioned areas. Based on the analysis of 266 Projects in Indonesia, the MAC of surface facilities per boe in Onshore area are 20.80 US$/boe (oil project) and 18.59 US$/boe (gas project), while the MAC of surface facilities per boe in Offshore area are 14.32 US$/boe (oil project) and 27.62 US$/boe (gas projects). In general, the MAC of surface facilities per boe still far bellow the oil price. Finally, this paper will show how to produce MAC of surface facilities per boe by using control chart analysis. This paper also expected to provide references for the government of Indonesia in giving approval to the cost of surface facilities proposed by contractors and provide contractors a quick look at oil and gas industry in Indonesia especially to those who plan to invest in Indonesia, and also help them create their petroleum exploration and exploitation strategy in Indonesia by considering on this information that will provide benefits for both government and contractor.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
期刊最新文献
Treatment of Produced Water with Back Produced ASP Using Analytics to Assess Health Status of DLE Combustion Gas Turbines Design of Economical Polymer and Surfactant-Polymer Processes in High Temperature Carbonated Um Gudair Kuwaiti Field. Enhancement of Routine Data Acquisition in a Giant Offshore Brownfield by Bridging Gaps Identified Through Comprehensive Data Analysis Applying Brain Science to Achieve Organizational Success
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
现在去查看 取消
×
提示
确定
0
微信
客服QQ
Book学术公众号 扫码关注我们
反馈
×
意见反馈
请填写您的意见或建议
请填写您的手机或邮箱
已复制链接
已复制链接
快去分享给好友吧!
我知道了
×
扫码分享
扫码分享
Book学术官方微信
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术
文献互助 智能选刊 最新文献 互助须知 联系我们:info@booksci.cn
Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。
Copyright © 2023 Book学术 All rights reserved.
ghs 京公网安备 11010802042870号 京ICP备2023020795号-1